The JW Marriott brand holds high standards for its luxury hotels, and the new property in Hanoi, Vietnam, is no different. The 74,384-sm building conveys a distinct Vietnamese flair, with its stylized dragon form inspired by local mythology and the country’s coastline.
Sited next to the Vietnam National Convention Center and the Hanoi Museum, convenient to nearby tourist attractions, the JW Marriott Hanoi greets visitors with a landscaped, semi-circular courtyard. Below this raised entry plaza lies a podium level housing two ballrooms; meeting facilities; dining, bar, and lounge areas; three levels of indoor parking; and back-of-house support functions. Atop the podium, the hotel includes a grand lobby, 450 guest rooms and suites, an executive lounge, a glass-enclosed rooftop swimming pool, and a fitness center.
The hotel is built for ADA compliance, even though no such laws currently exist in Vietnam. Accommodations include wider entry corridors in several rooms and special considerations in bathroom facilities. Elegant finishes are a priority throughout.
“It’s not easy working with Marriott’s standards,” remarks Building Team Awards judge Susan Heinking, AIA, NCARB, LEED AP O+M, Vice President and Director of Sustainability at VOA Associates. Indeed, this Building Team had to navigate a thicket of design requirements, including directives from owner Bitexco Group, Marriott International, and the neighboring Vietnam National Convention Center.
GOLD AWARD
Project summaryJW Marriott Hanoi Hotel
Hanoi, VietnamBUILDING TEAM
Submitting firm: Turner International – Vietnam (CM)
Owner/developer: Bitexco Group
Hotel operator: Marriott International
Architect: Carlos Zapata Studio
Architect of record: Viet Nam National Construction Consultants Corporation
Interior architects: Peter Silling & Associates Hotel Interior Design; DWP | Design Worldwide Partnership
Structural: Leslie E. Robertson Associates
Foundation: GECI
MEP: DSA Engineering Contractors: Hyundai Engineering & Construction; Delta Civil and Industrial Construction; Trung A. Stock ConstructionGENERAL INFORMATION
Project size: 74,384 sm
Construction cost: Confidential at owner’s request
Construction period: November 2009 to September 2013
Delivery method: PM/CM as agent, fast-trackMarriott’s in-house architectural group—responsible for overseeing design of all the brand’s hotels and resorts—was brought in at several stages for input and approval, but adherence to their standards proved difficult when financial problems led to a two-year delay.
Marriott criteria had changed in the interim, and new design styles caused previously selected finishes to be rejected. In addition, the clients decided to reorganize the site to make room for two villas, scrapping plans to build tennis courts and install a significant amount of landscaping.
Even basic communication was a concern, with Building Team members and consultants such as Turner Construction, Carlos Zapata Studio, Leslie E. Robertson Associates, and DSA Engineering scattered among offices in nine different countries. The firms decided early on that English would be the standard for all communications.
Vietnam is still a developing country in many aspects, so there was concern about the availability of skilled workers. Safety was also paramount, with Turner implementing weekly training sessions and audits to reinforce this priority for crews. Figuring out the best way to deploy teams—and to keep employees reporting through delays and cash-flow difficulties—made construction management even more complex.
The Building Team brought in international consultants and engineers when expertise was needed on elements unfamiliar to Vietnamese partner firms, such as the cantilevered design and structural steel construction. Sika, which supplied the waterproofing system for the podium roof, sent employees to train contractors on-site to prevent leaks that could threaten the ballrooms below.
The way the JW Marriott Hanoi came together in spite of the obstacles and difficulty level impressed the Building Team Awards judges. Says juror Matthew Dumich, AIA, of Adrian Smith + Gordon Gill Architecture: “It’s as if someone said, ‘No one knows how to do any of this stuff. Let’s do it anyway.’ And it works.”
A curtain wall system at the podium level brings natural light into the hotel’s café. Elegant finishes were a priority for the owner. PHOTO: NGUYEN HAI VAN / COURTESY TURNER VIETNAM
The structure is constructed on a podium, with ballrooms and restaurants on the lowest floor enjoying riverfront views. PHOTO: VU LONG / COURTESY TURNER VIETNAM
Related Stories
| Apr 12, 2011
American Institute of Architects announces Guide for Sustainable Projects
AIA Guide for Sustainable Projects to provide design and construction industries with roadmap for working on sustainable projects.
| Apr 11, 2011
Wind turbines to generate power for new UNT football stadium
The University of North Texas has received a $2 million grant from the State Energy Conservation Office to install three wind turbines that will feed the electrical grid and provide power to UNT’s new football stadium.
| Apr 8, 2011
SHW Group appoints Marjorie K. Simmons as CEO
Chairman of the Board Marjorie K. Simmons assumes CEO position, making SHW Group the only firm in the AIA Large Firm Roundtable to appoint a woman to this leadership position
| Apr 5, 2011
Zaha Hadid’s civic center design divides California city
Architect Zaha Hadid is in high demand these days, designing projects in Hong Kong, Milan, and Seoul, not to mention the London Aquatics Center, the swimming arena for the 2012 Olympics. But one of the firm’s smaller clients, the city of Elk Grove, Calif., recently conjured far different kinds of aquatic life when members of the City Council and the public chose words like “squid,” “octopus,” and “starfish” to describe the latest renderings for a proposed civic center.
| Apr 5, 2011
Are architects falling behind on BIM?
A study by the National Building Specification arm of RIBA Enterprises showed that 43% of architects and others in the industry had still not heard of BIM, let alone started using it. It also found that of the 13% of respondents who were using BIM only a third thought they would be using it for most of their projects in a year’s time.