flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

2019 Reconstruction Awards: The 1060 Project at Wrigley Field

Reconstruction Awards

2019 Reconstruction Awards: The 1060 Project at Wrigley Field

Venerable Wrigley Field is raised up in a top-to-bottom restoration that took five years to complete.


By John Caulfield, Senior Editor | November 8, 2019
Wrigley field looking to the northeast

Wrigley Field, looking northeast toward Lake Michigan. Two new digital scoreboards flank the traditional scoreboard whose numbers are manipulated by hand. All photos: Mark Ballogg/Ballogg Photography.

Wrigley Field, the second-oldest baseball stadium in the country, opened in 1914. Soon after the Ricketts family purchased the ballpark and its main tenant, the Chicago Cubs, in 2009, plans were set in motion to significantly upgrade the deteriorating structure, expand the facility, and enhance its amenities.

The project was ambitious, and the list of improvements extensive: improving the building’s foundation, restoring and reinforcing the core structure, rebuilding the bleachers, restoring the historic marquee, reconstructing the façade, upgrading player facilities, adding premier clubs and fan amenities, improving concession and restroom availability, installing new digital outfield signage and video boards, adding modern media facilities, and converting the parking lot into a plaza and six-story office building with a new underground clubhouse.

All of this was accomplished over a five-year period during the 20 to 26 weeks per year of off season, many of those weeks in frigid weather conditions. In 2018, the project team reorganized the remaining work and expedited the schedule by one year, which meant that nearly half of the overall project volume had to be completed in the last two years.

 

The 1914 Club at Wrigley FieldThe ceiling of the 1914 Club under home plate has a ribbed metal underlayment that will drain any condensation to the edges to prevent water damage to the room. 

 

Planning under such constraints was critical. This project required eight years of preconstruction that didn’t end until the final phase of construction began last year. When considering the basement and new Cubs clubhouse under the former parking lot, the team explored more than 50 different sizes, layouts, and configurations, as well as associated structural materials. Throughout the design and construction, the project team relied heavily on laser scanning and 3D modeling.

The most critical part of the project was strengthening the building’s foundation to accommodate the planned expansion. Wrigley Field was essentially lifted onto stilts while the foundations and column supports were restored, vastly augmenting the ballpark’s foundational load capacity. Pepper Construction, the project’s GC, sunk four micropiles at each of the “F” line major columns to a depth of 100 feet under each column before welding on a new zero-tolerance column base. Each micropile could withstand 500,000 pounds of force; one micropile is strong enough to hold the 225-ton Statue of Liberty.

 

See Also: 2019 Reconstruction Awards: Betting on a city's future

 

Among the key elements of the stadium’s restoration, which required considerable re-engineering, was the Concourse, which loops around Wrigley Field beginning in the main grandstand and through the bleachers. A detailed sequence was developed to restore and expand the 40,000-sf mezzanine across the ballpark and two serpentine walkways while simultaneously repairing the underbelly of the ballpark’s concrete structure. A massive, 400-foot-long by eight-foot-tall grade beam, sitting on more than 90 micropiles along the western edge of the ballpark, was installed to redistribute the expanded load of the upper level concourse and stabilize soil conditions between the ballpark and the plaza.

 

The restored concourse at Wrigley FieldThe restored concourse (below) would not have been possible without the project team’s colossal efforts to improve Wrigley Field’s antiquated structural system.

 

Each year during construction periods, the concourse walkway had to be ripped out to work on below-grade areas that house mechanicals, plumbing, AV equipment, and underground utilities. Once the underground work was completed, the overhead piping could also be reconstructed.

The entire exterior ballpark façade was restored to the glory days of the 1930s. The original brick features, sunburst-patterned steel grille work, and the restored historic marquee were reintroduced. The stucco and clay tile and terra cotta roofing covered the entire ballpark façade, including the expanded left- and right-field terraces.

Added to Wrigley was Gallagher Way plaza, a new six-story, two-basement facility adjacent to the ballpark. The first two floors provide retail space, the third floor is for conference rooms, and floors 4-6 serve as the Cubs’ offices. A new 30,000-sf clubhouse, located outside the ballpark under the plaza, provides the players with the best-in-class off-the-field facilities needed to train, rehabilitate from their injuries, and prepare for games.

 

Platinum Award Winner

BUILDING TEAM Pepper Construction (submitting firm, GC) The Ricketts Family (owner) CAA ICON (owner’s representative) Populous, Stantec (architects) Thornton Tomasetti (SE) ME Engineers (ME) Terra Engineering (CE) Details 970,000 sf Total cost Confidential at owner’s request Construction time October 2014 to April 2019 Delivery method CM at risk

Related Stories

Reconstruction Awards | Nov 26, 2019

Sweetest sounds: Metropolitan Opera House

An early 20th-century opera house now hosts concerts from Disney Acapella to Weezer.

Reconstruction Awards | Nov 25, 2019

The University of Chicago Harris School at the Keller Center

Project team goes all out for LEED Platinum and the Living Building Challenge.

Reconstruction Awards | Nov 22, 2019

Let there be light: Union Station Great Hall

What’s the cure for a leaky skylight? Another skylight built above it, of course.

Reconstruction Awards | Nov 21, 2019

Temporary quarters: Senate of Canada Building

Canada’s Senate gets an interim home in what was once the capital’s main train station.

Reconstruction Awards | Nov 19, 2019

Springfield Technical Community College: Goodbye to 'the shuffle'

College unites student services under one roof.

Reconstruction Awards | Nov 18, 2019

The Paint Factory: Not just a new coat of paint

An enlightened A/E firm is spurring redevelopment in an old industrial section of Little Rock.

Reconstruction Awards | Nov 15, 2019

Back on track: Union Terminal renovation and restoration

Painstaking care went into restoring Cincinnati’s train terminal/museum complex.

Reconstruction Awards | Nov 14, 2019

Museum at the Gateway Arch: Subterranean sensation

The project team used its creativity to overcome floods and other obstacles to construction.

Reconstruction Awards | Nov 13, 2019

Zachry Engineering Education Complex: Rethinking engineering education

Texas A&M’s engineering school builds for future growth.

Reconstruction Awards | Nov 12, 2019

Linode Headquarters: High-tech + historic

New headquarters mixes old and new to help this fast-growth company attract top talent.

boombox1
boombox2
native1

More In Category


Giants 400

BD+C Awards Programs

Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400



halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021