Behind the scenes of integrated project delivery — successful tools and applications

Behind the scenes of integrated project delivery — successful tools and applications

The underlying variables and tools used to manage collaboration between teams is ultimately the driving for success with IPD.


By Megan Donham, Associate Consultant, CBRE Healthcare | September 7, 2014
Photo: Tomasz Sienicki via Wikimedia Commons
Photo: Tomasz Sienicki via Wikimedia Commons

In order to better understand the Integrated Project Delivery (IPD) Model, let’s take a metaphorical trip to a doctor’s office. 

Imagine we are having a wound treated, a wound that was caused by diabetes. During our visit, we are seen by an endocrinologist to help us better manage our diabetes. We are then seen by a Nutritionist to help manage and plan our meals based on our health needs. Lastly, before leaving, a pharmacist stops by to provide medications on the spot. 

Some of you may be wondering, “What does this have to do with IPD?” Well, in the above example, this type of cross-discipline, co-location, and utilization of expertise, or “integrated care team,” as some call it, is part of a recent paradigm shift that the healthcare industry is feeling nationwide. 

This shift can be viewed as analogous to the IPD model. While IPD is deemed transformational and revolutionary based on its ability to mine risk through financial incentive, contracted in an Integrated Form of Agreement or Tri-Party Agreement (an agreement between the owner, architect, and contractor), it is how the three parties collaboratively work together. The underlying variables and tools used to manage collaboration between teams is ultimately the driving for success with IPD.

 

DAY-TO-DAY TOOLS FOR IPD

To ensure goals are met, it is imperative that teams identify and utilize an effective structure to hold every member accountable to a near-term degree. In project delivery, there are usually three main, big-picture goals that all team members are aiming to achieve: scope, schedule, and budget. What sets the IPD delivery model apart from others are the tools and structure implemented by the IPD team to deliver the project within or under budget while still meeting the owner’s needs.

To maintain accountability for a big-picture item, there must be a means by which teams can track their progress. If this is not done properly, it can lead to major issues ranging from budget overages to change orders to schedule slips. Ever heard the adage “out of sight, out of mind”? Well, to avoid falling into this pattern, many IPD teams engage in daily stand-up meetings. These meetings are brief, 10-20 minutes, where all three parties stand and review a list of items that require some type of action within the next week. This may seem short and redundant at first, but once team members own an action, the benefit of these meetings becomes very clear. 

Through the natural and innate human desire to succeed, these meetings drive every member of the team to be accountable, urgent, and collaborative with all three entities of the IPD agreement throughout all phases of the project. 

IPD allows these meetings to drive the big-picture goals because the architect, contractor, and owner are able to discuss construction and design items every day, through the design, preconstruction, and construction phases and all the way through closeout. 

Target Value Design (TVD) is a major tool in setting IPD apart from traditional methods. TVD breaks the mold of contractors providing estimates based on detailed design. Instead, estimates are based on a target cost which is collaboratively established amongst all team members. 

TVD in IPD diminishes the traditional “throw-it-over-the-wall” design since contractors and sub-contractors are brought on board in the design phase. This allows the designers to engage the people who will be procuring and finishing-out their projects as they design. This helps avoid design results that require re-work due to constructability and budget issues, de-value engineering and delay.

Stemming from TVD, an IPD team participates in PITs, or Project Implementation Team meetings, also known as Component Team Meetings. PIT meetings are comprised of interdisciplinary groups of project participants, and are crucial in achieving success with IPD. 

Typically with IPD, there are PIT teams for each major aspect driving the design and construction: MEP PIT, Civil/Site PIT, Structure PIT, Build/Fit-Out PIT, Equipment PIT, Food Service PIT, AV/IT PIT, Closeout PIT, etc. (there can be more groupings depending on the size of the project). These meetings are extremely successful and serve as the foundation of TVD. It is in these meetings that designers are able to engage and receive real-time feedback from the subcontractors and other team members who will be executing the design in the field. 

Also, like the stand-up meetings, the PIT meetings take place through all phases of the project, ensuring the designers are receiving real-time answers from subcontractors and vendors before construction has begun and often before final documents are issued.     

 

RESULTS

So let’s imagine a construction project that brought all major players on-board almost concurrently. With an owner’s vision, or preliminary program, the architect, contractor, and owner may all work together to establish the target-value with detailed estimates to drive expectations. 

The detailed estimate design originates in an environment that has harnessed and co-located all key players, of not only the design phase, but also the construction phase. Below is an example of how this type of environment and structure enhances project goals when utilizing IPD.

At a weekly MEP PIT meeting, the owner-representative informs the team that the owner has decided to change the original HVAC selection from a chilled water to a DX central AC plant. The mechanical contractor, present in the meeting, is able to get specifications for the DX system. The engineer and architect, also in attendance, are able to begin redesign work and plan changes. The contractor is able to revise pricing based on the new system selection and all other related aspects that will change. 

All of the rework and revisions are completed in less than a week and within budget. The schedule is not impacted and the plans are changed prior to pouring the slab. The team is thus able to collaborate and provide the owner an estimate of the affect the changes will have on important operational parameters such as heat/cool loads, maintenance, and facility operations cost, post-occupancy. 

