flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

Steel Stud Manufacturers Association donates $100,000 to industry research

Steel Stud Manufacturers Association donates $100,000 to industry research

SSMA is co-funding projects identified to be critical by the industry including research on fire rated intersections, clip-angle connections, blast resistant cold-formed steel framed walls, adoption of cold- formed steel framing in ASCE 41 and establishing cold-formed steel framing’s sustainability message.


By Posted by Tim Gregorski, Senior Editor | December 17, 2012

The Steel Stud Manufacturers Association (SSMA) today announced that they will fund $100,000 in 2013 for industry research. SSMA will contribute to the American Iron and Steel Institute’s (AISI) cold-formed steel framing projects including their codes, standards and technology implementation program.

SSMA is co-funding projects identified to be critical by the industry including research on fire rated intersections, clip-angle connections, blast resistant cold-formed steel framed walls, adoption of cold- formed steel framing in ASCE 41 and establishing cold-formed steel framing’s sustainability message.

“SSMA’s commitment to the industry’s quest to remove the barriers has never been stronger,” said SSMA Technical Director Rahim Zadeh, P.E. “Partnering with AISI to explore opportunities and actively participate in codes and standards is vital to keep steel framing competitive with alternative materials.” +

Related Stories

| Jan 27, 2012

BRB Architects designs new campus center for Molloy College

Intended to be the centerpiece of the College’s transformation from a commuter college to a 24-hour learning community, the “Public Square” will support student life with spaces such as a café, lounges, study rooms, student club space, a bookstore and an art gallery.

| Jan 27, 2012

Columbia University’s New Core Laboratory aims for LEED Silver

Construction manager Sordoni Construction Co. along with the design team of Payette Architects and Vanderweil Engineers will provide design and construction services to renovate the majority of the existing Core Lab building to create the new Lamont Center for Bio-Geochemistry.

| Jan 26, 2012

World of Concrete 2012: A tinge of optimism

Cement consumption is expected to increase significantly in 2013, the first time an increase has been predicted in the past five years.

| Jan 26, 2012

Three dead, 16 missing in Rio buildings collapse

The buildings, one 20 floors high, collapsed on Wednesday night in a cloud of dust and smoke just one block away from the city's historic Municipal Theater.

| Jan 26, 2012

Siemens launches smoke detection knowledge center

New knowledge center web site demonstrates efficacy of smoke detection. 

| Jan 26, 2012

Hendrick Construction completes Osso Restaurant in Charlotte

Designed by François Fossard, Osso's upscale interior includes tapered, twisted decorative columns and an elegant fireplace in the center of the lounge. 

| Jan 26, 2012

HOK partners with USGBC on design of Haiti children's center

Passive design principles give form to a sustainable, restorative environment for the children of Haiti.

| Jan 26, 2012

American Standard names Gould as president and CEO

Gould succeeds Don Devine, who led the successful turnaround of American Standard Brands.

| Jan 26, 2012

Summit Design+Build completes law office in Chicago

Applegate & Thorne-Thomsen's new office suite features private offices, open office area, conference rooms, reception area, exposed wood beams and columns, and exposed brick. 

| Jan 24, 2012

New iPad app ready for prime time

Siemens’ versatile application connects users to APOGEE BAS control and monitoring functions via wireless network connectivity. The application directly interacts with BACnet/IP and Siemens APOGEE P2 field panels. 

boombox1
boombox2
native1

More In Category

Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021