Back on track: Union Terminal renovation and restoration

Reconstruction Awards

Back on track: Union Terminal renovation and restoration

Painstaking care went into restoring Cincinnati’s train terminal/museum complex.


By John Caulfield, Senior Editor | November 15, 2019
Union Terminal exterior

The restoration of Union Terminal and the massive fountain at its entrance took 2½ years. The rotunda spans 180 feet. Eight mosaic and 22 painted murals were restored. Photo: Brad Feinknopf.

After Cincinnati’s Union Terminal was completed, in 1933, it was deemed one of America’s most important Art Deco buildings. And certainly one of the more imposing. The rotunda alone spans 180 feet, making it the world’s second-largest half-dome (after the Sydney Opera House). Since the late 1990s, the terminal has been home to the Cincinnati Museum Center, a complex of six organizations that include a children’s museum and one devoted to natural history and science.

But Union Terminal had fallen on hard times. Its extensive renovation took 2½ years and over 1.1 million manhours to complete. To understand the terminal’s existing conditions, the reconstruction team conducted a 3D point cloud scan that generated 4.3 billion data points.

The project focused on restoring the integrity of the terminal’s structure and providing new mechanical systems. More than 478,000 pounds of ductwork were installed. A cooling tower ties into 23 new air handlers and three new centrifugal chillers. Five boilers were replaced.

Also replaced were eight structural steel beams in the ceiling of the children’s museum that had endured decades of water damage. Each beam weighed eight tons and was 40 feet long and 36 inches in height.

 

Inside Union Terminal with American flagPhoto: ©Cincinnati Museum Center. 

 

The terminal’s restoration also entailed:

• Removing and reassembling a massive fountain at the front of the building so that a waterproofing membrane could be installed.

• Applying 5,200 lbs of SonaKrete, an acoustical finish, to the rotunda’s interior wall before it was repainted.

• Replacing, restoring, or thoroughly cleaning 1,060 doors and 1,270 windows, as well as eight mosaic murals and 22 painted murals in the rotunda and exhibit wing.

Brick and stone were removed from the terminal’s façade and replaced once a watertight barrier was installed. A critical component of the project was the detailed coordination of opening up small sections to ensure a temporary weatherproofed system was in place without exposing the interior work.

 

GOLD AWARD WINNER

BUILDING TEAM Turner Construction (submitting firm, GC) Cincinnati Museum Center (owner) GBBN Architects (design architect) THP Limited (SE) The Kleingers Group (CE) Arup (MEP) Heapy Engineering (engineering consultant) John G. Waite Associates Architects (historic preservation contractor) DETAILS 500,000 sf Total cost $172.7 million Construction time July 2016 to November 2018 Delivery method CM at risk

Related Stories

Reconstruction Awards | Nov 11, 2016

Exclusive Chicago club re-emerges as a boutique hotel

Built in 1893 for the World’s Columbian Exposition, the CAA was an exclusive social club founded by leading figures in American sports and commerce.

Reconstruction Awards | Dec 1, 2015

Massive Chicago parking garage gets overdue waterproofing

Millennium Lakeside Garage, the largest underground parking facility in the U.S., hadn’t been waterproofed since the 1970s. The massive project took nearly 2½ years and 33,554 man-hours.

Reconstruction Awards | Nov 30, 2015

Washington Monument restored after 2011 East Coast earthquake

This restoration and repair project, which was completed under budget and eight days early (despite several setbacks), involved re-pointing 2.5 miles of mortar joints, repairing 1,200 linear feet of cracks, and installing 150 sf of Dutchman repairs. Construction took place from November 2011 to May 2014.

Reconstruction Awards | Nov 30, 2015

Denver's 107-year-old seminary campus modernized

The scope of the project included the seminary dorms, library, and chapel, all of which posed their own set of obstacles.

Reconstruction Awards | Nov 24, 2015

Center of I.M. Pei-designed plaza part of Washington redevelopment

The L’Enfant Plaza, a three-story below-grade mall, was renovated to include a new glass atrium pavilion and a 40-foot-long, interactive LED.

Reconstruction Awards | Nov 24, 2015

Manhattan's first freestanding emergency department a result of adaptive reuse

The Lenox Hill Healthplex, a restoration of the Curran O’Toole Building, has glass-block walls and a carefully preserved exterior.

Reconstruction Awards | Nov 19, 2015

Nave restored at Yale’s Sterling Memorial Library

Turner Construction and Helpern Architects revived the 150-foot-long nave, which was embellished with stained glass windows by G. Owen Bonawit, stone carvings by René P. Chambellan, and decorative ironwork by Samuel Yellin.

Reconstruction Awards | Nov 19, 2015

Infinite Chicago redevelopment bridges past to present

The renovation of three historic downtown buildings—the Gibbons and Steger Buildings and Pickwick Stables—includes a multi-level concrete walkway connection.

Reconstruction Awards | Nov 18, 2015

Sun Theater serves the youth of St. Louis

Lawrence Group and property owner TLG Beaux Arts raised $11 million to restore the 26,000-sf theater into a modern performance venue.  

Reconstruction Awards | Nov 17, 2015

Smithsonian Institution’s Arts and Industries Building again an exposition and museum space

After removing decades’ worth of unfortunate additions to expose 17 historic interior spaces for the National Historic Landmark, the Building Team zoned in on the client’s key concern.  

boombox1
boombox2
native1

More In Category


Giants 400

BD+C Awards Programs

Entry information and past winners for Building Design+Construction's two major awards programs: 40 Under 40 and Giants 400



halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021