In order to better understand the Integrated Project Delivery (IPD) Model, let’s take a metaphorical trip to a doctor’s office.
Imagine we are having a wound treated, a wound that was caused by diabetes. During our visit, we are seen by an endocrinologist to help us better manage our diabetes. We are then seen by a Nutritionist to help manage and plan our meals based on our health needs. Lastly, before leaving, a pharmacist stops by to provide medications on the spot.
Some of you may be wondering, “What does this have to do with IPD?” Well, in the above example, this type of cross-discipline, co-location, and utilization of expertise, or “integrated care team,” as some call it, is part of a recent paradigm shift that the healthcare industry is feeling nationwide.
This shift can be viewed as analogous to the IPD model. While IPD is deemed transformational and revolutionary based on its ability to mine risk through financial incentive, contracted in an Integrated Form of Agreement or Tri-Party Agreement (an agreement between the owner, architect, and contractor), it is how the three parties collaboratively work together. The underlying variables and tools used to manage collaboration between teams is ultimately the driving for success with IPD.
DAY-TO-DAY TOOLS FOR IPD
To ensure goals are met, it is imperative that teams identify and utilize an effective structure to hold every member accountable to a near-term degree. In project delivery, there are usually three main, big-picture goals that all team members are aiming to achieve: scope, schedule, and budget. What sets the IPD delivery model apart from others are the tools and structure implemented by the IPD team to deliver the project within or under budget while still meeting the owner’s needs.
To maintain accountability for a big-picture item, there must be a means by which teams can track their progress. If this is not done properly, it can lead to major issues ranging from budget overages to change orders to schedule slips. Ever heard the adage “out of sight, out of mind”? Well, to avoid falling into this pattern, many IPD teams engage in daily stand-up meetings. These meetings are brief, 10-20 minutes, where all three parties stand and review a list of items that require some type of action within the next week. This may seem short and redundant at first, but once team members own an action, the benefit of these meetings becomes very clear.
Through the natural and innate human desire to succeed, these meetings drive every member of the team to be accountable, urgent, and collaborative with all three entities of the IPD agreement throughout all phases of the project.
IPD allows these meetings to drive the big-picture goals because the architect, contractor, and owner are able to discuss construction and design items every day, through the design, preconstruction, and construction phases and all the way through closeout.
Target Value Design (TVD) is a major tool in setting IPD apart from traditional methods. TVD breaks the mold of contractors providing estimates based on detailed design. Instead, estimates are based on a target cost which is collaboratively established amongst all team members.
TVD in IPD diminishes the traditional “throw-it-over-the-wall” design since contractors and sub-contractors are brought on board in the design phase. This allows the designers to engage the people who will be procuring and finishing-out their projects as they design. This helps avoid design results that require re-work due to constructability and budget issues, de-value engineering and delay.
Stemming from TVD, an IPD team participates in PITs, or Project Implementation Team meetings, also known as Component Team Meetings. PIT meetings are comprised of interdisciplinary groups of project participants, and are crucial in achieving success with IPD.
Typically with IPD, there are PIT teams for each major aspect driving the design and construction: MEP PIT, Civil/Site PIT, Structure PIT, Build/Fit-Out PIT, Equipment PIT, Food Service PIT, AV/IT PIT, Closeout PIT, etc. (there can be more groupings depending on the size of the project). These meetings are extremely successful and serve as the foundation of TVD. It is in these meetings that designers are able to engage and receive real-time feedback from the subcontractors and other team members who will be executing the design in the field.
Also, like the stand-up meetings, the PIT meetings take place through all phases of the project, ensuring the designers are receiving real-time answers from subcontractors and vendors before construction has begun and often before final documents are issued.
RESULTS
So let’s imagine a construction project that brought all major players on-board almost concurrently. With an owner’s vision, or preliminary program, the architect, contractor, and owner may all work together to establish the target-value with detailed estimates to drive expectations.
The detailed estimate design originates in an environment that has harnessed and co-located all key players, of not only the design phase, but also the construction phase. Below is an example of how this type of environment and structure enhances project goals when utilizing IPD.
At a weekly MEP PIT meeting, the owner-representative informs the team that the owner has decided to change the original HVAC selection from a chilled water to a DX central AC plant. The mechanical contractor, present in the meeting, is able to get specifications for the DX system. The engineer and architect, also in attendance, are able to begin redesign work and plan changes. The contractor is able to revise pricing based on the new system selection and all other related aspects that will change.
