2019 Data Center Giants Report: AEC firms stretch to keep up with data center demand

Giants 400

2019 Data Center Giants Report: AEC firms stretch to keep up with data center demand

This and more data center sector trends from Building Design+Construction's 2019 Giants 300 Report. 


By John Caulfield, Senior Editor  | August 28, 2019
2019 Data Center Giants Report DPR - Digital realty Ashburn, Va Photo Ulf Wallin

Last January, Digital Realty opened a 230,000-sf data center in Ashburn, Va., one of this sector’s most robust zones. Built by DPR Construction using concrete tilt-up panels, this was the Digital Realty’s first deployment of its mega-scale prototype, and the time from groundbreaking to IST/Occupancy took only eight months. Phase 1 includes a 6-MW data hall, the first of six halls with equal critical power planned over the data center’s three-year buildout period. Photo: Ulf Wallin

  

In 2018, Holder Construction did $1.38 billion in data center construction. As of May 2019, it had 28 data center projects in the works, and the firm expects construction this year to approach $3 billion. One such project—in Phoenix, for a large REIT—opened in July 2019 with 6 MW of processing capacity, and will reach 48 MW when it’s eventually built out to around 500,000 sf.

To keep pace with this sector’s expansion, Holder is increasing its headcount by 25%. “The AEC industry is very close to being overwhelmed by data center demand, especially for electricians,” says Tony TeVault, Vice President with Holder’s office in Atlanta. “Every market is at full capacity and equipment vendors are super-stretched.”

Data center sector growth is creating opportunities for AEC firms, as owners scramble to build facilities as fast as they can. “Speed to market” is this sector’s abiding objective, in part to accommodate looming 5G technology.

 

ALSO SEE: Top 35 Data Center Architecture Firms
ALSO SEE: Top 50 Data Center Engineering Firms
ALSO SEE: Top 45 Data Center Construction Firms

 

“As soon as a client receives a positive capacity demand signal in a region, the race is on to design and build a data center at rapid pace,” says James Coe, PE, Senior Principal with Syska Hennessy, whom BD+C interviewed with Joshua Fluecke, PE, LEED AP, Associate Principal. They note that engineering design teams are under pressure to adapt a provider’s prescriptive design within an eight- to 12-week window, and to offer construction administration support for an accelerated build schedule that typically falls between seven and nine months.

“Contractors need to use every tool at their disposal to ensure just-in-time delivery of materials and methods like prefabrication to shorten schedules,” says John Arcello, Advanced Tech Core Market Co-Leader with DPR Construction. “The magic will happen in the planning stages: preconstruction and VDC services have the tools to drive the process,” especially in design-build collaborations that he says are more common within this sector.

Another “tool” some AEC firms have availed themselves of is the acquisition of talent and market share to serve a consolidating sector with fewer and bigger players. Last December, the engineering firm Morrison Hershfield merged with CCG Facilities, a mission-critical engineering firm. And last March, HED joined forces with the data-center specialty firm IDG.

 

Hyperscale and edge data center facilities prevail

The sector is polarized between two dominant building types: massive hyperscale facilities and much smaller data centers for edge computing, which are usually located near population centers to ensure smooth content delivery.

Hyperscale data centers are simply getting bigger. Robert Sty, PE, LEED AP, Director of the Tech Sector for HDR, says that it wasn’t too long ago when data centers with 20 MW of capacity were considered large. Now, hyperscale campuses are being planned for 200 to 300 MW of power and millions of square feet. Gary Murphy, a Principal with HED, says data centers are being designed for 500+ MW. “Data centers are becoming more industrialized: as demand grows, so does their scale and performance.”

Water cooling for cabinets is becoming more prevalent, as owners push the envelope on higher allowable temperatures to lower their operational costs. Terence Deneny, Vice President of Structure Tone’s Mission Critical division, has seen some users locate IT racks in parking lots to test equipment tolerances and take advantage of free air cooling. Matt Lamont, HKS’s Vice President and Mission Critical Team Leader–America West Region, adds that a key discussion among clients revolves around driving the power usage effectiveness (PUE) ratio—the power entering the data center over the power used—to sub 1.15 levels.

These hyperscale facilities put pressure on local utilities to provide the power, water, and industrial wastewater required for their operations, says Ken Gilmartin, Jacobs’ Senior Vice President and GM–Advanced Facilities and Federal Solutions.

