The Allen Independent School District in Allen, Texas, will not open its high school's $60 million Eagle Stadium this fall.
The stadium opened in 2012, but cracks recently began appearing throughout the structure, Business Insider reports. Nelson Forensics inspected the stadium and judged that the support structures were not designed to hold the stadium's weight.
Some of the problems include failure to completely fill the concourse deck pan during concrete pours and too much space between stirrups. Overall, the investigators found that the load demand exceeded the building's standards by 10-20% in multiple areas; in a few isolated areas, this number rose to 70%.
Prior to this prelimary report, the stadium's designer, PBK Architects, had said that the cracking was likely a result of concrete shrinkage. Now, WFAA reports, PBK and Pogue Construction, who built the stadium, will pay for the repairs through their insurance. The repairs are estimated at less than $1 million.
During this year's football season, Allen will pay $5,300 per game so that its students can play at a nearby high school.
Below are some photos of the damage and a graphic released by Nelson Forensics (all images courtesy of Business Insider and the Dallas Morning News).
Related Stories
| May 25, 2011
Low Impact Development: Managing Stormwater Runoff
Earn 1.0 AIA/CES HSW/SD learning units by studying this article and successfully passing the online exam.
| May 25, 2011
Register today for BD+C’s June 8th webinar on restoration and reconstruction projects
Based on new and award-winning building projects, this webinar presents our “expert faculty” to examine the key issues affecting project owners, designers and contractors in case studies ranging from gut renovations and adaptive reuses to restorations and retrofits.
| May 25, 2011
Hotel offers water beds on a grand scale
A semi-submerged resort hotel is the newest project from Giancarlo Zema, a Rome-based architect known for his organic maritime designs. The hotel spans one kilometer and has both land and sea portions.
| May 25, 2011
Smithsonian building $45 million green lab
Thanks to a $45 million federal appropriation to the Smithsonian Institution, the Smithsonian Environmental Research Center in Edgewater, Md., has broken ground on what is expected to be one of the most energy-efficient laboratories in the country. The 69,000-sf lab is targeting LEED Gold and is expected to use 37% less energy and emit 37% less carbon dioxide than a similar building.
| May 25, 2011
World’s tallest building now available in smaller size
Emaar Properties teamed up with LEGO to create a miniature version of the Burj Khalifa as part of the LEGO Architecture series. Currently, the LEGO Burj Khalifa is available only in Dubai, but come June 1, 2011, it will be available worldwide.