Underfloor air distribution, how to get the details right

Underfloor air distribution, how to get the details right

Our experts provide solid advice on the correct way to design and construct underfloor air distribution systems, to yield significant energy savings.


By By Peter Fabris, Contributing Editor | August 19, 2011
UFAD system from Tate Access Floors at Great River Energys LEED Platinum headquarters.
This article first appeared in the August 2011 issue of BD+C.

Raised flooring was introduced years ago for use in data centers, where the ability to easily move power and data cabling under the floor was a big plus. At the time, it was not unusual for raised floors to have less than a solid feel; this was chiefly due to thin floor panel material, which often resulted in a squeaky, hollow sound as occupants walked on the floor. Contractors were not accustomed to the demands of raised-floor construction, leading to poor performance.

Today, general contractors and subcontractors have the know-how to install these systems to high standards. Properly installed, raised flooring feels as sturdy as any other flooring, and underfloor air distribution (UFAD), often combined with air displacement ventilation, is gaining acceptance among building owners and designers. “Ten or twelve years ago, UFAD was perceived as risky, but not anymore,” says David Atwood, general manager of Boston-based contractor Integrated Interiors. “On major gut rehabs or new construction, it is getting more consideration than we’ve ever seen.” (Note: For the purposes of this article,  “UFAD” is used interchangeably with “underfloor air displacement ventilation.”)

APPLICATION IN NUMEROUS BUILDING TYPES

The UFAD technology’s multiple advantages make it an increasingly popular choice for a variety of building types, including offices, schools, college classrooms, libraries, casinos, and, of course, data centers.

UFAD can help reduce the amount of construction materials used in a project, particularly on high-rise projects. Unlike overhead HVAC, underfloor heating and cooling uses little ductwork, so the amount of sheet metal used is greatly reduced. Moreover, the elimination of overhead ducts means plenum heights can be reduced by six inches or more per floor. “We have modeled an 11-story building, and it gained an entire floor from the reduced plenum heights,” Atwood says. The savings on structural steel, envelope elements, and curtain wall materials adds up as building height increases.

One of the most important benefits of raised floor systems is that they can easily be reconfigured by moving floor tiles and diffusers to different locations, and cabling can be accessed and moved easily under the floor. As a result, maintenance staff can rearrange workstations for new tenants without drilling holes and disassembling portions of the ceiling. In an office building with high tenant turnover, the resulting savings in labor costs over the years can be considerable. And because floor outlets are easy tomove, there’s no need to buy cubicles with power outlets, which cost considerably more than nonpowered units.

UFAD systems use much lower static air pressure to heat or cool a space than conventional overhead HVAC systems. Thus, the power needed to run fans is reduced, thereby saving energy. Some UFAD manufacturers claim that total HVAC power savings can be as much as 20-30% compared with overhead systems, but that’s probably overstating the case, according to Tom Webster, research specialist with the Center for the Built Environment at the University of California, Berkeley. He says that, in a typical office environment, the CBE has measured HVAC energy savings from UFAD systems in the 10-15% range under ideal conditions using currently available technology. Still, 10-15% energy savings is nothing to sneeze at.

However, Webster cautions that because no two buildings are alike, it is extremely difficult to compare the energy use of an overhead system with a UFAD system. Variables such as climate, ceiling height, system configuration, and the presence of other energy-conserving elements in the building complicate the equation. One thing is clear, says Webster: cooling climates will reap higher energy savings than heating climates from UFAD.

With some tweaking, it is possible to improve UFAD energy performance, Webster adds. If diffusers are positioned just right on the floor, and if occupants and maintenance staff adjust the diffusers properly—actions more honored in the breach than in the observance—greater energy savings can be realized.

UFAD systems may also contribute to improved thermal comfort and air quality. Surveys have shown a higher rate of satisfaction when occupants have more control over heating and cooling of their individual spaces, and some studies have found improved productivity in UFAD buildings. One reason: lower static air pressure means much less air mixing compared with overhead systems. Thus, when someone sneezes, germs don’t travel as far as they would in an overhead system. That’s one reason that UFAD can contribute to a LEED credit for indoor air quality.

