Holt Construction, U.S. Army Corps of Engineers complete temporary hospital in two weeks

Healthcare Facilities

Holt Construction, U.S. Army Corps of Engineers complete temporary hospital in two weeks

The project is located in Paramus, N.J.


By David Malone, Associate Editor | May 5, 2020
BNBMC Temporary Hospital with contractors

All photos courtesy Holt Construction

A new temporary medical facility, comprising two fully-equipped tents, was completed in just two weeks at Bergen New Bridge Medical Center (BNBMC) in Paramus, N.J. The project was built by Holt Construction, the U.S. Army Corps of Engineers, and FEMA.

The hospital is a first of its kind for Army Corps temporary facility construction standards and will serve as a treatment facility for acute, non-COVID related patients due to the influx of COVID-positive patients in the main building. Located in a large parking lot adjacent to BNBMC's main building, the temporary hospital will serve an additional 100 patients in total.

 

BNBMC temporary hospital hallway and patient bays

 

Each tent includes 50 patient beds as well as an admissions bay, nurse stations, six bathrooms with showers, hospital staff nourishment and support areas, a nurse call system in each patient room, medical gas storage, medicine storage, and soiled holding. Life safety provisions, such as fire alarm, sprinkler, fire extinguishers, and other life-safety systems, were also installed. Plumbing and sprinkler were run from the main building to the lot and new incoming primary power with a stepdown transformer was provided to power the two tents.

 

See Also: Danish hospital is constructed from 24 steel frame modules

 

The tents were constructed by over 80 carpenters, 20 electricians, and 20 plumbers working in three shifts around the clock. Social distancing was enforced at all times and all personnel were equipped with N95 face masks, face shields, gloves, and goggles. Additionally, sanitation stations were set up for use upon entering and exiting the site.

 

BNBMC temporary hospital interior

 

BNBMC temporary hospital exterior power

 

BNBMC Temporary Hospital covered entrance

 

Related Stories

Game Changers | Feb 4, 2016

GAME CHANGERS: 6 projects that rewrite the rules of commercial design and construction

BD+C’s inaugural Game Changers report highlights today’s pacesetting projects, from a prefab high-rise in China to a breakthrough research lab in the Midwest.

Healthcare Facilities | Jan 27, 2016

CBRE: Here's what healthcare owners need to know when selecting a real estate developer

Understanding equity sources, balancing costs, and involving legal departments early in the process can help health systems maintain leverage during the RFP process, writes CBRE Healthcare’s Chris Bodnar.

Healthcare Facilities | Jan 27, 2016

South Carolina governor’s push to repeal health facility construction rules gets boost from Feds

Legislature may move to strike certificate of need requirements.

Metals | Jan 19, 2016

6 ways to use metal screens and mesh for best effect

From airy façades to wire mesh ceilings to screening walls, these projects show off the design possibilities with metal.

Great Solutions | Jan 19, 2016

Healing garden doubles as therapy trails

A Boston-area hospital takes the healing garden to the next level.

Healthcare Facilities | Jan 15, 2016

Mount Sinai Health System signs first healthcare IPD IFOA contract in New York City

Francis Cauffman, Syska Hennessy, Turner Construction are the primary parties in agreement.  

| Jan 14, 2016

How to succeed with EIFS: exterior insulation and finish systems

This AIA CES Discovery course discusses the six elements of an EIFS wall assembly; common EIFS failures and how to prevent them; and EIFS and sustainability.

Great Solutions | Jan 6, 2016

Shepley Bulfinch develops elegant design solution to address behavioral issues in emergency departments

ED scheme allows staff to isolate unruly patients and visitors in a secure area.

Great Solutions | Jan 4, 2016

Toronto’s newest hospital employs 10 robots for moving food, supplies, and equipment

The 1.8 million-sf Humber River Hospital is loaded with high-tech gadgets. Its coolest innovation is the use of automated guided vehicles.

Urban Planning | Jan 4, 2016

The next boomtown? Construction and redevelopment sizzle in San Diego

The city's emission-reduction plan could drive influx into downtown

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021