Mount Sinai Health System signs first healthcare IPD IFOA contract in New York City

Healthcare Facilities

Mount Sinai Health System signs first healthcare IPD IFOA contract in New York City

Francis Cauffman, Syska Hennessy, Turner Construction are the primary parties in agreement.


By Peter Fabris, Contributing Editor | January 15, 2016
Mount Sinai Health System signs first healthcare IPD IFOA contract in New York City

Photo: David Edwards/Creative Commons

Mount Sinai Health System (MSHS) became the first health system in New York City to execute an Integrated Form of Agreement (IFOA) for their capital program at Mount Sinai St. Luke’s Hospital.  

Other signatories to the IFOA include Francis Cauffman (architect), Syska Hennessy (engineer), and Turner Construction Company (contractor). Trade subcontractors that signed adjoining agreements as part of the Integrated Project Delivery (IPD) team are: EJ Electric, Fresh Meadows Mechanical, Heritage Mechanical, Cardoza Plumbing, Jacobsen Carpentry, Sirina Fire Protection, and Skyline Controls. 

The Integrated Project Delivery (IPD) process is new to the New York healthcare construction market, though it has been used for several years elsewhere. CBRE Healthcare, retained to provide IPD advisory services, collaborated with Mount Sinai on the delivery model development beginning in 2015. Though the details of the contract were just recently finalized, the IPD team, operating collaboratively, began work on various projects over a year ago.

“The team has proven the value of the IPD process and the results thus far are leading us to consider wider adoption of the delivery model for capital programs at our other facilities,” said Ken Holden, Chief Facilities Officer for Mount Sinai Health System. 

Related Stories

Coronavirus | Apr 14, 2020

COVID-19 alert: Missouri’s first Alternate Care Facility ready for coronavirus patients

Missouri’s first Alternate Care Facility ready for coronavirus patients

Coronavirus | Apr 10, 2020

COVID-19: Converting existing hospitals, hotels, convention centers, and other alternate care sites for coronavirus patients

COVID-19: Converting existing unused or underused hospitals, hotels, convention centers, and other alternate care sites for coronavirus patients 

Coronavirus | Apr 9, 2020

COVID-19 alert: Robins & Morton to convert Miami Beach Convention Center into a 450-bed field hospital

COVID-19 alert: Robins & Morton to convert Miami Beach Convention Center into a 450-bed field hospital

Coronavirus | Apr 4, 2020

COVID-19: Construction completed on first phase of Chicago's McCormick Place into Alternate Care Facility

Walsh Construction, one of the largest contractors in the city of Chicago and in the United States, is leading the temporary conversion of a portion of the McCormick Place Convention Center into an Alternate Care Facility (ACF) for novel coronavirus patients. Construction on the first 500 beds was completed on April 3. 

Coronavirus | Apr 1, 2020

TLC’s Michael Sheerin offers guidance on ventilation in COVID-19 healthcare settings

Ventilation engineering guidance for COVID-19 patient rooms

Healthcare Facilities | Mar 29, 2020

A ‘roadmap’ for building hospitals in rural and underfunded markets

Hoar Construction’s formula emphasizes preconstruction planning and input from healthcare workers.

Healthcare Facilities | Mar 27, 2020

Designing healthcare for surge capacity

We believe that part of the longer-term answer lies not just with traditional health providers, but in the potential of our cities and communities to adapt and change.

Modular Building | Mar 17, 2020

Danish hospital is constructed from 24 steel frame modules

Onsite construction was completed in two weeks.

Healthcare Facilities | Mar 9, 2020

Mobile wayfinding platform helps patients, visitors navigate convoluted health campuses

Gozio Health uses a robot to roam hospital campuses to capture data and create detailed maps of the building spaces and campus.

Healthcare Facilities | Feb 28, 2020

Valleywise Health Medical Center breaks ground in Phoenix

Cuningham Group Architecture and EYP designed the project.  

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021