ASHRAE/IES publish first standard focused on commissioning process

ASHRAE/IES publish first standard focused on commissioning process

Standard 202, an industry consensus document, includes specific tasks to be conducted to verify that a project meets the owner's requirements.


By ASHRAE | September 27, 2013

ATLANTA – A newly published standard focused on the commissioning process will help ensure a fully functional, fine-tuned facility.

ANSI/ASHRAE/IES Standard 202, Commissioning Process for Buildings and Systems, identifies the minimum acceptable commissioning process for buildings and systems as described in ASHRAE’s Guideline 0-2005, The Commissioning Process. Standard 202 is ASHRAE’s first standard focused on the commissioning process. The commissioning process as detailed in Standard 202 applies to all construction projects and systems and is an industry consensus document.

“Given the integration and interdependency of facility systems, a performance deficiency in one system can result in less than optimal performance by other systems,” Gerald Kettler, P.E., chair of the committee that wrote the standard, said. “Implementing the Commissioning Process is intended to reduce the project capital cost through the warranty period and also reduce the life-cycle cost of the facility. Using this integrated process results in a fully functional, fine-tuned facility, with complete documentation of its systems and assemblies and trained operations and maintenance personnel.”

The commissioning process assumes that owners, programmers, designers, contractors and operations and maintenance entities are fully accountable for the quality of their work. The process begins at project inception and continues for the life of a facility.

The process includes specific tasks to be conducted to verify that design, construction, verification, testing, documentation and training meet the owner’s project requirements, according to Kettler.

The standard defines the commissioning process through 13 functional steps, each of which contains deliverables. The commissioning activities and deliverable are as follows:

  • Initiate the Commissioning Process, including defining roles and responsibilities

  • Define the project requirements, which results in the  Owner’s Project Requirements (OPR) document

  • Develop commissioning plan – produces a written Commissioning Process Plan

  •  Plan design approach to Owners Project Requirements – defines the basis of design

  • Set contractor commissioning requirement, which are included in the commissioning specifications

  •  Design review by the commissioning authority provides feedback and a design review report

  • Submittals review verifies compliance with the OPR in a submittal review report

  • Observation  & Testing verifies system performance with results documented in construction checklists and reports

  • Issues resolution coordination is done with an issues and resolution log

  • Systems manual assembly results in a systems manual for building operation

  • Conduct training for building operations with training plans and records

  • Post occupancy operation commissioning provides an end of warranty commissioning report

  • Assembly of a commissioning report captures all the project commissioning documentation

Other commissioning guidance from ASHRAE includes Guideline 0-2005, The Commissioning Process;Guideline 1.1-2007, HVAC&R Technical Requirements for the Commissioning Process; and Guideline 1.5-2012, The Commissioning Process for Smoke Control Systems.

ASHRAE also is working on several other guidelines related to commissioning:  Guideline 0.2P, The Commissioning Process for Existing Systems and Assemblies; Guideline 1.2P, The Commissioning Process for Existing HVAC&R Systems; Guideline 1.3P, Building Operation and Maintenance Training for the HVAC&R Commissioning Process; and Guideline 1.4P, Procedures for Preparing Facility Systems Manuals.

The cost of ANSI/ASHRAE/IES Standard 202-2013, Commissioning Process for Buildings and Systems, is $72 ($61, ASHRAE members). To order, contact ASHRAE Customer Contact Center at 1-800-527-4723 (United States and Canada) or 404-636-8400 (worldwide), fax 678-539-2129, or visitwww.ashrae.org/bookstore.

ASHRAE, founded in 1894, is a building technology society with more than 50,000 members worldwide. The Society and its members focus on building systems, energy efficiency, indoor air quality, refrigeration and sustainability. Through research, standards writing, publishing, certification and continuing education, ASHRAE shapes tomorrow’s built environment today. More information can be found atwww.ashrae.org/news.

Related Stories

Resiliency | Jun 24, 2021

Oceanographer John Englander talks resiliency and buildings [new on HorizonTV]

New on HorizonTV, oceanographer John Englander discusses his latest book, which warns that, regardless of resilience efforts, sea levels will rise by meters in the coming decades. Adaptation, he says, is the key to future building design and construction.

Multifamily Housing | Jun 23, 2021

COVID-19’s impact on multifamily amenities

Multifamily project teams had to scramble to accommodate the overwhelming demand for work-from-home spaces for adults and study spaces for children. 

Architects | Jun 22, 2021

6 ways design can supercharge innovation in health sciences and medical education

It might sound radical, but the best way to achieve better collaboration is by eliminating traditional operational silos and the resulting departments.

K-12 Schools | Jun 20, 2021

Los Angeles County issues design guidelines for extending PreK-12 learning to the outdoors

The report covers everything from funding and site prep recommendations to whether large rocks can be used as seating.

Hotel Facilities | Jun 18, 2021

Adaptive reuse for hospitality, with Frank Cretella of Landmark Developers

In an exclusive interview for HorizonTV, Landmark Developers' President Frank Cretella talks about the firm's adaptive reuse projects for the hospitality sector. Cretella outlines his company's keys to success in hospitality development, including finding unique properties and creating memorable spaces.

Architects | Jun 16, 2021

BSB Design acquires California architectural firm Withee Malcolm

The acquisition marks a pivotal step in BSB Design’s long-term strategic plan.

Architects | Jun 15, 2021

Sandy Hook Permanent Memorial set to break ground

SWA Group designed the project.

Architects | Jun 15, 2021

Chicago Architecture Center and Chicago Architectural Club announce competition calling for new visions for State of Illinois “Thompson Center”

Competition seeks to give State of Illinois Center new life while preserving its architecture and public character.

Wood | Jun 10, 2021

Three AEC firms launch a mass timber product for quicker school construction

TimberQuest brand seeks to avoid overinvestment in production that has plagued other CLT providers.

Office Buildings | Jun 10, 2021

The future of the workplace is social clubs

Office design experts from NELSON Worldwide propose a new concept for the workplace, one that resembles the social clubs of the past. 

boombox1
boombox2
native1

More In Category


Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.



Libraries

Reasons to reinvent the Midcentury academic library

DLR Group's Interior Design Leader Gretchen Holy, Assoc. IIDA, shares the idea that a designer's responsibility to embrace a library’s history, respect its past, and create an environment that will serve student populations for the next 100 years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021