flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

Design-build delivery is setting new parameters for project management

Building Team

Design-build delivery is setting new parameters for project management

FMI paper provides clues to what makes these contracts click (or not).


By John Caulfield, Senior Editor | January 4, 2019

Design-build, especially as part of P3 agreements, is steadily becoming the preferred contractual delivery method for nonresidential construction. Image: FMI

More owners and developers are latching onto design-build as a preferred delivery method for projects large and small. And a new paper from FMI, the construction management consultant and investment banking firm, outlines how AEC firms and their clients that enter into such contracts are avoiding stress points that often bog down construction.

Drawing on FMI’s “2018 Design-Build Utilization” report, “the paper, “The Growing World of Design-Build,” written by FMI senior consultant Paul Trombitas, estimates that design-build project delivery will increase by 18% between 2018 and 2021, and comprise 44% of total construction spending, or the equivalent of $1.19 trillion over that four-year span.  

A sustained emphasis toward educating owners and project stakeholders on the process and benefits associated with design-build has facilitated continued adoption and greater utilization industrywide. On the public side, increased design-build legislation has helped push the adoption of such projects. On the private side, owners tend to select design-build for unique and challenging projects that require lots of collaboration.

Design-build is projected to account for 44% of all construction spending for the years 2018 through 2021. Image: FMI

 

Of the various customer segments that use design-build, manufacturing, road infrastructure, and education will represent the greatest percentage of design-build construction spending over the next three years, states FMI.

In addition to larger and more complex projects, design-build continues to expand into project sizes of less than $25 million, as owners continue to gain exposure to the benefits of the delivery method.

However, design-build has its own set of challenges that, according to FMI principal Bill Spragins, revolve around the differing roles assumed by the parties, the number of decisions that must be made simultaneously, and the increased speed of decision-making associated with compression of the design and construction cycle.

For example, a project is potentially set up fail when owners confine their use of this delivery method to procurement without aligning the decision-making and approval processes within the organization to meet scheduling needs. A project can also be derailed by misaligned expectations between the owner and design-builder regarding the level of control that the owner’s team retains over design decisions.

Consequently, for a design-build delivery method to work, specific parameters need to be established about project scope, scheduling, and who’s responsible for what.

FMI states that AEC firms looking to win design-build projects need to think strategically: What slices of the market are they targeting, who are the right customers, what services do they need, and how do these offerings set a firm apart from its competition?

 

FMI recommends that AEC firms take a customer-focused approach when trying to win design-build contracts. Image: FMI

 

FMI uses a “4C model” to illustrate the context of profitable growth. Its starts with defining the business “climate” that the AEC firm is operating in—from demographics to regulations—and then digging deeper into possible changes, expectations, and needs of customers

AEC firms need to find out what criteria owners use to select contractors. They also need to weigh their own strengths and weaknesses against competitors’ for a given project.

FMI singles out a number of steps for winning design-build projects:

•Build a compelling story about why your firm is right for the project

•Build a go-to-market strategy that defines customers before an RFP hits the street

•Think like a customer

•Find out what the customer wants and why it’s important.

•Put your time where your strategy is. Build in organizational capacity that’s centered on a key focus, such as spending time with customers in advance.

The paper provides some avenues for minimizing stress points that can arise during a design-build contract. Having early and continued alignment among all project owners and stakeholders can help remove or limit these issues.

Make sure you completely understand requirements or other bidding assumptions, particularly on design-build projects. Of the projects FMI studied, 25% fell victim to this. At times, even the owner won’t understand the true impact of some of the requirements that are written into the contract.

Make sure there are formal internal hand-off meeting(s) between estimating/preconstruction and project management/field operations. This should include subcontractor involvement in planning the work.

Within the design-build arena, public-private partnerships (P3s) have emerged as a way for public and private sector entities to align on the provision of assets and the delivery of services and then effectively manage that partnership. To assemble the most successful P3 project teams, contractors should:

•Build your expertise through strategic joint ventures. Pick your partners carefully.

•Plan comprehensively for project complexities. Be smart about your business decisions.

•Understand the cost and risk barriers to entry. You need deep pockets and a thick skin.

•Have a deep understanding of an owner’s “ecosystem.”

•Start building relationships with public officials and finance representatives now.

•Collaborate and innovate.

Related Stories

| Aug 11, 2010

Green Building Initiative launches two certification programs for green building professionals

The Green Building Initiative® (GBI), one of the nation’s leading green building organizations and exclusive provider of the Green Globes green building certification in the United States, today announced the availability of two new personnel certification programs for green building practitioners: Green Globes Professional (GGP) and Green Globes Assessor (GGA).

| Aug 11, 2010

Brandeis University's new Shapiro Science Center completed

Payette, a leading architectural design firm specializing in complex buildings for medical and scientific research, academic teaching, and healthcare, announced today the completion of Phase One of the 175,000 square foot Carl J. Shapiro Science Center at Brandeis University in Waltham, Mass. Phase One of the complex is 101,045 GSF and Phase Two is planned for 74,080 GSF.

| Aug 11, 2010

AGC: No recovery yet for construction industry as latest figures show double-digit drops in spending compared to last year

The construction industry continues to suffer from significant declines in privately-funded construction investments, with new federal figures showing private construction investments declined by 20.6 percent between September 2008 and September 2009. The new Census Bureau figures show there’s no sign of an economic recovery yet for the nation’s construction industry, the Associated General Contractors of America noted today.

| Aug 11, 2010

Casino Queen breaks ground on $2.15 million entertainment venue

The Casino Queen in East St. Louis, Ill., is raising the stakes in its bid to capture a larger share of the local gaming market with the start of construction on a new $2.15 million sports bar and entertainment venue that will enhance the overall experience for guests.

| Aug 11, 2010

Construction employment declines in 49 states & D.C. in September compared to last year

Construction employment again declined in large numbers in all but one state this September compared to last year according to an analysis of new state-by-state employment figures released today by the federal government.

| Aug 11, 2010

Outdated office tower becomes Nashville’s newest boutique hotel

A 1960s office tower in Nashville, Tenn., has been converted into a 248-room, four-star boutique hotel. Designed by Earl Swensson Associates, with PowerStrip Studio as interior designer, the newly converted Hutton Hotel features 54 suites, two penthouse apartments, 13,600 sf of meeting space, and seven “cardio” rooms.

| Aug 11, 2010

HDR, Perkins+Will top BD+C's ranking of the nation's 100 largest healthcare design firms

A ranking of the Top 100 Healthcare Design Firms based on Building Design+Construction's 2009 Giants 300 survey. For more Giants 300 rankings, visit http://www.BDCnetwork.com/Giants

| Aug 11, 2010

U.S. Green Building Council's new headquarters earns LEED Platinum

The U.S. Green Building Council (USGBC) is proud to announce the Platinum certification of its new Washington, D.C. headquarters – making it the first project to certify under the latest version of the LEED green building rating system.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021