A new report by the New York State Comptroller found that New York City construction site inspections and regulation enforcement need improvement.
The state watchdog found that nearly 90% of active New York City construction sites it visited had safety problems. It also said the city’s Department of Buildings doesn’t effectively prioritize which sites get inspected.
Officials from the Comptroller’s office visited 18 active construction sites last summer and reported that 16 of those sites had a total of 77 safety issues. The problems included not having a site safety manager, missing or incomplete site safety logs and daily inspection records, and no documentation of workers completing required site safety training or attending mandatory safety meetings.
In 60% of cases where hazardous conditions were present for more than 30 days, DOB did not issue a citation for failing to correct the problem, the report says. The DOB agreed with most recommendations made to improve practices as cited in the report, which included more timely action to fix hazardous conditions at job sites.
The city department’s chief also noted that conditions “may change on a daily, or even hourly basis; therefore, the types of conditions that the auditors noted may not be present at the time of DOB’s inspection.”
Related Stories
| Nov 29, 2011
Suffolk Construction breaks ground on Boston residential tower
Millennium Place III is a $220 million, 256-unit development that will occupy a full city block in Boston’s Downtown Crossing.
| Nov 29, 2011
Report finds credit crunch accounts for 20% of nation’s stalled projects
Persistent financing crunch continues to plague design and construction sector.
| Nov 29, 2011
SB Architects completes Mission Hills Volcanic Mineral Springs and Spa in China
Mission Hills Volcanic Mineral Springs and Spa is home to the largest natural springs reserve in the region, and measures 950,000 sf.
| Nov 29, 2011
Turner Construction establishes partnership with Clark Builders
Partnership advances growth in the Canadian marketplace.
| Nov 29, 2011
AIA launches stalled projects database
To populate this database with both stalled projects and investors interested in financing them, the AIA in the last week initiated a communications campaign to solicit information about stalled projects around the country from its members and allied professionals.
| Nov 28, 2011
Leo A Daly and McCarthy Building complete Casino Del Sol expansion in Tucson, Ariz.
Firms partner with Pascua Yaqui Tribe to bring new $130 million Hotel, Spa & Convention Center to the Tucson, Ariz., community.
| Nov 28, 2011
Armstrong acquires Simplex Ceilings
Simplex will become part of the Armstrong Building Products division.
| Nov 28, 2011
Nauset Construction completes addition for Franciscan Hospital for Children
The $6.5 million fast-track, urban design-build projectwas completed in just over 16 months in a highly sensitive, occupied and operational medical environment.
| Nov 23, 2011
Lord, Aeck & Sargent opens fourth U.S. office, acquiring architecture firm in Austin, Texas
Strategic move offers growth opportunity and strengthens the firm’s historic preservation portfolio.