BIM Clarification and Codification in a Louisiana Sports Museum

BIM Clarification and Codification in a Louisiana Sports Museum


By By Jeff Yoders, Contributing Editor | October 12, 2011
The curvilinear substructure expresses the regions sporting past and land form. METHOD Design wedded a 3D structural model (opp
This article first appeared in the October 2011 issue of BD+C.

The Louisiana State Sports Hall of Fame is currently being built in Natchitoches, one of the Old West settlements in the Louisiana Purchase. The $12 million, 22,000-sf project will celebrate memorabilia donated by 250 Cajun country sports heroes and showcase their impact on the state. Trahan Architects of Baton Rouge designed a contemporary, curvilinear building to express not just local materials, but the land of northern Louisiana, too.

When it’s completed next March, the building will be in the form of a curvilinear museum substructure situated in a box of native cypress-timber planks. According to Victor “Trey” Trahan, FAIA, president and principal-in-charge of Trahan Architects, the design of the building itself is meant to recall both the hilly topography of northern Louisiana and the flow of the Cane River, while the exterior box controls light and shadow outside the building. Fluid shapes of river channels are separated by interstitial masses in the curvilinear structure, the same way that delta islands separate the waters of a river, thus creating the organizing principle for visitor circulation and gallery arrangement in the museum.

However, that expressive design required coordination and planning that just wouldn’t be possible without the use of 3D BIM. While this was a traditional design-bid-build project, the owner, the state of Louisiana, and the design architect both wanted a BIM consultant to oversee the creation of the precast concrete panels on the substructure inside the outer box. Trahan also required that five-axis CNC milling be used for the formwork of the exterior panels. Case Building + Technology, a BIM and integrated practice consultancy based in New York, was originally brought into the Building Team by the architect, but eventually became a design consultant and BIM manager for the construction manager, VCC of Little Rock, Ark. Case was founded in 2008 by several former members of SHoP Architects, a firm that delivered some very intricate BIM projects, including the 290 Mulberry Street Condominiums (http://www.290mulberry.com) in New York.

“There needed to be expertise at the level of panel fabrication that typically is just not available to the design architect that early in the process,” said Federico Negro, the partner-in-charge on the project for Case Building + Technology.

Trahan Architects used Rhino 3D (.3dm file format), a NURBS tool, for the free-form, curvilinear exterior skin model of the substructure. Trahan originated that model in Autodesk Maya, a 3D animation software used mainly by the film and gaming industries, and brought it into Rhino to add geometric information. They also provided an Autodesk Revit (.rvt) model of the entire project. Still, without actual field conditions built into the model, the precast concrete panels themselves couldn’t be molded and created with any level of detail necessary for installation. Case analyzed the entire skin model and determined that a total of 1,030 separate precast panels would be needed with 4-8 connections to the underlying steel frame for each panel. The whole surface was analyzed for gaps and constructability questions, and all gaps had to be fixed on the model’s surface. Each pair of connecting panels had to achieve a tolerance of a quarter-inch between them.

They also had to coordinate connections with the model of structural engineer, LBYD of Birmingham, Ala. The support steel had to be analyzed for clash detection with the concrete panels. Two clash detection programs were used on the project: Gehry Technologies’ Digital Project and Autodesk Navisworks Manage. All panel-to-panel clearance detection was done in Digital Project. For trade coordination, which fell under Case’s purview as the overall BIM manager for VCC, Navisworks was used because of its robust import/export capabilities and the sheer numbers of different software packages (14 different programs) the trade subcontractors were using on the project.

“That’s just the way we like to work,” said Case Building + Technology’s Negro. “We’re not going to specify something else for a fabricator or anyone else to learn and use on a project. We want to be as far from top-down as possible. Working directly for the CM and down through all trades gave us a much bigger perspective of the overall project and really integrated everyone on the team.”

Once the design skin model was rationalized, made seamless, and quality-checked for constructability, an automated program then sent a unique shop ticket for each panel to fabricator Advanced Cast Stone of Fort Worth, Texas. The shop tickets were created in Rhino via Rhinoscript. The script took a computer folder of panel file information and automatically created a shop ticket for each panel. The program automatically placed the embed points on the panel, prepared a fabrication file for molds, and created all the cameras and views needed for the visual part of the ticket itself. The script also created a table articulating and explaining all the different embed types on that panel. That information went into the shop ticket and an accompanying .csv file capable of being opened in Microsoft Excel. This automated process created a simple set of points to tell the shop what was needed to create each of the 1,030 panels delivered in a STEP (.step). Four corners and connection points were named and articulated in each shop ticket, and a shop drawing accompanied each ticket.

To track coordination problems between structural, MEP, and fire protection, Case used Web-based tracking tool Jira (https://www.atlassian.com/software/jira), developed by Australian software company Atlassian, which is primarily used for tracking bugs in computer code. However, it worked just as well for tracking clashes as it does for finding bugs.

