It's a world record! Largest uninterrupted concrete pour kicks off Wilshire Grand project

It's a world record! Largest uninterrupted concrete pour kicks off Wilshire Grand project

Guinness World Records verifies the concrete pour as the largest ever


By BD+C Staff | February 19, 2014

After about 20 hours of continuous pouring, judges from Guinness World Records verified that the concrete pour at the $1 billion Wilshire Grand project in Los Angeles is the largest uninterrupted pour of slurry on record.  

It took 208 trucks making as many as 10 deliveries each last weekend to complete the pour. In all, 21,000 cubic yards of concrete were poured to form the foundation for the 73-story tower. 

The project, led by Turner Construction for developer Korean Air, includes office space, restaurants, retail, and 900 luxury hotel rooms. Scheduled to open in 2016, the tower will be the tallest building west of Chicago. AC Martin Partners is designing the 1,100-foot-tall tower, with Thornton Tomasetti as structural engineer.

Here are some of the pour’s impressive numbers:
• 19 pumps dispensed concrete into the pit through 13 hoses
• 24 temperature sensors provided hourly readings (the concrete should remain between 120 and 160 degrees)
• 45 degree water pumped through 100,000 feet of polyethylene hose snaked throughout the pit will help counteract the natural heating
• The concrete weighs some 82 million pounds


12:00 noon PST February 15, 2014

12:00 midnight PST February 15, 2014


12:00 noon PST February 15, 2014

Related Stories

| Jan 6, 2012

Gensler unveils restoration and expansion of Houston's Julia Ideson building

The "new" building will serve as a repository of Houston memorabilia and rare archival material as well as the city's official reception space and a venue for exhibits, meetings and other special events.

| Jan 6, 2012

New Walgreen's represents an architectural departure

The structure's exterior is a major departure from the corporate image of a traditional Walgreens design.

| Jan 6, 2012

Summit Design+Build completes Park Place in Illinois

Summit was responsible for the complete gut and renovation of the former auto repair shop which required the partial demolition of the existing building, while maintaining the integrity of the original 100 year-old structure, and significant re-grading and landscaping of the site.

| Jan 4, 2012

Siemens acquires Pace Global Energy Services

Acquisition will enhance portfolio with new energy consulting and management services.

| Jan 4, 2012

Shawmut Design & Construction awarded dorm renovations at Brown University

Construction is scheduled to begin in June 2012, and will be completed by December 2012.

| Jan 4, 2012

Skanska acquires Industrial Contractors

Industrial Contractors Inc. is a contractor in the commercial, industrial and power markets of the Midwest. The company employs 2,400 people and in 2011 the revenues are estimated to be approximately $500 million.

| Jan 4, 2012

HDR to design North America’s first fully digital hospital

Humber River  is the first hospital in North America to fully integrate and automate all of its processes; everything is done digitally.

| Jan 4, 2012

New LEED Silver complex provides space for education and research

The academic-style facility supports education/training and research functions, and contains classrooms, auditoriums, laboratories, administrative offices and library facilities, as well as spaces for operating highly sophisticated training equipment.

| Jan 3, 2012

Gilbane awarded $88M Contract for Ohio elementary school construction

The new award, which comprises the construction of five new elementary schools and demolition of 11 older facilities, is the latest K-12 building program managed by Gilbane for the Ohio School Facilities Commission since 1998.

| Jan 3, 2012

AIA's ABI November Index reaches 52.0

The Architecture Billings Index (ABI) reached its first positive mark since August. 

boombox1
boombox2
native1

More In Category


Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.



Libraries

Reasons to reinvent the Midcentury academic library

DLR Group's Interior Design Leader Gretchen Holy, Assoc. IIDA, shares the idea that a designer's responsibility to embrace a library’s history, respect its past, and create an environment that will serve student populations for the next 100 years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021