All of the rework and revisions are completed in less than a week and within budget. The schedule is not impacted and the plans are changed prior to pouring the slab. The team is thus able to collaborate and provide the owner an estimate of the affect the changes will have on important operational parameters such as heat/cool loads, maintenance, and facility operations cost, post-occupancy.
Because of the nature and processes inherent in IPD, this issue did not impact the schedule or budget. The issue was brought up before construction had begun, the subcontractor was able to provide the designer and engineer with all necessary information and support to ensure constructability was guaranteed, and the design team was able to make the plan change prior to the release of final plans. What could have been a very pricey and time-consuming Change Order was mitigated through a collaborative re-planning session in which all valuable project team members participated.
CONCLUSION
The IPD method incentivizes all team members to work collaboratively to provide the client with the best possible product; a project that meets scope, maintains budget, and delivers on schedule.
Like the Integrated Care Teams mentioned previously, an IPD team is a one-stop shop that is established during or even before design. This delivery method cultivates cross-discipline design, ideally before construction begins, through various tools that help to focus accountability on not just an individual level, but also a team-wide level.
Both figuratively and literally, IPD provides a design and construction world without walls and fences. It instead provides a clear definition and structure of the near-term and long-term goals of the entire project team at large. Ambiguity is a major enemy of IPD, but utilization of the proper tools creates transparency in every aspect of design, budget, schedule, and construction.
The project vision will be as clear to the owner as it is to the designers, contractors, and down through the entire project team.
About the Author
Megan Donham is an Associate Consultant with CBRE Healthcare. She can be reached at megan.donham@cbre.com.
Related Stories
Multifamily Housing | Apr 12, 2024
Habitat starts leasing Cassidy on Canal, a new luxury rental high-rise in Chicago
New 33-story Class A rental tower, designed by SCB, will offer 343 rental units.
Student Housing | Apr 12, 2024
Construction begins on Auburn University’s new first-year residence hall
The new first-year residence hall along Auburn University's Haley Concourse.
K-12 Schools | Apr 11, 2024
Eric Dinges named CEO of PBK
Eric Dinges named CEO of PBK Architects, Houston.
Construction Costs | Apr 11, 2024
Construction materials prices increase 0.4% in March 2024
Construction input prices increased 0.4% in March compared to the previous month, according to an Associated Builders and Contractors analysis of the U.S. Bureau of Labor Statistics’ Producer Price Index data released today. Nonresidential construction input prices also increased 0.4% for the month.
Healthcare Facilities | Apr 11, 2024
The just cause in behavioral health design: Make it right
NAC Architecture shares strategies for approaching behavioral health design collaboratively and thoughtfully, rather than simply applying a set of blanket rules.
K-12 Schools | Apr 10, 2024
A San Antonio school will provide early childhood education to a traditionally under-resourced region
In San Antonio, Pre-K 4 SA, which provides preschool for 3- and 4-year-olds, and HOLT Group, which owns industrial and other companies, recently broke ground on an early childhood education: the South Education Center.
University Buildings | Apr 10, 2024
Columbia University to begin construction on New York City’s first all-electric academic research building
Columbia University will soon begin construction on New York City’s first all-electric academic research building. Designed by Kohn Pedersen Fox (KPF), the 80,700-sf building for the university’s Vagelos College of Physicians and Surgeons will provide eight floors of biomedical research and lab facilities as well as symposium and community engagement spaces.
K-12 Schools | Apr 10, 2024
Surprise, surprise: Students excel in modernized K-12 school buildings
Too many of the nation’s school districts are having to make it work with less-than-ideal educational facilities. But at what cost to student performance and staff satisfaction?
Industrial Facilities | Apr 9, 2024
Confessions of a cold storage architect
Designing energy-efficient cold storage facilities that keep food safe and look beautiful takes special knowledge.
Cultural Facilities | Apr 8, 2024
Multipurpose sports facility will be first completed building at Obama Presidential Center
When it opens in late 2025, the Home Court will be the first completed space on the Obama Presidential Center campus in Chicago. Located on the southwest corner of the 19.3-acre Obama Presidential Center in Jackson Park, the Home Court will be the largest gathering space on the campus. Renderings recently have been released of the 45,000-sf multipurpose sports facility and events space designed by Moody Nolan.