But poorly written and administered contracts are still problems, says latest Arcadis report.


By John Caulfield, Senior Editor | June 26, 2017

The value and lengths of construction disputes declined globally in 2016, according to the latest report based on disputes handled by Arcadis' Contract Solutions team. Image: Pixabay

The resolution of global construction disputes remained steady in 2016, and the average time it took to resolve those disputes declined  bit, according to the seventh annual Arcadis Global Construction Disputes Report 2017, which is subtitled “Avoiding the Same Pitfalls.”

This report reflects the construction disputes that Arcadis’ team handled around the world. The report infers that the roadblocks to expeditious and less cost dispute resolution often stem from the need for better contract administration, robust documentation, and a proactive approach to risk management.

“Our industry contains the best problem solvers in the world,” the report states. “But there often seems to be a lack of ability or willingness of the project participants to compromise and resolve disputes at the earliest and most inexpensive stage possible.” Roy Cooper, Senior Vice President of Arcadis Contract Solutions, attributes disputes to “human emotions that can impede settlements, as they do with physical factors such as differing site conditions and design errors.”

The world’s economic expansion generally is not seen as an impediment to resolving contract disputes. Global growth is projected at 3.5% in 2017, and 3.6% in 2018, according to the International Monetary Fund. 

While the outlook is positive, the report sees risks in labor contraction, increasing commodities prices, and uncertain immigration policies. “A potential widening of global imbalances, coupled with sharp currency exchange rate movements, should those occur in response to major policy shifts, could further intensify protectionist pressures.”

 

A summary of Arcadis' findings for 2016. Image: Arcadis US

 

That being said, the global average construction dispute value declined in 2016 by nearly 7% to US$42.8 million (and that includes one US$2 billion dispute Arcadis handled). Asia averaged the highest dispute value, at US$84 million, and the United Kingdom saw a double-digit increase in its average dispute value, to US$34 million.

The global average length of a dispute also fell slightly last year, to 14 months. North America’s dispute duration was the longest of all Arcadis’ regions, an average of 15.6 months. For the third consecutive year, the most common cause for disputes in North America in 2016 was errors and/or omissions in the contract documentation.

 

 

Asia had the highest average dispute value last year; North America the longest time it took to resolve a dispute. Image: Arcadis

Globally, Arcadis identifies failure to properly administer a contract among the five most common causes of disputes, along with poorly drafted or incomplete/unsubstantiated claims; the failure of an employer, contractor or subcontractor to understand or comply with its contractual obligations; errors and omissions in the contract; and incomplete design information or employer requires.

The most common methods to resolve construction disputes were, in order of preference, party-to-party negotiation, arbitration, and mediation.

And the most important activities to avoid disputes were led by proper contract administration, accurate documents, and fair and appropriate risk and balances in contracts.

Related Stories

Market Data | Jul 21, 2020

7 must reads for the AEC industry today: July 21, 2020

Abandoned high-rise becomes mixed-use luxury apartments and researchers are developing anti-coronavirus tech for buildings.

Market Data | Jul 20, 2020

Construction employment rises from May to June in 31 states, slips in 18

Recent data from Procore on jobsite workers’ hours indicates employment may have leveled off.

Market Data | Jul 20, 2020

6 must reads for the AEC industry today: July 20, 2020

Never waste a crisis and robotic parking systems help developers optimize parking amenities.

Market Data | Jul 17, 2020

7 must reads for the AEC industry today: July 17, 2020

Kennedy Middle School's new Administration/Family Center and Tips to make optimal use of salvaged materials.

Market Data | Jul 16, 2020

Final NEPA rule will make it easier to rebuild infrastructure, reinvigorate the economy, and continue protecting the environment

Administration’s final reforms to the federal environmental review process fix problems with prior process, maintain environmental rigor, and accelerate needed infrastructure improvements.

Market Data | Jul 16, 2020

5 must reads for the AEC industry today: July 16, 2020

1928 hotel reimagined as a new resiential and cultural hub and Walgreens plans hundreds of doctor's offices at its stores.

Market Data | Jul 10, 2020

5 must reads for the AEC industry today: July 10, 2020

The world's tallest hybrid timber tower and the Florida Gators have a new $65 million ballpark.

Market Data | Jul 9, 2020

6 must reads for the AEC industry today: July 9, 2020

The world's most sustainable furniture factory and what will construction look like when COVID-19 ends?

Market Data | Jul 8, 2020

North America’s construction output to fall by 6.5% in 2020, says GlobalData

Even though all construction activities have been allowed to continue in most parts of the US and Canada since the start of the COVID-19 pandemic, many projects in the bidding or final planning stages have been delayed or canceled.

Market Data | Jul 8, 2020

5 must reads for the AEC industry today: July 8, 2020

AEMSEN develops concept for sustainable urban living and nonresidential construction has recovered 56% of jobs lost since March.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021