200 Fillmore

200 Fillmore

Denver, Colorado


By Maggie Koerth-Baker | August 11, 2010
This article first appeared in the 200610 issue of BD+C.

Built in 1963, the 32,000-sf 200 Fillmore building in Denver housed office and retail in a drab, outdated, and energy-splurging shell—a “style” made doubly disastrous by 200 Fillmore's function as the backdrop for a popular public plaza and outdoor café called “The Beach.”

In 2005, the owner, Western Development Group, determined to pluck 200 Fillmore out from its Class C office space doldrums. To do that, a Building Team headed by the Denver office of Chicago firm 4240 Architecture came up with three goals: maximize the leasable area, improve the building's energy usage, and enhance the appearance of The Beach.

The team ran head-on into problems. First, they discovered the building already exceeded zoning limits on area, so any expansion had to stay within the building's original footprint. Their best option for expansion, then, lay in the cantilevered concrete slab that extended around the outside as part of the original façade. Field tests showed the slab could support a new exterior wall, but only one weighing less than 10 pounds per face square foot. The solution: A terra cotta rainscreen system that gave the building an inviting appearance at a low weight.

This part of the project required better-than-average organizational skills. The terra cotta tiles were not flat, nor did they have clean, straight edges. To make sure the rainscreen was installed with a 3/16-in. joint throughout, the team experimented with a full-size mockup. All this was going on even as ground-floor retail was open and the upper three floors were gutted.

Bumping up the building's energy efficiency led the Building Team to, of all places, the restrooms, which had claustrophobically low seven-foot ceilings that were constrained by undersized air handler units stored in the space above. The team junked those floor-based units in favor of one large roof unit that served the whole building. The result was not only a more efficient HVAC system, but also a person-friendly restroom design—with ceiling heights raised to eight feet.

Improvements to The Beach include tall grasses and seasonal flower landscaping that wrap around the retail and plaza edge. A new wood and steel entry canopy complements the terra cotta rainscreen and steel window treatments, while simultaneously connecting the lobby and outdoors and reducing the building's scale.

All these changes resulted in a radically different building—both inside and out. Gone is the '60s-era façade with its set-back windows framed by a mesh grille and crossed by vertical support bars. In its place are new flush windows on the second and third floors, and a balcony on the fourth floor, which is now residential space for the building's owner. Horizontal trim at the tops of the windows mimic the balcony's railing system.

The Building Team was able to accomplish this complete overhaul—from original design to completed construction—in 12 months. Although the project went $300,000 (7.5%) over the original $4 million budget, the overrun was negated by the fact that the new 200 Fillmore was fully leased on opening day.

Related Stories

Office Buildings | Jan 11, 2019

Open offices are bad!

The Harvard studies on the unintended effects of open office defines it as space where 'one entire floor was open, transparent and boundaryless… [with] assigned seats,' and the other had 'similarly assigned seats in an open office design, with large rooms of desks and monitors and no dividers between people's desks.'

Office Buildings | Dec 18, 2018

Google announces new $1B Hudson Square campus project

The 1.7 million-sf campus will expand the company’s New York City presence.

Office Buildings | Dec 13, 2018

Apple selects Austin for $1 billion campus

The company will also build smaller expansions in six other U.S. cities over the next three years.

Office Buildings | Dec 4, 2018

Brookfield launches contest for startups to receive two years of free office space

This is part of a larger campaign to burnish the image of L.A.’s Wells Fargo Center. 

Office Buildings | Nov 28, 2018

Amazon HQ2 and the new geography of work

The big HQ2 takeaway is how geography and mobility are becoming major workplace drivers.

Office Buildings | Nov 13, 2018

Amazon selects HQ2 cities

Both cities are on the East Coast.

Mixed-Use | Oct 25, 2018

Philadelphia’s uCity Square kicks off major expansion drive

This innovation center has several office, lab, and residential buildings in the works.

Office Buildings | Oct 25, 2018

Stantec consolidates three Portland-area offices into one downtown location

Stantec worked with Ankrom-Moisan Architects on the design.

boombox1
boombox2
native1

More In Category



Sustainable Design and Construction

Northglenn, a Denver suburb, opens a net zero, all-electric city hall with a mass timber structure

Northglenn, Colo., a Denver suburb, has opened the new Northglenn City Hall—a net zero, fully electric building with a mass timber structure. The 32,600-sf, $33.7 million building houses 60 city staffers. Designed by Anderson Mason Dale Architects, Northglenn City Hall is set to become the first municipal building in Colorado, and one of the first in the country, to achieve the Core certification: a green building rating system overseen by the International Living Future Institute.


MFPRO+ News

San Francisco unveils guidelines to streamline office-to-residential conversions

The San Francisco Department of Building Inspection announced a series of new building code guidelines clarifying adaptive reuse code provisions and exceptions for converting office-to-residential buildings. Developed in response to the Commercial to Residential Adaptive Reuse program established in July 2023, the guidelines aim to increase the viability of converting underutilized office buildings into housing by reducing regulatory barriers in specific zoning districts downtown. 

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021