Slow payments cost GCs and subs $64 billion annually

Codes and Standards

Slow payments cost GCs and subs $64 billion annually

Study finds 51-day average payment turnaround.


By Peter Fabris, Contributing Editor | October 17, 2019

Courtesy Pixabay

Delayed payments are costing both general contractors and subcontractors tens of billions annually, according to a new study.

The study was conducted by construction finance platform Rabbet, formerly Contract Simply, in partnership with Procore Technologies. A similar study by Rabbet in 2018 found that slow payments cost subcontractors $40 billion.

This year, the company added general contractors to the study, and found payment delays cost all contractors an estimated $64 billion. More than 60% of subcontractors said they have decided not to bid on certain projects if the owner or general contractor has a reputation for paying late. Some 72% said they would offer a 1% to 5% discount for quicker payments.

Just 39% of subcontractors said that they are able to cover late payments with cash on hand. Slow payments by owners drive up the cost of projects by about 5.3%, according to the study. Owners also risk mechanic’s liens and project shutdowns when they pay late.

Related Stories

| Mar 8, 2012

Federal silica dust rule caught in bureaucratic limbo

A federal rule meant to protect the lungs of workers has been caught in bureaucratic purgatory for more than a year.

| Mar 8, 2012

New LEED-EBOM rating has requirements for specific project types

Several key changes are proposed for the LEED-EBOM Rating System in 2012.

| Mar 8, 2012

Green buildings more resilient than conventionally built structures

A new study by the U.S. Green Building Council (USGBC) and the University of Michigan’s Taubman College of Architecture and Urban Planning suggests that structures built to green standards can advance building resiliency.

| Mar 1, 2012

LEED Platinum standard likely to mean net-zero energy by 2018

As LEED standards continue to rise, the top level, LEED Platinum, will likely mean net-zero energy construction by 2018.

| Mar 1, 2012

EPA beefs up stormwater discharge rule from construction projects

The U.S. Environmental Protection Agency (EPA) has now finalized its 2012 construction general permit (CGP) that authorizes stormwater discharges from construction projects that disturb one or more acres of land in the areas where EPA is the permitting authority.

| Mar 1, 2012

Regulators investigate structural failures during construction of two Ohio casinos

Regulators with the Occupational Safety & Health Administration and the city of Cincinnati are investigatingthe collapse of the second floor of Cincinnati's Horseshoe Casino as workers were pouring concrete.

| Mar 1, 2012

Is your project too small for LEED? Consider other green standards

There are many other recognized national, state and local programs that offer a variety of best management practices and sustainable design, construction and operating strategies.

| Mar 1, 2012

California bill aims to cut costs for commercial building energy retrofits

A bill in the California Assembly would allow the state to pool together property owners’ energy-retrofit loans.

| Feb 29, 2012

Carvalho appointed Shawmut Safety Director

He has been a driving force behind multiple safety-orientated initiatives at Shawmut, including Safety Week, the creation of an online safety manual, and the implementation of a new safety reporting and tracking system. 

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021

Â