Mount Sinai Health System signs first healthcare IPD IFOA contract in New York City

Healthcare Facilities

Mount Sinai Health System signs first healthcare IPD IFOA contract in New York City

Francis Cauffman, Syska Hennessy, Turner Construction are the primary parties in agreement.


By Peter Fabris, Contributing Editor | January 15, 2016
Mount Sinai Health System signs first healthcare IPD IFOA contract in New York City

Photo: David Edwards/Creative Commons

Mount Sinai Health System (MSHS) became the first health system in New York City to execute an Integrated Form of Agreement (IFOA) for their capital program at Mount Sinai St. Luke’s Hospital.  

Other signatories to the IFOA include Francis Cauffman (architect), Syska Hennessy (engineer), and Turner Construction Company (contractor). Trade subcontractors that signed adjoining agreements as part of the Integrated Project Delivery (IPD) team are: EJ Electric, Fresh Meadows Mechanical, Heritage Mechanical, Cardoza Plumbing, Jacobsen Carpentry, Sirina Fire Protection, and Skyline Controls. 

The Integrated Project Delivery (IPD) process is new to the New York healthcare construction market, though it has been used for several years elsewhere. CBRE Healthcare, retained to provide IPD advisory services, collaborated with Mount Sinai on the delivery model development beginning in 2015. Though the details of the contract were just recently finalized, the IPD team, operating collaboratively, began work on various projects over a year ago.

“The team has proven the value of the IPD process and the results thus far are leading us to consider wider adoption of the delivery model for capital programs at our other facilities,” said Ken Holden, Chief Facilities Officer for Mount Sinai Health System. 

Related Stories

| Feb 14, 2013

Peter Bardwell named 2013 president of the American College of Healthcare Architects

The Board of Regents of the American College of Healthcare Architects (ACHA) has named Peter L. Bardwell, FAIA, FACHA of Columbus, Ohio as 2013 national President.

| Feb 6, 2013

George W. Bush Presidential Center among award-winning roofing projects honored by Sika Sarnafil

Winners of the 2012 Contractor Project of the Year Competition were announced this week by Sika Sarnafil. The annual competition highlights excellence in roofing installation. Roofing contractors are judged based on project complexity, design uniqueness, craftsmanship, and creative problem solving.

| Feb 6, 2013

RSMeans cost comparisons: office buildings and medical offices

RSMeans' February 2013 Cost Comparison Report breaks down the average construction costs per square foot for four types of office buildings across 25 metro markets.

| Dec 9, 2012

AEC professionals cautiously optimistic about commercial construction in ’13

Most economists say the U.S. is slowly emerging from the Great Recession, a view that was confirmed to some extent by an exclusive survey of 498 BD+C subscribers whose views we sought on the commercial construction industry’s outlook on business prospects for 2013.

| Nov 11, 2012

Greenbuild 2012 Report: Healthcare

Green medical facilities extend beyond hospital walls

| Oct 24, 2012

Loma Linda University Medical Center lets light in with metal wall systems

Designers for the building aimed to create a positive environment for patients and visitors, and wanted to let in as much natural daylight as possible.

| Oct 11, 2012

Hank Adams Named to Lead HDR’s Healthcare Program

With more than 25 years of experience, HDR vice president is tapped to lead firm's healthcare projects.

| Oct 10, 2012

Skanska to Construct Children’s Hospital of Richmond at Virginia Commonwealth University Pavilion

Skanska USA announced that it has been awarded an $80 million contract to construct a new Children’s Pavilion at Children’s Hospital of Richmond at VCU.

| Oct 2, 2012

Bernards working on project at L.A. White Memorial Medical Center

The new facility is a $15-million, 41,000-sf concrete structure which includes three stories of medical office space atop a three-level parking garage.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021