Addressing client concerns about design-assist

Building Team

Addressing client concerns about design-assist

Common concerns about DA include lack of familiarity, obtaining competitive pricing, and design liability.


By Tom Garske, Jennifer Horvath, Ed Keener, Stephen Metz, Jeff Ortman, Randy Sleeper, Kurt Smith, and Monica Wangler | Ohio Construction Transformation Consortium | July 11, 2016

Construction in Miami in July 2016. Photo: Phillip Pessar/Creative Commons.

Design-assist is not without potential drawbacks. Here are some common concerns—and how your Building Team can reassure clients that DA is worth considering.

OWNER CONCERN: Lack of familiarity with design-assist. DA is a relatively new delivery model. Architects and CMs may have a tendency to revert back to traditional roles.

PLAN OF ACTION: Although the DA process produces a more efficient, collaborative design process, care must be taken to ensure that the collaborative process continues throughout construction. During construction, there are inevitable owner concerns. That’s why it’s important to have established a process to address these changes. The collaborative process can be used to resolve challenges in a quick, cost-effective manner.

OWNER CONCERN: Subcontract administration. The subcontractor might not perform as expected or fall out of line with the budget.

PLAN OF ACTION: It is important to administer a preconstruction contract with the DA subcontractor, which allows the owner to terminate the agreement at any time prior to construction. This acts as a safeguard when a subcontractor’s pricing is not in line with the budget, and there is no reasonable way to get to the budget; in such a case, the owner would have reasonable cause to terminate the subcontractor’s contract. In this situation the trade package would need to be bid, which could push back the schedule depending on the selection process.

OWNER CONCERN: Obtaining competitive pricing. Some owners believe early involvement with subcontractors and the construction manager in the project precludes them from receiving competitive bids.

PLAN OF ACTION: Because the construction team is hired early in the design phase, the Building Team can obtain benchmark prices during the programming phase, making competitive pricing feasible. The Building Team can also obtain nonbinding preliminary price proposals during the DA selection process based on initial plans, such as schematic drawings; binding final prices can be submitted upon completion of the plans.

OWNER CONCERN: Added costs of the DA process. Design-assist may add time and cost to the design phase of the project due to additional collaboration with subcontractors and added time to procure services.

PLAN OF ACTION: The reductions achieved in construction cost and schedule should offset additional costs during the design phases, making design-assist advantageous overall.

OWNER CONCERN: Design liability. Greater collaboration among the architect, engineer, subcontractors, and construction manager might raise questions about who has responsibilities and design liability throughout the process.

PLAN OF ACTION: The project team should clearly set obligations and liabilities of the team members with respect to plans, specifications, and the building information model (if applicable) to overcome this concern. You should also develop a design-assist execution plan to identify roles, responsibilities, and deliverables for all team members.

Related Stories

Multifamily Housing | Mar 18, 2015

Prefabricated skycubes proposed with 'elastic' living apartments inside

The interiors for each unit are designed using an elastic living concept, where different spaces are created by sliding on tracks.

Sponsored | | Mar 17, 2015

Are face-to-face meetings still important?

One CEO looks pass convenience and advocates for old school, in-person meetings.

Resort Design | Mar 16, 2015

Giancarlo Zema Design Group unveils plans for semi-submerged resort in Qatar

The resort will have four semi-submerged hotels that look similar to super-yachts, each including 75 luxury suites with private terraces.

Mixed-Use | Mar 13, 2015

Dubai announces mega waterfront development Aladdin City

Planned on 4,000 acres in the Dubai Creek area, the towers will be covered in gold lattice and connected via air-conditioned bridges.

Contractors | Mar 13, 2015

Construction materials prices rise for first time in six months

The largest monthly gain in petroleum prices in over three years caused construction materials prices to expand 0.4% in February, ending a six-month streak when prices failed to rise, according to the Bureau of Labor Statistics.

High-rise Construction | Mar 12, 2015

Foster and Partners designs 'The One' in Toronto

Developer Sam Mizrahi worked with Foster and Partners and Core Architects to design Toronto's tallest skyscraper aside from the CN Tower, The One, which will house a luxury shopping mall and condos.

Contractors | Mar 12, 2015

Construction demand exploding in 2015, but costs complicate recovery

Raw materials and labor costs temper expectations for soaring profits.

Modular Building | Mar 10, 2015

Must see: 57-story modular skyscraper was completed in 19 days

After erecting the mega prefab tower in Changsha, China, modular builder BSB stated, “three floors in a day is China’s new normal.”

Sponsored | Metals | Mar 10, 2015

Metal Building Systems: A Rising Star in the Market

A new report by the Metal Building Manufacturer's Association explains the entity's efforts in refining and extending metal building systems as a construction choice.

Retail Centers | Mar 10, 2015

Retrofit projects give dying malls new purpose

Approximately one-third of the country’s 1,200 enclosed malls are dead or dying. The good news is that a sizable portion of that building stock is being repurposed.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021