For one client, construction engineer McKinstry led the testing of four different power generation solutions within a live data center to determine the best solution for a rollout across multiple locations. (The client chose natural gas.) Dan Ronco, McKinstry’s Director of Electrical Construction, adds that more clients are considering renewable energy sources. He cautions, however, that “the hard part is making intermittent renewables work in critical, always-on environments.”

Edge computing facilities support the market’s time-critical functions (e.g., streaming). Coe of Syska Hennessy has seen micro data centers as small as one cabinet within a facility to 150 kW self-contained modular buildings. HKS’s Lamont says that the “maximum load” of edge centers his firm has worked on has been 1,000 kW, and they often run without human personnel.

“These types of facilities must be approached as a product design, and not as a custom solution for each location,” says Bruce Edwards, RA, a Principal with Morrison Hershfield. He elaborates that because edge data centers are pretty similar, their standardized design and construction lend themselves to prefabrication or modular options.

“Prefabrication and modular construction for data centers is becoming more consistent and reliable,” says Annette Allen, Fluor’s Vice President, Business Development–Life Sciences and Advanced Manufacturing. “They can reduce the amount of engineering required, and drive capital efficiencies, meaning cost and scheduling certainty.”

 

MORE FROM BD+C'S 2019 GIANTS 300 REPORT

Tags

Related Stories

| Jul 26, 2016

ARCHITECTURE GIANTS: Innovations from 51 top design firms

Check out what these 50 design firms are doing to stay ahead of the pack.

| Jul 26, 2016

Top 80 Architecture/Engineering firms

Stantec, HOK, and Callison RTKL once again top Building Design+Construction's 2016 ranking of the largest architecture/engineering firms in the United States. 

| Jul 25, 2016

Top 55 Engineering Companies

WSP | Parsons Brinckerhoff, Fluor, and Arup top Building Design+Construction's 2016 ranking of the largest engineering firms in the United States.   

| Jul 25, 2016

Top 35 Engineering/Architecture Firms

AECOM, Jacobs, and Thornton Tomasetti head Building Design+Construction's 2016 ranking of the largest engineering/architecture firms in the United States. 

| Jul 25, 2016

Top 100 Architecture Firms

Gensler surpasses $1.1 billion in revenue, topping Building Design+Construction’s annual ranking of the nation’s largest architecture firms, as reported in the 2016 Giants 300 Report.

| Jul 19, 2016

2016 GIANTS 300 REPORT: Ranking the nation's largest architecture, engineering, and construction firms

Now in its 40th year, BD+C’s annual Giants 300 report ranks AEC firms by discipline and across more than 20 building sectors and specialty services.

Giants 400 | Jan 29, 2016

TRANSIT SECTOR GIANTS: Perkins+Will, Skanska among top transit/TOD facility AEC firms

BD+C's rankings of the nation's largest transit/TOD sector design and construction firms, as reported in the 2015 Giants 300 Report 

Giants 400 | Jan 29, 2016

AIRPORT TERMINAL GIANTS: KPF, Jacobs, Hensel Phelps among top airport sector AEC firms

BD+C's rankings of the nation's largest airport sector design and construction firms, as reported in the 2015 Giants 300 Report 

Giants 400 | Jan 29, 2016

SPORTS FACILITIES GIANTS: Populous, AECOM, Turner among top sports sector AEC firms

BD+C's rankings of the nation's largest sports sector design and construction firms, as reported in the 2015 Giants 300 Report 

Giants 400 | Sep 30, 2015

SCIENCE + TECHNOLOGY SECTOR GIANTS: HDR, Jensen Hughes, Skanska top S+T firm rankings

BD+C's rankings of the nation's largest S+T sector design and construction firms, as reported in the 2015 Giants 300 Report.

boombox1
boombox2
native1

More In Category




Giants 400

Call for surveys: 2024 Giants 400 Report

Building Design+Construction's annual Giants 400 Report ranks the nation's top architecture, architecture/engineering (AE), engineering/architecture (EA), general contractors, and fee-based construction management (CM) firms, by revenue. You’ll want to be sure your firm is on the Giants 400 lists, as potential clients look to these rankings for prospective firms to design and construct their future projects.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021