FIRST COST VS. LIFE CYCLE COST

The question of first cost vs. life cycle cost for UFAD systems is somewhat controversial and depends on what assumptions are being made. UC Berkeley’s Center for the Built Environment says that its baseline assumptions yielded a cost premium of $3.50/gsf between the median UFAD system and the baseline overhead system. In cases where the owner or designer calls for a raised floor to make moving cabling and power lines easier, however, installing UFAD may prove less costly than going overhead, according to the CBE’s Webster. When all cost factors are accounted for over the life of a building, it is possible for UFAD to come out ahead in total cost of ownership. But, again, it depends a lot on the assumptions that have gone into the calculation.

It is also the case that, with the exception of total gut renovation projects, underfloor air distribution systems are usually cost-prohibitive for reconstruction projects. Perhaps the biggest possible downside to the technology, though, is that improper installation will reduce system efficiency, raise energy costs, and reduce thermal comfort for occupants. While it doesn’t take a genius to install UFAD correctly, it does mean that general contractors and the building trades must pay attention to the details.

Here, according to experts consulted for this article, are a number of factors to keep in mind when employing underfloor air distribution systems in your projects.

KEYS TO PROPER UFAD INSTALLATION

Proper installation of UFAD systems requires attention to detail, rigorous scheduling, and job site cleanliness—all responsibilities that fall primarily on the general contractor, who must educate all the members of the Building Team and ensure that the certain critical factors are addressed.

Develop an efficient layout. Projects that don’t take this crucial first step may run into interface conflicts and poor coordination among the trades. Here’s where BIM/3D models may streamline the process.

Finish the overhead work first. Coordinate construction trades to get most overhead work out of the way as early as possible. Scissor lifts, staging, and ladders all pose a safety risk when working around exposed floor openings.

Educate your subcontractors. Subcontractors must understand that they are working in areas that will become part of the air delivery system. Work cleanliness and the proper sealing of all penetrations are essential to whole building performance.

Get the flooring team in early. Flooring teams should be involved right after the concrete slab is poured. Most floor plans for UFAD projects incorporate a blend of raised flooring and conventional concrete slabs. Merging a raised flooring system with a fixed concrete slab requires a thorough survey and tactical benchmarking. The slab may directly meet the raised floor around the building core, such as near the elevators, and concrete may have to be ground down to provide an even seam.

Draw a map. Mark out a dot grid with spray paint on the slab to identify where pedestal bases are to be located within the floor plate. Skipping this step can lead to installation conflicts. “You don’t want to locate diffusers under a piece of furniture,” warns Scott Alwine, LEED AP, with Tate Access Floors, Jessup, Md.

Position cutouts and power service correctly. After studying the floor plate design and furniture layout, the team must maintain close communication with the panel manufacturer so that cutouts, where power and data lines will enter, are properly located. With floor panels installed, electrical and mechanical trades can install service boxes with power and data cabling guided through pre-cut openings in floor panels.

Eliminate gaps in the floor. Rigorous quality controls should be in place to ensure that there are no gaps in the underfloor air plenum. “You have to make sure everything under the floor is sealed,” Alwine says. “That includes utility closets, where cabling comes through the floor, where the floor meets the elevator, and around columns.”

Make sure the final layer of flooring is perfect. There are many choices of finishes on raised floor tiles, including terrazzo and synthetic materials, but carpet tiles that overlap the seams of floor panels are the most common. The carpet installer should use the minimum amount of adhesive necessary, so that the tiles can be removed easily when access to the underfloor is needed. “You also want to make sure that the carpet tiles line up with the floor panels for easy removal and replacement,” Alwine says. BD+C

 

UFAD Contributes to Office Building’s LEED Platinum Rating

Great River Energy’s 165,000-sf LEED Platinum headquarters in Maple Grove, Minn., is a showcase for green building systems, including underfloor air distribution. Heating and cooling are fed by a geothermal system from the waters of neighboring Arbor Lake.

“It may be the first time that geothermal has been combined with underfloor displacement ventilation in the U.S.,” says Doug Pierce, AIA, LEED AP, a senior associate with the Minneapolis office of architect Perkins+Will. Air is delivered at a constant 67?F. “During many days in spring and fall, there is very little use of compressors, saving a fair amount of energy,” he says.

UFAD with displacement ventilation helped the project earn a LEED point for indoor air quality. “To earn that point, you have to provide 30% more fresh air than the ASHRAE baseline,” Pierce says. Displacement ventilation is 20% more effective at delivering fresh air to the breathing zone than conventional mixing systems. Thus, you only need to bring in another 10% more fresh air to deliver a total 30% more fresh air to the occupant space as compared to conventional mixing ventilation systems.

