Scope it out

Healthcare Facilities

Scope it out

How to design and build what’s needed to meet organizational goals and strategies.


By Curtis Skolnick, Managing Director | November 30, 2017

Planners are often asked to test a facilities concept, define how much space it will take, and determine how much it will cost to complete. These questions are useful in the early concept phase of a project, but the basis for planning is missing; what am I solving for, and how does this potential “bricks and mortar” solution meet a defined service, market, or strategic need of the organization? It’s all about scoping the right concept before getting too far down the facility planning phase.

Defining and documenting project scope (the project intention, goal, or purpose) at the outset and controlling scope throughout the planning and delivery process is essential to ensuring the project vision becomes reality.

Ask yourself:

●    What strategies and goals are we trying to achieve?

●    What is the scope of the envisioned project and how was it defined?

Clearly defining the project, then articulating the scope and rationale to the team is paramount prior to launch. Scope typically relates to:

●    Meeting the demands of the organization’s patients (service area)

●    Cultivating a new or expanded service line opportunity

●    Helping to improve throughput and operations

●    Fixing an infrastructure or standard-of-care issue

●    Scope control/communicating clear scope of work

●    Attaining successful project definition

Rushing into design and construction without clearly defining the project scope can lead to project delay and frustration later in the process. If each team member cannot clearly articulate the scope of the project, you should stop and get everyone on the same page. Establish measurable project goals early to stay on track.

 

Scope Definition and Documentation

A facility project is a tactical element of a strategic plan or the output of business plan; this plan is built on the mission, vision, and goals of the organization. An organization’s strategic plan should include:

●    Mission and vision identification

●    SWOT analysis (strengths, weaknesses, opportunities, and threats)

●    Internal and external environmental analysis

●    Identification of gaps between mission/vision and internal/external needs

●    Service needs identification

●    Market-based needs and capacity analysis

●    Strategic financial analysis

●    Measurable strategic goals

●    Tactics to meet the strategic goals of the organization

The needs identified in a strategic plan or focused business plan drive the tactical need for a project—not the other way around. A well-conceived scope guides facilities master planning and the detailed programming and design phases of a project. The scope of the project also acts as the base to define the project budget. Scope and budget are inextricably linked and need to be constantly checked against each other. It’s imperative that the two balance relative to a complete financial analysis of the project. If the project doesn’t “pencil” from a return-on-investment (ROI) perspective, then you’ll need to adjust scope and budget to get the project in line financially and still meet the market and service delivery goals of the organization.

If you conduct these analyses early, you have a better chance of making less costing changes if needed. As you move through the project delivery process, the ability to easily make changes decreases, and the cost of changes increases. Therefore, it’s important to appropriately define the scope, test it against the budget, and communicate and document it at the project outset.

 

 

Scope Control

Once scope is defined and clearly communicated to the project delivery team, it must be managed. Use scope control tools developed during the early planning phases and during each subsequent planning and design phase (master planning, space planning, schematic design, design development, and construction documents) to avoid scope creep. Scope creep refers to uncontrolled changes in a project’s defined scope. Typically, scope increases consist of new services, new features, or additional room elements without corresponding strategic or market demand justification. Avoid scope creep early by:

●    Plan based on defined and justified needs rather than articulated wants

●    Encourage stakeholder participation and plan based on facts and analysis to ensure buy-in from all parties

●    Eliminate “pet” projects or elements with no financial strategic justification; this is “wish-casting” instead of “forecasting” and usually results in wasted finite resources at the expense of needed projects

●    Clearly communicate scope to all key constituents and members of the project delivery team before embarking on detailed planning, design, and construction

●    Track scope early and continue to track throughout the life of the project

Remember, you don’t need to eliminate scope changes all together. Sound strategic logic and rapidly changing market dynamics may dictate appropriate (controlled) changes to scope that are justified. Strong scope controls will identify acceptable variances and appropriately jump-start conversations as to the “why” for the changes.

