Lake Washington STEM school combines modular and site-built construction to meet ambitious schedule

Lake Washington STEM school combines modular and site-built construction to meet ambitious schedule

New high school built in just seven months thanks to modular construction


By M SPACE | June 10, 2013
When the Lake Washington School District outside Seattle needed a new high school built on an ambitious permitting and construction schedule of seven months, modular construction proved to be an ideal solution.
 
“Conventional construction just wasn’t an option,” said Allan Long, Sr. Project Manager for M SPACE, the modular contractor for the project.
 
The LWSD ran into various permitting issues restricting site work on a new Science, Technology, Engineering and Math (STEM) school that was set to open in the fall of 2012. Since the modular process allows the bulk of construction to be done offsite in a factory, with minimal site disruption, the LWSD chose modular as the solution to its challenges.
 
The school is now serving 300 students, and by 2014, will be at near capacity with 600 9th-12th graders.
 
Integrus Architects, the designer on the project, began working the modular aspect of the project into it from the beginning, according to Yong Sun Lee, project manager with Integrus.
 
 
 
 
“In schematic design, we met with and toured various modular manufacturers’ facilities to understand the fabrication process,” Lee said. 
 
“It was in the early stages that we were sensitive to issues of modular dimensions (transportation widths and heights), structure and material types.  In design development, we maintained communication with the participating modular manufacturers and dealers with constructability/design insight,” she said. 
 
Blazer Industries in Oregon began building the “mods” in April 2012, and M SPACE started craning them into place in July 2012.  The school was constructed in two phases, with the first phase ending in August 2012. M SPACE contracted with Absher Construction as the onsite GC for the civil work, modular construction, roofing, sprinkler system and mechanical, electrical and plumbing.
 
 
 
 
M SPACE began setting the second phase in September 2012 and finished the following month, with the remaining site work completed by March 2013. With the two phases combined, the permanent 65,000 square-foot two-story school has 24 classrooms, a presentation hall, common areas, administrative offices and a nurse’s office. Additional features include photovoltaic panels in part of the roof, storefront windows, power cord reels in the science studios, two-hour rated walls, and light dimming ballasts in fixtures.
 
Four spaces in the school were site built, allowing modular and traditional construction to be combined to best suit the client’s need. The site-built commons has 22-foot ceilings, offering an open and inviting space for students. The top of the commons – the roof mods – were built in the factory, reducing the amount of time that workers had to spend at significant heights, according to Alan Duer, M SPACE Pacific Northwest Territory Manager.
 
“Mixing modular construction with conventional construction proved to be a valid alternative to the old ways of building,” Duer said. 
 
To learn more about the school, please visit the M SPACE website.
 
 
 

Related Stories

| Sep 14, 2022

Indian tribe’s new educational campus supports culturally appropriate education

The Kenaitze Indian Tribe recently opened the Kahtnuht’ana Duhdeldiht Campus (Kenai River People’s Learning Place), a new education center in Kenai, Alaska.

| Sep 13, 2022

California building codes now allow high-rise mass-timber buildings

California recently enacted new building codes that allow for high-rise mass-timber buildings to be constructed in the state.

| Sep 13, 2022

Orange County opens civic center complex—one of California’s largest P3 projects

Orange County’s recently opened County Administration North (CAN) building caps an urban center development that constitutes one of California’s largest ever P3 projects.

Laboratories | Sep 12, 2022

Lab space scarcity propels construction demand in life sciences sector

In its 2021 Life Sciences Real Estate Outlook, JLL predicted that access to talent would be a primary concern for an industry sector that had been growing by leaps and bounds. A year later, talent still guides real estate decisions. But market conditions of a different sort were cooling the biotech field: namely, investors that have soured on startups which underperformed after going public. What this means for new construction and renovation going forward is unpredictable, as the drivers behind life sciences’ surge are still palpable.

| Sep 12, 2022

Staff at New York City architecture firm is first in U.S. to unionize

Staff at New York City architecture firm is first in U.S. to unionize.

| Sep 12, 2022

San Antonio’s new courthouse aims to provide safety and security while also welcoming the public

The San Antonio Federal Courthouse, which opened earlier this year, replaces a courthouse that had been constructed as a pavilion for the 1968 World’s Fair. 

Giants 400 | Sep 9, 2022

Top 20 Casino Architecture + AE Firms for 2022

JCJ Architecture, DLR Group, HBG Design, and Cuningham top the ranking of the nation's largest casino architecture and architecture/engineering (AE) firms for 2022, as reported in Building Design+Construction's 2022 Giants 400 Report.

Giants 400 | Sep 9, 2022

Top 120 Hospitality Sector Architecture + AE Firms for 2022

Gensler, WATG, HKS, and JCJ Architecture top the ranking of the nation's largest hospitality facilities sector architecture and architecture/engineering (AE) firms for 2022, as reported in Building Design+Construction's 2022 Giants 400 Report. Note: This ranking includes revenue for all hospitality facilities work, including casinos, hotels, and resorts. 

| Sep 9, 2022

Add sand shortage to supply chain woes

As if it wasn’t enough to have lumber, windows, doors, and metal pipe in short supply, you can add sand, which is theoretically plentiful on Earth, to the list of construction materials that can be hard to come by.

boombox1
boombox2
native1

More In Category


Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.



Libraries

Reasons to reinvent the Midcentury academic library

DLR Group's Interior Design Leader Gretchen Holy, Assoc. IIDA, shares the idea that a designer's responsibility to embrace a library’s history, respect its past, and create an environment that will serve student populations for the next 100 years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021