All the precast concrete panels have now been fabricated, and installation began in early August in Natchitoches. The project is on track to open in March.

“Protecting design intent is always a big factor here,” Negro said. “Having people that can demystify surfaces and geometry is a big part of what we do, and it is hard work on such a complex design, but it’s not impossible to preserve that design. Not even close.” BD+C

Related Stories

| Aug 11, 2010

Florida mixed-use complex includes retail, residential

The $325 million Atlantic Plaza II lifestyle center will be built on 8.5 acres in Delray Beach, Fla. Designed by Vander Ploeg & Associates, Boca Raton, the complex will include six buildings ranging from three to five stories and have 182,000 sf of restaurant and retail space. An additional 106,000 sf of Class A office space and a residential component including 197 apartments, townhouses, ...

| Aug 11, 2010

Restoration gives new life to New Formalism icon

The $30 million upgrade, restoration, and expansion of the Mark Taper Forum in Los Angeles was completed by the team of Rios Clementi Hale Studios (architect), Harley Ellis Devereaux (executive architect/MEP), KPFF (structural engineer), and Taisei Construction (GC). Work on the Welton Becket-designed 1967 complex included an overhaul of the auditorium, lighting, and acoustics.

| Aug 11, 2010

Best AEC Firms to Work For

2006 FreemanWhite Hnedak Bobo Group McCarthy Building Companies, Inc. Shawmut Design and Construction Walter P Moore 2007 Anshen+Allen Arup Bovis Lend Lease Cannon Design Jones Lang LaSalle Perkins+Will SmithGroup SSOE, Inc. Timothy Haahs & Associates, Inc. 2008 Gilbane Building Co. HDR KJWW Engineering Consultants Lord, Aeck & Sargent Mark G.

| Aug 11, 2010

High-Performance Workplaces

Building Teams around the world are finding that the workplace is changing radically, leading owners and tenants to reinvent corporate office buildings to compete more effectively on a global scale. The good news is that this means more renovation and reconstruction work at a time when new construction has stalled to a dribble.

| Aug 11, 2010

Great Solutions: Business Management

22. Commercial Properties Repositioned for University USE Tocci Building Companies is finding success in repositioning commercial properties for university use, and it expects the trend to continue. The firm's Capital Cove project in Providence, R.I., for instance, was originally designed by Elkus Manfredi (with design continued by HDS Architects) to be a mixed-use complex with private, market-...

| Aug 11, 2010

Nurturing the Community

The best seat in the house at the new Seahawks Stadium in Seattle isn't on the 50-yard line. It's in the southeast corner, at the very top of the upper bowl. "From there you have a corner-to-corner view of the field and an inspiring grasp of the surrounding city," says Kelly Kerns, project leader with architect/engineer Ellerbe Becket, Kansas City, Mo.

| Aug 11, 2010

AIA Course: Historic Masonry — Restoration and Renovation

Historic restoration and preservation efforts are accelerating throughout the U.S., thanks in part to available tax credits, awards programs, and green building trends. While these projects entail many different building components and systems, façade restoration—as the public face of these older structures—is a key focus. Earn 1.0 AIA learning unit by taking this free course from Building Design+Construction.

| Aug 11, 2010

BIM adoption tops 80% among the nation's largest AEC firms, according to BD+C's Giants 300 survey

The nation's largest architecture, engineering, and construction companies are on the BIM bandwagon in a big way, according to Building Design+Construction's premier Top 50 BIM Adopters ranking, published as part of the 2009 Giants 300 survey. Of the 320 AEC firms that participated in Giants survey, 83% report having at least one BIM seat license in house, half have more than 30 seats, and near...

| Aug 11, 2010

World's tallest all-wood residential structure opens in London

At nine stories, the Stadthaus apartment complex in East London is the world’s tallest residential structure constructed entirely in timber and one of the tallest all-wood buildings on the planet. The tower’s structural system consists of cross-laminated timber (CLT) panels pieced together to form load-bearing walls and floors. Even the elevator and stair shafts are constructed of prefabricated CLT.

| Aug 11, 2010

Integrated Project Delivery builds a brave, new BIM world

Three-dimensional information, such as that provided by building information modeling, allows all members of the Building Team to visualize the many components of a project and how they work together. BIM and other 3D tools convey the idea and intent of the designer to the entire Building Team and lay the groundwork for integrated project delivery.

boombox1
boombox2
native1

More In Category


Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.



Libraries

Reasons to reinvent the Midcentury academic library

DLR Group's Interior Design Leader Gretchen Holy, Assoc. IIDA, shares the idea that a designer's responsibility to embrace a library’s history, respect its past, and create an environment that will serve student populations for the next 100 years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021