5 Tips on Building with SIPs

5 Tips on Building with SIPs

Structural insulated panels are gaining the attention of Building Teams interested in achieving high-performance building envelopes in commercial, industrial, and institutional projects.


December 17, 2010
This article first appeared in the December 2010 issue of BD+C.

Typically composed of a layer of EPS, XPS, or polyurethane foam sandwiched between oriented strand board panels, structural insulated panels can provide R-values for walls, floors, and roofs ranging from 14 to 58, depending on the panel thickness and composition. SIPs also are manufactured to spec, which can result in reduced waste and potential labor savings.

First-time users may find working with SIPs somewhat worrisome, so we asked Frank Kiesecker, of SIP manufacturer ACH Foam Technologies, Denver, to provide some prescriptive advice that even experienced SIP users could benefit from.

1. Pre-plan electrical and equipment needs. Since SIPs are manufactured to meet the project’s specifications, it’s important to plan for electrical chases in advance to prevent time-consuming and sometimes costly modifications during installation. For example, SIP facings should never be cut horizontally for the installation of electrical wiring; doing so will compromise structural performance.

In addition, during the design phase, it’s important to determine whether there are any equipment needs for the installation of the panels. If the project specifies roof panels or wall or floor panels larger than 8x8 feet, a forklift or crane may be required for installation.

2. Organize the panels for installation. Proper storage, weather protection, and handling will make the installation process more efficient. Store the panels on a level space, no closer than three inches to the ground. Organize the panels by the sequence in which they will be installed (i.e., separate the first-floor panels from the second-floor ones), and make sure they’re covered with a breathable protective tarp to keep them dry.

3. Install the panels properly and seal them tight. SIPs need to be fully supported during installation. The panels slip over a wall plate, which needs to be set half an inch from the building edge to ensure that the panels are fully supported. Also, make sure to set the panels in place in the correct order: start in the corners or valleys and work outward. Once installed, all panel joints and voids must be properly sealed using adhesive or SIP tape to minimize air leakage and maintain the structure’s long-term durability.

4. Protect SIPs from water penetration. Once SIPs have been installed and sealed, weather protection such as housewrap is required to prevent moisture deterioration. Follow the housewrap manufacturer’s installation guidelines, and make sure to flash all penetrations. Over time, windows will leak some water at the sill. Use flashing under and around the units to direct water away from the wall structure.

5. Right-size your HVAC system. One common mistake, says Kiesecker, is underestimating the high insulating and air-sealing properties of SIPs when selecting an HVAC system. SIPs allow for smaller HVAC equipment. When working with an HVAC contractor, make sure they take into account an estimate for lower levels of air infiltration. Proper HVAC sizing is critical because an underused system will fail to reach a steady operating rate, resulting in short cycling, which is less energy efficient and requires more maintenance.

Other important factors to consider when determining HVAC sizing:

  • Size of the structure (each floor should be analyzed individually)
  • Orientation of building
  • Type of wall construction, and associated R-value
  • Window and door specs, including the number of windows and doors and their location, insulation value, and fenestration rating
  • Duct location (i.e., in heated space, unheated space, attic, crawl space, etc.)
  • Amount of air infiltration.

SIPs Do’s and Don’ts

  • Do provide adequate support for SIPs when storing them. SIPs should be stored flat and covered.
  • Do study installation drawings before setting panels.
  • Do remove debris from the plate area prior to panel placement.
  • Do provide level and square foundations or floors that support SIP walls.
  • Do provide adequate bracing of panels during erection.
  • Do hold the sill plate back from edge of floor system a half-inch to allow full bearing of SIP OSB facings.
  • Do provide 1½-inch-diameter access holes in plating to align with electrical wire chases in SIPs.
  • Do store sealant and SIP tape in a warm area for best application results in cold weather.
  • Do follow the manufacturer’s recommended joint sealing techniques.
  • Do place sealant along the leading edge of wood being inset into the panel.
  • Do use sealant on wood-to-wood, wood-to-EPS, and EPS-to-EPS connections.
  • Do use SIP tape or equivalent vapor retarder on roof panel joints.
  • Do install proper flashing and sealants around all rough openings and penetrations, as required.
  • Do use only continuous 2Xs, I-beams, and insulated I-beams for spline connections.
  • Do use proper underlayments for roofing and siding. SIP walls are airtight without housewrap, but they do need a drainage plane material.
  • Do install plumbing in interior walls. Furr out interior sections for pipes if necessary.
  • Do provide adequate ventilation to maintain indoor air quality.
  • Do use termite- and mold-resistant materials when required.
  • Don’t leave panels exposed to the elements for long periods of time.
  • Don’t lift SIPs by the top OSB facing or drop SIPs on corners.
  • Don’t install SIPs directly on concrete.
  • Don’t cut wall panel skins horizontally for installation of electrical wiring or overcut the OSB facings for field-cut openings. Use factory-provided chases in SIP core.
  • Don’t be afraid to field trim panels for an exact fit.
  • Don’t install recessed lighting inside the panels.
  • Don’t put plumbing in SIPs.

Related Stories

| Jan 31, 2012

Fusion Facilities: 8 reasons to consolidate multiple functions under one roof

‘Fusing’ multiple functions into a single building can make it greater than the sum of its parts. The first in a series  on the design and construction of university facilities.

| Jan 31, 2012

Suffolk Construction to manage Lawrence & Memorial Hospital Cancer Center project in Waterford, Conn.

Leading construction management firm overseeing one of first healthcare projects in the country to utilize innovative IPD process.

| Jan 31, 2012

Perkins Eastman’s Miller appointed Chairman of the AIA International Committee

International expertise leveraged as global industry resource.

| Jan 31, 2012

KBE selected for school project in Waterbury, Conn.

Located adjacent to the existing elementary school, the $28 million, 82,000 s/f Pre-K to eighth Grade school is expected to host its first students in the fall of 2013.

| Jan 31, 2012

Construction Law Firm Allensworth & Porter, LLP adds May to the firm

Prior to joining Allensworth & Porter, May served as the staff attorney for the Texas Civil Justice League, and was responsible for drafting, analyzing, and tracking civil justice and business-related legislation during the 82nd Legislative Session. 

| Jan 31, 2012

Skanska USA Civil promotes Bradley to southeast general superintendent

In Bradley’s new position, he will manage field operations for all Skanska Civil projects in the southeast.

| Jan 30, 2012

Siemens and Air-Ex Team deliver building controls training to Mt. San Antonio College students

Siemens contributes training modules and technology to support hands-on courses.

| Jan 30, 2012

Hollister Construction Services to renovate 30 Montgomery Street in Jersey City, N.J.

Owner Onyx Equities hires firm to oversee comprehensive upgrades of office building.

| Jan 27, 2012

Caterpillar reports record sales and profit for 4Q and full-year 2011

Momentum carries into 2012 with sales and revenues outlook raised to $68 to $72 billion.

| Jan 27, 2012

Smith Seckman Reid opens two new offices

Smith Seckman Reid, Inc. (SSR), an engineering design and facility consulting firm, has opened two new offices, one in Chicago, the other in Washington, D.C.

boombox1
boombox2
native1

More In Category


Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.



Libraries

Reasons to reinvent the Midcentury academic library

DLR Group's Interior Design Leader Gretchen Holy, Assoc. IIDA, shares the idea that a designer's responsibility to embrace a library’s history, respect its past, and create an environment that will serve student populations for the next 100 years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021