Industry groups petition for change order reform on federal projects

Codes and Standards

Industry groups petition for change order reform on federal projects

Nine design and construction associations ask for assurance that funds available for additional work.


By Peter Fabris, Contributing Editor | April 6, 2015
Industry groups petition for change order reform on federal projects

Photo: Matti Mattila via Wikimedia Commons

Nine associations representing construction contractors, subcontractors, and design professionals petitioned the Office of Federal Procurement Policy (OFPP) to alter how the office handles change orders.

The groups want the Federal Acquisition Regulation (FAR) amended to "make explicit" that before ordering a change to a construction contract, the contracting officer must assure that funds are available to pay for additional work being ordered.

“Our members are facing increasing numbers of instances in which a Contracting Officer will direct a change in the scope of work on a construction project, lacking funds available to pay for the increased costs being imposed upon the contractor,” the associations wrote in a March 18 letter to OFCPP Administrator Anne Rung.

The groups signing the letter included the Design-Build Institute of America, the American Council of Engineering Companies, the American Subcontractors Association, the Associated General Contractors of America, the Mechanical Contractors Association of America, the National Association of Surety Bond Producers, the National Electrical Contractors Association, the Sheet Metal and Air Conditioning Contractors’ National Association and The Surety & Fidelity Association of America.

They also recommended an amendment that would allow contracting officers to continue to make changes in the work within the general scope of the contract, at any time and without notice to sureties, “but only if funds are available to pay the costs of such changes.”

Related Stories

| Mar 22, 2012

Bill would reintroduce “opt-out” provision in lead paint law

The Lead Exposure Reduction Amendments Act of 2012 (S2148) would restore the "Opt-Out" provision removed from the Environmental Protection Agency's Lead Renovate, Repair and Painting (LRRP) rule in April 2010.

| Mar 15, 2012

New Florida building code establishes flood and storm surge provisions

The new 2010 code establishes minimum design and construction requirements to protect buildings from wind, rain, floods, and storm surges.

| Mar 15, 2012

Illinois city rejects international code due to home sprinkler requirement

Macomb, Illinois aldermen voted to recommend that the city not adopt 2012 international building and residential code standards requiring the installation of overhead sprinkler systems in newly constructed one-family and two-family homes.

| Mar 15, 2012

Tenant advocates propose licensing landlords in New York City

With thousands of New York City rental units posing potential dangers to tenants, city advocates are proposing measures to make landlords improve building safety.

| Mar 15, 2012

Construction industry a big winner in federal small disadvantaged business procurement

Last year, only 5% of federal contract dollars went to small disadvantaged businesses. Construction and facilities support firms were the biggest beneficiaries.

| Mar 15, 2012

ANSI approves new fall protection standards

The American National Standards Institute (ANSI) has approved two American Society of Safety Engineers' (ASSE) standards addressing fall protection.

| Mar 8, 2012

Engineering innovation provides new option for meeting seismic codes in skyscrapers

Two University of Toronto engineers have developed “viscoelastic-energy-dissipating dampers” to replace many of the heavy concrete beams used in tall structures.

| Mar 8, 2012

CSI webinar on building code compliance March 22

A March 22 webinar will provide an overview of a 28-step process during the design of a building to ensure compliance with building codes.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021