Industry groups petition for change order reform on federal projects

Codes and Standards

Industry groups petition for change order reform on federal projects

Nine design and construction associations ask for assurance that funds available for additional work.


By Peter Fabris, Contributing Editor | April 6, 2015
Industry groups petition for change order reform on federal projects

Photo: Matti Mattila via Wikimedia Commons

Nine associations representing construction contractors, subcontractors, and design professionals petitioned the Office of Federal Procurement Policy (OFPP) to alter how the office handles change orders.

The groups want the Federal Acquisition Regulation (FAR) amended to "make explicit" that before ordering a change to a construction contract, the contracting officer must assure that funds are available to pay for additional work being ordered.

“Our members are facing increasing numbers of instances in which a Contracting Officer will direct a change in the scope of work on a construction project, lacking funds available to pay for the increased costs being imposed upon the contractor,” the associations wrote in a March 18 letter to OFCPP Administrator Anne Rung.

The groups signing the letter included the Design-Build Institute of America, the American Council of Engineering Companies, the American Subcontractors Association, the Associated General Contractors of America, the Mechanical Contractors Association of America, the National Association of Surety Bond Producers, the National Electrical Contractors Association, the Sheet Metal and Air Conditioning Contractors’ National Association and The Surety & Fidelity Association of America.

They also recommended an amendment that would allow contracting officers to continue to make changes in the work within the general scope of the contract, at any time and without notice to sureties, “but only if funds are available to pay the costs of such changes.”

Related Stories

| Feb 23, 2012

Federal budget cuts put major building projects on hold

A plan to build the National Bio and Agro-Defense Facility in Kansas is among several major building projects in jeopardy after the Obama administration’s 2013 budget was unveiled. The budget would cut all construction spending for the facility.

| Feb 23, 2012

Federal agencies fixed on leasing LEED-certified space

The federal government is especially focused on renting LEED-certified spaces.

| Feb 23, 2012

Regulators investigating construction accident at World Trade Center

The New York Port Authority and the city’s fire and building departments are investigating an accident at the World Trade Center construction site in lower Manhattan after a crane dropped steel beams that fell about 40 stories onto the truck that delivered them.

| Feb 23, 2012

New Virginia statewide building code goes into effect March 1

After March 1, all building plans in Virginia must adhere to the 2009 code that was adopted a year ago.

| Feb 23, 2012

Privatizing flood insurance could lead to new code requirements

One thing that could pave the way toward private flood insurance would be NFIP reforms, like requiring new construction in flood-prone areas to be elevated.

| Feb 22, 2012

ACI BIM manual for cast-in-place concrete in development

The improved communication, coordination, and collaboration afforded by BIM implementation have already been shown to save time and money in projects.

| Feb 20, 2012

Comment period for update to USGBC's LEED Green Building Program now open

This third draft of LEED has been refined to address technical stringency and rigor, measurement and performance tools, and an enhanced user experience.

| Feb 20, 2012

GAF introduces web portal for architects and specifiers

The new portal offers a clean look with minimal clutter to make it easier to find the technical information and product data that architects need.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021