Scope increases may require additional resources (e.g. staffing, space, equipment, capital costs, time, and operational costs) which must be justified or they could potentially put the project at risk. A few thousand square feet of scope creep could add millions to your total project cost, create delays if changed late in the design process, and cause a few headaches along the way. Allowing scope creep without correlating demand and revenue may require additional staffing resources, equipment, and furnishings, and carries the long-term operational cost without the requisite return on investment.

Interestingly scope can shrink too. Cutting revenue producing scope to make budget will have downward impact on potential ROI, the ability to meet service demand, and ability to offer services and recruit new staff. If a department is downsized to allow another area to grow and still remain within budget, make sure the downsized department is not rendered dysfunctional. If this happens, you may pay once the facility is operational.

There is great risk and cost to unfettered scope creep and a poorly defined project; therefore, proper planning and controls must be in place to prevent your project from being derailed. Items to consider:

●    Thoroughly understand the project vision and involve all stakeholders in defining and documenting the project scope

●    Utilize tools to monitor and control scope, and track the departmental “units” (e.g. number of rooms) and departmental space

●    Expect changes; develop processes and criteria to evaluate proposed scope changes and to decide which changes are necessary to fulfill the intended vision

Start with acutely defining and documenting scope on the front end of the project. Control scope throughout the process to position yourself to control your project, instead of your project controlling you.

 

If you build it, will they come?

In summary, too often healthcare executives employ an “If you build it, they will come” mentality to a project. Sure, a new facility or space frequently have a halo effect and activity may spike initially. But if the services aren’t what the patient, caregivers, and physicians require, then they will stop coming. The analyses conducted in the planning phase will help to accurately define project scope; meet the strategic, market, and financial goals of leadership; and meet the needs of the healthcare organization’s community.

Related Stories

| Jun 20, 2013

Virtual meetings enhance design of University at Buffalo Medical School

HOK designers in New York, St. Louis and Atlanta are using virtual meetings with their University at Buffalo (UB) client team to improve the design process for UB’s new School of Medicine and Biomedical Sciences on the Buffalo Niagara Medical Campus.

| Jun 19, 2013

New York City considers new construction standards for hospitals, multifamily buildings

Mayor Michael Bloomberg’s administration has proposed new building codes for hospitals and multifamily dwellings in New York City to help them be more resilient in the event of severe weather resulting from climate change.  

| Jun 17, 2013

DOE launches database on energy performance of 60,000 buildings

The Energy Department today launched a new Buildings Performance Database, the largest free, publicly available database of residential and commercial building energy performance information.

| Jun 12, 2013

5 building projects that put the 'team' in teamwork

The winners of the 2013 Building Team Awards show that great buildings cannot be built without the successful collaboration of the Building Team. 

| Jun 5, 2013

USGBC: Free LEED certification for projects in new markets

In an effort to accelerate sustainable development around the world, the U.S. Green Building Council is offering free LEED certification to the first projects to certify in the 112 countries where LEED has yet to take root.

| Jun 3, 2013

Construction spending inches upward in April

The U.S. Census Bureau of the Department of Commerce announced today that construction spending during April 2013 was estimated at a seasonally adjusted annual rate of $860.8 billion, 0.4 percent above the revised March estimate of $857.7 billion.

| May 21, 2013

7 tile trends for 2013: Touch-sensitive glazes, metallic tones among top styles

Tile of Spain consultant and ceramic tile expert Ryan Fasan presented his "What's Trending in Tile" roundup at the Coverings 2013 show in Atlanta earlier this month. Here's an overview of Fasan's emerging tile trends for 2013.

| May 20, 2013

Jones Lang LaSalle: All U.S. real estate sectors to post gains in 2013—even retail

With healthier job growth numbers and construction volumes at near-historic lows, real estate experts at Jones Lang LaSalle see a rosy year for U.S. commercial construction.

| May 9, 2013

Post-tornado Greensburg, Kan., leads world in LEED-certified buildings per capita

Six years after a tornado virtually wiped out the town, Greensburg, Kan., is the world's leading community in LEED-certified buildings per capita.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021