Because of the nature and processes inherent in IPD, this issue did not impact the schedule or budget. The issue was brought up before construction had begun, the subcontractor was able to provide the designer and engineer with all necessary information and support to ensure constructability was guaranteed, and the design team was able to make the plan change prior to the release of final plans. What could have been a very pricey and time-consuming Change Order was mitigated through a collaborative re-planning session in which all valuable project team members participated.

 

CONCLUSION

The IPD method incentivizes all team members to work collaboratively to provide the client with the best possible product; a project that meets scope, maintains budget, and delivers on schedule. 

Like the Integrated Care Teams mentioned previously, an IPD team is a one-stop shop that is established during or even before design. This delivery method cultivates cross-discipline design, ideally before construction begins, through various tools that help to focus accountability on not just an individual level, but also a team-wide level. 

Both figuratively and literally, IPD provides a design and construction world without walls and fences. It instead provides a clear definition and structure of the near-term and long-term goals of the entire project team at large. Ambiguity is a major enemy of IPD, but utilization of the proper tools creates transparency in every aspect of design, budget, schedule, and construction. 

The project vision will be as clear to the owner as it is to the designers, contractors, and down through the entire project team. 

About the Author
Megan Donham is an Associate Consultant with CBRE Healthcare. She can be reached at megan.donham@cbre.com.

Related Stories

Office Buildings | May 20, 2024

10 spaces that are no longer optional to create a great workplace

Amenities are no longer optional. The new role of the office is not only a place to get work done, but to provide a mix of work experiences for employees.

Mass Timber | May 17, 2024

Charlotte's new multifamily mid-rise will feature exposed mass timber

Construction recently kicked off for Oxbow, a multifamily community in Charlotte’s The Mill District. The $97.8 million project, consisting of 389 rental units and 14,300 sf of commercial space, sits on 4.3 acres that formerly housed four commercial buildings. The street-level retail is designed for boutiques, coffee shops, and other neighborhood services.

Construction Costs | May 16, 2024

New download: BD+C's May 2024 Market Intelligence Report

Building Design+Construction's monthly Market Intelligence Report offers a snapshot of the health of the U.S. building construction industry, including the commercial, multifamily, institutional, and industrial building sectors. This report tracks the latest metrics related to construction spending, demand for design services, contractor backlogs, and material price trends.

K-12 Schools | May 15, 2024

A new Alabama high school supports hands-on, collaborative, and diverse learning

In Gulf Shores, a city on Alabama’s Gulf Coast, a new $137 million high school broke ground in late April and is expected to open in the fall of 2026. Designed by DLR Group and Goodwyn Mills Cawood, the 287,000-sf Gulf Shores High School will offer cutting-edge facilities and hands-on learning opportunities.

Adaptive Reuse | May 15, 2024

Modular adaptive reuse of parking structure grants future flexibility

The shift away from excessive parking requirements aligns with a broader movement, encouraging development of more sustainable and affordable housing.

Affordable Housing | May 14, 2024

Brooklyn's colorful new affordable housing project includes retail, public spaces

A new affordable housing development located in the fastest growing section of Brooklyn, N.Y., where over half the population lives below the poverty line, transformed a long vacant lot into a community asset. The Van Sinderen Plaza project consists of a newly constructed pair of seven-story buildings totaling 193,665 sf, including 130 affordable units.

K-12 Schools | May 13, 2024

S.M.A.R.T. campus combines 3 schools on one site

From the start of the design process for Santa Clara Unified School District’s new preK-12 campus, discussions moved beyond brick-and-mortar to focus on envisioning the future of education in Silicon Valley.

University Buildings | May 10, 2024

UNC Chapel Hill’s new medical education building offers seminar rooms and midsize classrooms—and notably, no lecture halls

The University of North Carolina at Chapel Hill has unveiled a new medical education building, Roper Hall. Designed by The S/L/A/M Collaborative (SLAM) and Flad Architects, the UNC School of Medicine’s new building intends to train new generations of physicians through dynamic and active modes of learning.

Sustainability | May 10, 2024

Perkins&Will’s first ESG report discloses operational performance data across key metrics

Perkins&Will recently released its first ESG report that discloses the firm’s operational performance data across key metrics and assesses its strengths and opportunities.

MFPRO+ News | May 10, 2024

HUD strengthens flood protection rules for new and rebuilt residential buildings

The U.S. Department of Housing and Urban Development (HUD) issued more stringent flood protection requirements for new and rebuilt homes that are developed with, or financed with, federal funds. The rule strengthens standards by increasing elevations and flood-proofing requirements of new properties in areas at risk of flooding. 

boombox1
boombox2
native1

More In Category


Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.



Libraries

Reasons to reinvent the Midcentury academic library

DLR Group's Interior Design Leader Gretchen Holy, Assoc. IIDA, shares the idea that a designer's responsibility to embrace a library’s history, respect its past, and create an environment that will serve student populations for the next 100 years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021