Having the raised floor also made it more economical to specify 10-foot ceilings—a foot higher than usual—to enhance the daylighting in the building. “We used a post-tension slab that provided a total structural depth of only 10 inches,” Pierce says. Normally, he says, his firm would not recommend a post-tension system for institutional clients because such systems are hard to core drill for future services, and you end up with a 30-inch-deep structural system. With the raised floor, he says, “cabling and utilities could be moved around easily, so we used the post-tension slab, resulting in a high ceiling and floor-to-floor heights that were just a little less than typical.” As a result, the design gained an extra foot of interior height without increasing the exterior wall height.

Related Stories

Engineers | Jun 14, 2023

The high cost of low maintenance

Walter P Moore’s Javier Balma, PhD, PE, SE, and Webb Wright, PE, identify the primary causes of engineering failures, define proactive versus reactive maintenance, recognize the reasons for deferred maintenance, and identify the financial and safety risks related to deferred maintenance.

University Buildings | Jun 14, 2023

Calif. State University’s new ‘library-plus’ building bridges upper and lower campuses

A three-story “library-plus” building at California State University, East Bay (CSUEB) that ties together the upper and lower campuses was recently completed. The 100,977-sf facility, known as the Collaborative Opportunities for Research & Engagement (“CORE”) Building, is one of the busiest libraries in the CSU system. The previous library served 1.2 million visitors annually.

Higher Education | Jun 14, 2023

Designing higher education facilities without knowing the end users

A team of architects with Page offers five important factors to consider when designing spaces for multiple—and potentially changing—stakeholders.

Resiliency | Jun 14, 2023

HUD offers $4.8 billion in funding for green and resilient building retrofit projects

The Department of Housing and Urban Development (HUD) recently released guidelines for its Green and Resilient Retrofit Program (GRRP) that has $4.8 billion for funding green projects.

Arenas | Jun 14, 2023

A multipurpose arena helps revitalize a historic African American community in Georgia

In Savannah, Ga., Enmarket Arena, a multipurpose arena that opened last year, has helped revitalize the city’s historic Canal District—home to a largely African American community that has been historically separated from the rest of downtown.

Building Materials | Jun 14, 2023

Construction input prices fall 0.6% in May 2023

Construction input prices fell 0.6% in May compared to the previous month, according to an Associated Builders and Contractors analysis of the U.S. Bureau of Labor Statistics’ Producer Price Index data released today. Nonresidential construction input prices declined 0.5% for the month.

Mass Timber | Jun 13, 2023

Mass timber construction featured in two-story mixed-use art gallery and wine bar in Silicon Valley

The Edes Building, a two-story art gallery and wine bar in the Silicon Valley community of Morgan Hill, will prominently feature mass timber. Cross-laminated timber (CLT) and glulam posts and beams were specified for aesthetics, biophilic properties, and a reduced carbon footprint compared to concrete and steel alternatives.

Mixed-Use | Jun 12, 2023

Goettsch Partners completes its largest China project to date: a mixed-used, five-tower complex

Chicago-based global architecture firm Goettsch Partners (GP) recently announced the completion of its largest project in China to date: the China Resources Qianhai Center, a mixed-use complex in the Qianhai district of Shenzhen. Developed by CR Land, the project includes five towers totaling almost 472,000 square meters (4.6 million sf). 

Engineers | Jun 12, 2023

Stantec to acquire Environmental Systems Design

Stantec, a global leader in sustainable design and engineering, has signed an agreement to acquire Environmental Systems Design, Inc. (ESD), a 270-person engineering firm headquartered in Chicago. Founded in 1967, ESD has built a reputation for excellence and innovation in high-performance design with a roster of industry-leading clients. The terms of the transaction are not disclosed.

University Buildings | Jun 9, 2023

Cornell’s new information science building will foster dynamic exchange of ideas and quiet, focused research

Construction recently began on Cornell University’s new 135,000-sf building for the Cornell Ann S. Bowers College of Computing and Information Science (Cornell Bowers CIS). The structure will bring together the departments of Computer Science, Information Science, and Statistics and Data Science for the first time in one complex.

boombox1
boombox2
native1

More In Category


Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.



Libraries

Reasons to reinvent the Midcentury academic library

DLR Group's Interior Design Leader Gretchen Holy, Assoc. IIDA, shares the idea that a designer's responsibility to embrace a library’s history, respect its past, and create an environment that will serve student populations for the next 100 years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021