flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

A tableware storage space is reset to accommodate an investment firm’s headquarters in Raleigh, N.C.

Adaptive Reuse

A tableware storage space is reset to accommodate an investment firm’s headquarters in Raleigh, N.C.

This adaptive reuse establishes more direct visual and physical connections to a growing city. 


By John Caulfield, Senior Editor | October 23, 2017

Gensler led the Building Team that converted a 16,000-sf former storage facility into a new headquarters space for Investors Management Corporation, one of several old buildings that have been transformed during a recent redevelopment spurt in Raleigh, N.C. Image: Chris Leonard/courtesy of Gensler 

Raleigh, N.C., is in the midst of a development boom. Since 2005 through July of this year, this metro has added 3,672 residential units, 1,000 hotel rooms, 346,000 sf of retail space and 1.5 million sf of office space downtown.

The Raleigh-Durham metroplex has seen more than $3.3 billion of investment in 250 miles of highway infrastructure, $3.2 billion last year in new capital investments, and more than 30,000 new jobs announced in 2016.

One of the companies that’s been part of this boom is Investors Management Corporation, a small investment firm that purchased a 16,000-sf building from CE Rental that once served as a storage facility for dishes, tables and dining products, with the intention of converting this space into IMC’s new headquarters.

“The entire district in which this building is located is undergoing massive change, with many old warehouses finding new life,” observes Michael Wagner, architect and Associate at the Raleigh office of Gensler, architect and designer on IMC’s adaptive reuse.

The IMC project is one of those case studies where location seemed to trump just about everything else. The building is on hilltop site that overlooks downtown Raleigh. But IMC had acquired a building that was a half-century old, prefabricated, uninsulated, and backed up onto a railroad line. Adding to this renovation’s complexity was the tight scheduling IMC required because the lease on the company’s old headquarters building was expiring.

“The client gave us a great charge in finding the ‘worst building with the best view.’ So we did,” says Chad Parker, Principal and Co-Managing Director at Gensler’s Raleigh office.

The Building Team—which included Optima Engineering (MEP), Lynch Mykins (SE), and Stewart (CE and landscape architect)—maintained the two-story building’s exposed structural members and cross bracing, as well as its existing brick façade. By limiting more elaborate changes to the building’s infrastructure, the team was able to use the North Carolina Rehabilitation Code and, therefore, save time and money.

“The intent from the start was to repurpose as many existing materials and finishes as possible.” recalls Wagner.

The location of this building informed its floor plan. Gathering spaces, initially intended for the lower levels, were moved to level two, where the design team added a large outdoor porch that creates a visual connection between IMC’s headquarters and the buildings within the city center and north of downtown.

 

A linear skylight and clerestory running along the north-south axis lets more natural light into the building. Image: Chris Leonard/courtesy of Gensler

 

Because the back wall of the building bumps up against the property line, building codes prohibited glass on the rear façade. So to bring more natural light into the building, the Building Team installed a linear skylight and clerestory along the length of the brick-clad, single-story volume. Large glass openings along the building’s east façade replace eight- by eight-ft rollup garage doors, creating a direct connection to the outdoors.

The building, which dates back to at least 1981 according to tax records, was pretty barebones before its recent transformation, according to Wagner. It had no insulation in the roof or the wall. Off-the-shelf metal wall panels on girts had no interior finishes. All masonry walls were single wyeth, without insulation.

The Building Team added insulation inboard to the exterior face of wall when new interior framing and sheetrock were installed. The brick and metal panels were painted, but all weatherproofing, including an air barrier and batt insulation, was handled on the interior side of the existing wall.

The existing metal roof was left in place, and now provides the substrate for a new roof system that includes R-30 polyiso insulation as well as a new standing seam galvalume metal roof.

 

An open deck lets workers take a break outdoors and provides views of downtown Raleigh. Image: Chris Leonard/ courtesy of Gensler

 

To open the volume within the space, the Building Team demolished a wood frame interior mezzanine and two full-height CMU partition walls running perpendicular to the overall geometry of the building.

It also removed an existing freight elevator, and filled the hole in the second floor slab. The new framing for this infill became the center of the new reception space on level one. The existing stairs to the second level were repurposed, rotated 180 degrees, and reattached to the existing slab edge on level two.

The entire interior received new finishes. And the existing concrete floor was leveled to bridge a 2-inch offset in floor slabs, the result of previous building additions. A new exterior egress stair was added to the building’s south end.

 

The gathering spaces within the headquarters were moved to the second level. Image: Chris Leonard/courtesy of Gensler

 

Wagner says that any further expansion to IMC’s new headquarters would have to be vertical and would also need to satisfy future parking demands on a site where parking is already limited. 

This project was completed in early 2016. Several of IMC’s employees were allowed to move into the building the previous fall under a temporary certificate of occupancy. There are currently around 25 IMC employees working in the building.

Related Stories

Adaptive Reuse | Oct 26, 2020

Mall property redevelopments could result in dramatic property value drops

Retail conversions to fulfillment centers, apartments, schools, or medical offices could cut values 60% to 90%.

Adaptive Reuse | Oct 22, 2020

A Los Angeles design firm reimagines urban workplaces, multifamily buildings, and warehouses

Omgivning conjures varieties of adaptive-reuse concepts.  

Adaptive Reuse | Jul 29, 2020

Two Indianapolis schools find new digs in a long-dormant factory

Adaptive reuse preserved many of the building’s original features.

Coronavirus | May 18, 2020

Will empty hotels provide an answer for affordable housing shortage?

A Los Angeles-based startup sees the Midwest as most fertile for adaptive reuse.

Adaptive Reuse | Jun 11, 2019

The power and possibility of adaptive reuse

Building reuse generally offers greater environmental savings than demolition or new construction.

Adaptive Reuse | Jul 9, 2018

Work, park, live: Inside Cincinnati’s parking garage turned lifestyle hotel

The Summit hotel and conference center is a converted parking garage that was once a factory.

Office Buildings | Jun 6, 2018

Final Cut: Jupiter Entertainment’s new production studio in New York combines office and editing spaces

The project team completed this full-floor renovation in four months.

boombox1
boombox2
native1

More In Category


MFPRO+ News

San Francisco unveils guidelines to streamline office-to-residential conversions

The San Francisco Department of Building Inspection announced a series of new building code guidelines clarifying adaptive reuse code provisions and exceptions for converting office-to-residential buildings. Developed in response to the Commercial to Residential Adaptive Reuse program established in July 2023, the guidelines aim to increase the viability of converting underutilized office buildings into housing by reducing regulatory barriers in specific zoning districts downtown. 



halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021