Are contractors collecting what they need to make better decisions?

Contractors

Are contractors collecting what they need to make better decisions?

Research focused on five key types of data: project progress, manhours, productivity, safety, and equipment management.


By John Caulfield, Senior Editor | October 17, 2019

A new report on how contractors collect and use jobsite data is based on responses from 187 companies. Image: Dodge Data & Analytics.

More than half of contractors say their methods of collecting and analyzing data from their jobsites need to get better over the next three years, in part for their companies to use these data to predict employee and project performance.

That’s a key finding in a new 40-page SmartMarket report that Viewpoint and Dodge Data & Analytics have released, entitled
“Improving Performance with Project Data.”

The report is based on an online survey conducted from August 14, 2017, through September 12, 2018. The survey used Dodge’s Contractor Panel and contacts provided by Viewpoint. Of its 187 respondents, 98 were GCs, 47 specialty trade contractors, 28 construction managers, nine design-build firms, and four design-contracting firms. Thirty-seven percent of respondent companies generate revenues between $50 million and $250 million.

The research focused on five key types of data: project progress, manhours, productivity, safety, and equipment management.

Respondents were asked how they gather, store, manage, secure, analyze, and report on each of these types of data. Key trends include a rapid shift away from paper-based forms, reports, and spreadsheets to digital tools and platforms, some that leverage cloud technology; increasing use of apps on mobile phones and digital cameras in the field; the desire for more accurate field data that enables trends analysis across projects; and a focus on data security.

More than three-fifths of the contractors surveyed say they’ve seen improvements in their data gathering and analysis capabilities over the past three years. That’s especially true among larger companies. By far, the most important project data being gathered is performance information such as scheduling and costs, followed by payroll and manhour data.

The top-three benefits from data analysis, say contractors polled, are improving their ability to complete projects at or under budget (53%), greater productivity (47%), and greater profitability (46%).

However, more than half of the respondents (54%) admitted that they need to improve how they gather jobsite information over the next three years. And 45% think their ability to analyze trends across projects must get sharper, too, as well as their ability to gather current data from the field.

Relying on physical records, like paper forms, for data collection is steadily giving way among contractors to custom-designed or commercial software, a trend that is likely to be more prevalent over the next three years. Nearly three-quarters of respondents say they were satisfied with using software as a way to collect data.

Most pros (65% of the ones polled) still store their digital information in on-premise servers. But 37% have turned to third-party cloud providers, such as Amazon, to host their field information. The benefits of using the cloud are manifold, the most prominent being the ability to access data from the field while working in the office or remote locations, and vice versa.

Well over half of the contractors surveyed deploy mobile phone apps and cameras to collect and send data from the field. Expect that wave of data to rise, as drones, sensors, and wearables gain more traction as jobsite tools. However, contractors are also acutely aware of how their use of devices presents security risks. That explains why 86% of contractors say they are using anti-malware software, 78% are using enterprise-grade firewalls, and 56% have imposed policies for managing the use of mobile devices.

 

a plan to gather data

More than one-fifth of contractors surveyed have had experience with predictive analysis of data and business intelligence. That compares with just 7% for artificial intelligence and 6% for machine learning. The largest group of respondents noted they are aware of and understand the concepts of each of these emerging technologies but have not implemented them in their own organizations—39% for predictive analysis, 47% for artificial intelligence, and 33% for machine learning.

But it is clear that technology is advancing faster than the AEC industry’s ability to assimilate it. The report’s authors offer a multi-step process to structure a company’s data collection, analysis, and reporting.

• Determine what aspects of project delivery would benefit most from better information to guide your data strategy.

• Identify which types of field data will best-enable the proper analysis to generate critical decision-support information. And think about the minimum level of completeness, accuracy, and timeliness required for each type.

• Develop a focused technology and plan for collection and analysis that incorporates the specific data needed and types of analysis required, as well as financial and human capital investments, the time frames for implementation, clear roles of responsibility, and measurable goals for success.

The report includes two case studies—how Leander Construction is using the cloud to enhance productivity; and how W. Soule & Co. is using data to build better—as well as a Q&A with Jit Kee Chin, Suffolk Construction’s Chief Data Officer. Chin laments that what’s keeping AI from becoming a more efficient construction tool is the lack of useful data. Her viewpoint may explain why she sees “great potential” in automated monitoring.

Related Stories

| May 9, 2012

Construction Defect Symposium will examine strategies for reducing litigation costs

July event in Key West will target decision makers in the insurance and construction industries.

| May 8, 2012

WDMA and AAMA release window, door & skylight market studies

Historic data for 2006 through 2011 and forecast data for 2012 through 2015 are included in the report.

| May 8, 2012

Study presents snapshot of domestic violence shelter services

Unique partnership of architects and domestic violence advocates brings new strategies for emergency housing.

| May 8, 2012

Gensler & J.C. Anderson team for pro bono high school project in Chicago

City Year representatives came to Gensler for their assistance in the transformation of the organization’s offices within Orr Academy High School, which also serve as an academic and social gathering space for students and corps members.

| May 8, 2012

Skanska USA hires Zamrowski as senior project manager

In his new role at Skanska, Zamrowski will serve as the day-to-day on-site contact for select Pennsylvania-based projects during all phases of construction.

| May 8, 2012

Morgan/Harbour completes three projects at Columbia Centre

Projects completed on behalf of property owner, White Oak Realty Partners, LLC, Pearlmark Realty Partners, LLC and Angelo Gordon & Co.

| May 7, 2012

BIM in the academy

Lessons for the AEC industry.

| May 7, 2012

4 more trends in higher-education facilities

Our series on college buildings continues with a look at new classroom designs, flexible space, collaboration areas, and the evolving role of the university library.

| May 7, 2012

Best AEC Firms: MHTN Architects nine decades of dedication to Utah

This 65-person design firm has served Salt Lake City and the state of Utah for the better part of 90 years.

| May 7, 2012

2012 BUILDING TEAM AWARDS: TD Ameritrade Park

The new stadium for the College World Series in Omaha combines big-league amenities within a traditional minor league atmosphere.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021