The Wake County, North Carolina School Board is happy with its use of construction manager at risk for its construction projects, citing the ability to better keep projects on schedule. Some local small contractors are not pleased, though, with the board’s CM-at-Risk policy that was instituted in 2007. The county’s board of commissioners has offered a sympathetic ear to their complaints.
The key point of dispute is that under this delivery method, the construction manager prequalifies the subcontractors who can bid on the work. Some feel that as a result of this provision they are shut out of the process for work that was previously open to them.
These complaints helped lead to the passage of a state law last year requiring public entities to justify using CM-at-Risk for each project. Under this law, school staff will come back to the school board to request approval for using CM-at-Risk for most of the major projects funded by last fall’s bond issue.
At odds over this issue, the two boards have yet to reach consensus on how CM-at-Risk should be used on future school projects.
(http://www.newsobserver.com/2014/08/11/4059339/wake-county-schools-defend-use.html)
Related Stories
| Feb 23, 2012
Federal budget cuts put major building projects on hold
A plan to build the National Bio and Agro-Defense Facility in Kansas is among several major building projects in jeopardy after the Obama administration’s 2013 budget was unveiled. The budget would cut all construction spending for the facility.
| Feb 23, 2012
Federal agencies fixed on leasing LEED-certified space
The federal government is especially focused on renting LEED-certified spaces.
| Feb 23, 2012
Regulators investigating construction accident at World Trade Center
The New York Port Authority and the city’s fire and building departments are investigating an accident at the World Trade Center construction site in lower Manhattan after a crane dropped steel beams that fell about 40 stories onto the truck that delivered them.
| Feb 23, 2012
New Virginia statewide building code goes into effect March 1
After March 1, all building plans in Virginia must adhere to the 2009 code that was adopted a year ago.
| Feb 23, 2012
Privatizing flood insurance could lead to new code requirements
One thing that could pave the way toward private flood insurance would be NFIP reforms, like requiring new construction in flood-prone areas to be elevated.
| Feb 22, 2012
ACI BIM manual for cast-in-place concrete in development
The improved communication, coordination, and collaboration afforded by BIM implementation have already been shown to save time and money in projects.
| Feb 20, 2012
Comment period for update to USGBC's LEED Green Building Program now open
This third draft of LEED has been refined to address technical stringency and rigor, measurement and performance tools, and an enhanced user experience.
| Feb 20, 2012
GAF introduces web portal for architects and specifiers
The new portal offers a clean look with minimal clutter to make it easier to find the technical information and product data that architects need.