Bernards, a well-respected, nationally ranked construction firm and Colombo Construction Company, a southern California firm known for its quality healthcare projects, have teamed for the first time to provide construction management services for the $57 Million Tehachapi Valley Healthcare District Replacement Hospital in Tehachapi, California. This new 25-bed, 79,000 square foot facility will replace the existing hospital which no longer meets current California safety standards, and is located in a rural part of Kern County. As the only hospital in a 50-mile radius, the project is a vital addition to the community, so it’s important that the team completes the job as quickly and efficiently as possible.
Challenge
The project broke ground in early 2013, and the first challenge the team faced was how to manage the enormous number of drawings necessary for the construction of a hospital. Since Tehachapi is a California hospital, it requires approval from the Office of Statewide Health Planning and Development (OSHPD*). Because of time constraints during the bidding process, two sets of drawings had to be correlated: a “permit set” of 500 documents for OSHPD approval, and another “bid set” of 520 documents for the prime contractors.
Not only was the bid set larger, but it also contained updated information that was not reflected in the older permit set. The team needed a reliable solution to quickly and accurately compare the differences between the two versions. Printing hard copies of each set and comparing them against each other was not an option — the process would be time-consuming and risk a significant margin for error. Moreover, because of the project’s remote location, printing costs are extremely high. It was becoming clear that digital was the only way to go.
A Digital Solution
The team at first considered looking for a third-party service to help with the seemingly overwhelming task of comparing the two sets of drawings. Fortunately, Bernards Project Engineer William Lopez had a better idea. Having used Bluebeam Revu on other projects with great success, he was confident that leveraging Revu was the best course of action. The technology was already in-house, and this solution saved time and the cost of looking for a third party qualified enough to complete the work.
The Tehachapi team contacted the project architect, requesting PDF copies of both the permit and bid sets. They then began the process of creating an electronic plan room by installing two 55” screens and using Revu’s Compare Documents feature to display — side-by-side — the automatic comparison of the two sets. This feature enables users to select two drawings, and automatically highlights all disparities with clouds, so they are easy-to-find.
Upon completion, the team reviewed and organized all the markups using the “Markups list.” This feature tracks markups as they are added to the document in a convenient list that can be filtered, searched, imported and exported.
Results
Using Revu, the team compared an initial test set of 100 sheets, and everyone was happy and surprised when it took only 3 hours to back-check the results. In fact, William and the team were amazed by the speed and success of the test. “We were able to complete the final job of comparing the permit set against the bid set in just 15 hours — pretty amazing, considering we had expected this process to take over a week!”
A quality assurance/quality control review revealed that Revu was finding the myriad of important details, including revision symbols and date stamps, that manual scanning could have missed. Even minute details in the scanned permit drawings were picked up. Best of all, the team was able to spend their valuable weekends at home, not in the office reviewing drawings.
Mike Funderberg, Bernards’ Project Manager for the Tehachapi project, commented “The utilization of Bluebeam for this document comparison effort saved nearly 400 hours of the Bernards/Colombo staff’s time to devote to other pressing issues. Being able to not only utilize software, but rely on it, made our processes so much more efficient.”
Continuing to Leverage Revu
OSPHD is still in the process of updating the permit set to reflect the advancements of the bid set drawings, and is sending approvals just about every day. As the Bernards/Colombo team receives those changes, they slip-sheet them into the master set using Revu’s Replace Pages feature, updating the sets 10 times faster than it would take to update a paper set.
The Tehachapi team is also using Revu for BIM coordination. For example, when they discovered the ceilings needed to be dropped to accommodate additional ducts and piping, they created 3-D PDFs of the sectioned BIM, to send to the architect with their markups. This is a much faster and easier way to share redlines, and the team loves how easy it is to manipulate 3-D PDFs. They also plan on using Revu for takeoffs, color coding, and other day-to-day construction tasks, and have already set up Wi-Fi in the trailer, enabling plan review in the field.
To learn more about Revu or download a free 30-day trial, please visit us here.
*OSHPD is an agency created in 1978 to provide the state with enhanced understanding of the structure and function of its healthcare delivery systems.
Related Stories
Urban Planning | Apr 12, 2024
Popular Denver e-bike voucher program aids carbon reduction goals
Denver’s e-bike voucher program that helps citizens pay for e-bikes, a component of the city’s carbon reduction plan, has proven extremely popular with residents. Earlier this year, Denver’s effort to get residents to swap some motor vehicle trips for bike trips ran out of vouchers in less than 10 minutes after the program opened to online applications.
Laboratories | Apr 12, 2024
Life science construction completions will peak this year, then drop off substantially
There will be a record amount of construction completions in the U.S. life science market in 2024, followed by a dramatic drop in 2025, according to CBRE. In 2024, 21.3 million sf of life science space will be completed in the 13 largest U.S. markets. That’s up from 13.9 million sf last year and 5.6 million sf in 2022.
MFPRO+ News | Apr 12, 2024
Legal cannabis has cities grappling with odor complaints
Relaxed pot laws have led to a backlash of complaints linked to the odor emitted from smoking and vaping. To date, 24 states have legalized or decriminalized marijuana and several others have made it available for medicinal use.
Multifamily Housing | Apr 12, 2024
Habitat starts leasing Cassidy on Canal, a new luxury rental high-rise in Chicago
New 33-story Class A rental tower, designed by SCB, will offer 343 rental units.
MFPRO+ News | Apr 12, 2024
Greystar becomes top apartment owner, manager, and developer in 2024
One firm set records for this year’s National Multifamily Housing Council Top 50 roundup of multifamily firms. Greystar now sits at number one in the NMHC’s lists for top apartment owner, manager, and developer in 2024.
Construction Costs | Apr 11, 2024
Construction materials prices increase 0.4% in March 2024
Construction input prices increased 0.4% in March compared to the previous month, according to an Associated Builders and Contractors analysis of the U.S. Bureau of Labor Statistics’ Producer Price Index data released today. Nonresidential construction input prices also increased 0.4% for the month.
K-12 Schools | Apr 10, 2024
A San Antonio school will provide early childhood education to a traditionally under-resourced region
In San Antonio, Pre-K 4 SA, which provides preschool for 3- and 4-year-olds, and HOLT Group, which owns industrial and other companies, recently broke ground on an early childhood education: the South Education Center.
University Buildings | Apr 10, 2024
Columbia University to begin construction on New York City’s first all-electric academic research building
Columbia University will soon begin construction on New York City’s first all-electric academic research building. Designed by Kohn Pedersen Fox (KPF), the 80,700-sf building for the university’s Vagelos College of Physicians and Surgeons will provide eight floors of biomedical research and lab facilities as well as symposium and community engagement spaces.
K-12 Schools | Apr 10, 2024
Surprise, surprise: Students excel in modernized K-12 school buildings
Too many of the nation’s school districts are having to make it work with less-than-ideal educational facilities. But at what cost to student performance and staff satisfaction?
Cultural Facilities | Apr 8, 2024
Multipurpose sports facility will be first completed building at Obama Presidential Center
When it opens in late 2025, the Home Court will be the first completed space on the Obama Presidential Center campus in Chicago. Located on the southwest corner of the 19.3-acre Obama Presidential Center in Jackson Park, the Home Court will be the largest gathering space on the campus. Renderings recently have been released of the 45,000-sf multipurpose sports facility and events space designed by Moody Nolan.