ASHRAE/IES publish first standard focused on commissioning process

ASHRAE/IES publish first standard focused on commissioning process

Standard 202, an industry consensus document, includes specific tasks to be conducted to verify that a project meets the owner's requirements.


By ASHRAE | September 27, 2013

ATLANTA – A newly published standard focused on the commissioning process will help ensure a fully functional, fine-tuned facility.

ANSI/ASHRAE/IES Standard 202, Commissioning Process for Buildings and Systems, identifies the minimum acceptable commissioning process for buildings and systems as described in ASHRAE’s Guideline 0-2005, The Commissioning Process. Standard 202 is ASHRAE’s first standard focused on the commissioning process. The commissioning process as detailed in Standard 202 applies to all construction projects and systems and is an industry consensus document.

“Given the integration and interdependency of facility systems, a performance deficiency in one system can result in less than optimal performance by other systems,” Gerald Kettler, P.E., chair of the committee that wrote the standard, said. “Implementing the Commissioning Process is intended to reduce the project capital cost through the warranty period and also reduce the life-cycle cost of the facility. Using this integrated process results in a fully functional, fine-tuned facility, with complete documentation of its systems and assemblies and trained operations and maintenance personnel.”

The commissioning process assumes that owners, programmers, designers, contractors and operations and maintenance entities are fully accountable for the quality of their work. The process begins at project inception and continues for the life of a facility.

The process includes specific tasks to be conducted to verify that design, construction, verification, testing, documentation and training meet the owner’s project requirements, according to Kettler.

The standard defines the commissioning process through 13 functional steps, each of which contains deliverables. The commissioning activities and deliverable are as follows:

  • Initiate the Commissioning Process, including defining roles and responsibilities

  • Define the project requirements, which results in the  Owner’s Project Requirements (OPR) document

  • Develop commissioning plan – produces a written Commissioning Process Plan

  •  Plan design approach to Owners Project Requirements – defines the basis of design

  • Set contractor commissioning requirement, which are included in the commissioning specifications

  •  Design review by the commissioning authority provides feedback and a design review report

  • Submittals review verifies compliance with the OPR in a submittal review report

  • Observation  & Testing verifies system performance with results documented in construction checklists and reports

  • Issues resolution coordination is done with an issues and resolution log

  • Systems manual assembly results in a systems manual for building operation

  • Conduct training for building operations with training plans and records

  • Post occupancy operation commissioning provides an end of warranty commissioning report

  • Assembly of a commissioning report captures all the project commissioning documentation

Other commissioning guidance from ASHRAE includes Guideline 0-2005, The Commissioning Process;Guideline 1.1-2007, HVAC&R Technical Requirements for the Commissioning Process; and Guideline 1.5-2012, The Commissioning Process for Smoke Control Systems.

ASHRAE also is working on several other guidelines related to commissioning:  Guideline 0.2P, The Commissioning Process for Existing Systems and Assemblies; Guideline 1.2P, The Commissioning Process for Existing HVAC&R Systems; Guideline 1.3P, Building Operation and Maintenance Training for the HVAC&R Commissioning Process; and Guideline 1.4P, Procedures for Preparing Facility Systems Manuals.

The cost of ANSI/ASHRAE/IES Standard 202-2013, Commissioning Process for Buildings and Systems, is $72 ($61, ASHRAE members). To order, contact ASHRAE Customer Contact Center at 1-800-527-4723 (United States and Canada) or 404-636-8400 (worldwide), fax 678-539-2129, or visitwww.ashrae.org/bookstore.

ASHRAE, founded in 1894, is a building technology society with more than 50,000 members worldwide. The Society and its members focus on building systems, energy efficiency, indoor air quality, refrigeration and sustainability. Through research, standards writing, publishing, certification and continuing education, ASHRAE shapes tomorrow’s built environment today. More information can be found atwww.ashrae.org/news.

Related Stories

| Apr 19, 2012

The 10 mistakes most likely to get you sued

The California Chamber of Commerce has produced a white paper cataloging the top 10 mistakes most likely to get a company sued. While a few of the laws cited apply specifically to California, some of them are federal and may apply in your state.

| Apr 19, 2012

Holcim cement plants recognized at PCA Spring Meeting

The Holly Hill plant received the PCA’s Chairman’s Safety Performance Award in recognition of their exceptional health and safety programs. The Theodore plant received the Environmental Performance Award in recognition of the steps they take beyond those required by laws, regulations and permits to minimize their impact on the environment.

| Apr 19, 2012

KTGY Group’s Arista Uptown Apartments in Broomfield, Colo. completed

First of eight buildings highlights unique amenities.

| Apr 19, 2012

Nauset begins work on $20M Joint Forces HQ at Hanscom AFB

3D imaging key to project timetable and cost containment.

| Apr 19, 2012

HBD Construction names Steven Meeks vice president

Meeks will provide expertise for the company in its many diverse areas of construction projects including health care, senior living, education and retail.

| Apr 18, 2012

Lafarge moving North American headquarters to Illinois

Lafarge CEO John Stull says the factors in their decision were location in the Midwest and area transportation.

| Apr 18, 2012

Positive conditions persist for Architecture Billings Index

The AIA reported the March ABI score was 50.4, following a mark of 51.0 in February; greatest demand is for commercial building projects.

| Apr 18, 2012

Syska Hennessy re-launches Information and Communication Technology practice

The ICT practice will focus a blend of products including Information Technology, Security, Audiovisual, Building Automation, Fire Life Safety, Medical Communications and Intelligent Building Systems.

| Apr 18, 2012

Perkins+Will designs new complex for Johns Hopkins Hosptial

The Charlotte R. Bloomberg Children’s Center and the Sheikh Zayed Tower create transformative patient-centric care.

| Apr 18, 2012

BBS Architects & Engineers acquires Ward Associates

The merged companies’ on-going project portfolio valued at $220 million.

boombox1
boombox2
native1

More In Category


Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.



Libraries

Reasons to reinvent the Midcentury academic library

DLR Group's Interior Design Leader Gretchen Holy, Assoc. IIDA, shares the idea that a designer's responsibility to embrace a library’s history, respect its past, and create an environment that will serve student populations for the next 100 years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021