At Boston University’s dental school, ‘under construction’ won’t mean ‘closed for business’

Contractors

At Boston University’s dental school, ‘under construction’ won’t mean ‘closed for business’

A major renovation and addition are scheduled to minimize operational disruption.


By John Caulfield, Senior Editor | April 26, 2018

Boston University's Goldman School of Dental Medicine will increase its clinical space by 60% through a renovation and addition that are being conducted while the school stays open and continues to offer its services to students and the community. Image: SmithGroupjjr

On April 5, Shawmut Design and Construction broke ground on a 41,900-sf expansion and 53,100-sf renovation of Boston University’s Goldman School of Dental Medicine.

The building team that includes Smith Group JJR (design architect, SE, MEP), Compass Project Management (project manager), and Haley Aldrich (geotech engineer), expects to be onsite for 32 months, during which the school—an active building with over 200 students, plus faculty, staff, and thousands of patients per year—will remain open.

This is a common challenge for rehab projects, complicated in this case by a tight urban site and a building with only a 13,000-sf floor plate—“a postage stamp,” says Shawmut’s Vice President Kevin Sullivan—the building team has to work within.

To keep the school open during work, Sullivan says his firm started by “overcommunicating” with shareholders who included the school’s dean, and its directors of facilities and operations.

The Building Team came up with a multi-phase schedule that will work on the basement, first floor, and part of the second floor first; the two additions next; and then renovate the upper floors. Sullivan explains that this schedule allows for floors and utilities to be isolated, which will sometimes require installing temporary systems to avoid operational disruptions. It will also minimize the need to move students and patients around.

A link to download a virtual reality walkthrough video of this project, posted by Shawmut, can be accessed here.

A rendering of an operatory inside Boston University's renovated and expanded dental school. Image: SmithGroupjjr

 

The isolations will also allow the team to minimize vibration on occupants caused by drilling into concrete to install new façade that lets in more light into the building and blends in with the facades of other buildings in the neighborhood. Because of the tight site space, the Building Team had to close two traffic lanes and move a bus stop.

The expansion will include office, instructional, clinical, and student collaborative spaces on seven existing levels, plus support spaces and a new 140-seat auditorium on the first floor.

The renovation will reconfigure the layout of the patient and student/faculty entry, as well as its clinical, classroom, and student spaces.

All told, the project will increase clinical space by more than 60%, make treatment areas more comfortable and flexible, and provide a student and resident lounge, a café, and collaborative study area on the first floor. With the addition, the school’s floor plate will increase to 18,000 sf.  

The project’s completion data is slated for December 2020.

Related Stories

| Jun 1, 2012

AIA 2030 Commitment Program reports new results

The full report contains participating firm demographics, energy reduction initiatives undertaken by firms, anecdotal accounts, and lessons learned.

| Jun 1, 2012

Robert Wilson joins SmithGroupJJR

Wilson makes the move to SmithGroupJJR from VOA Associates, Inc., where he served as a senior vice president and technical director in its Chicago office.

| Jun 1, 2012

Gilbane Building's Sue Klawans promoted

Industry veteran tasked with boosting project efficiency and driving customer satisfaction, to direct operational excellence efforts.

| Jun 1, 2012

Ground broken for Children’s Hospital Colorado South Campus

Children’s Hospital Colorado expects to host nearly 80,000 patient visits at the South Campus during its first year.

| Jun 1, 2012

K-State Olathe Innovation Campus receives LEED Silver

Aspects of the design included a curtain wall and punched openings allowing natural light deep into the building, regional materials were used, which minimized the need for heavy hauling, and much of the final material included pre and post-consumer recycled content.

| Jun 1, 2012

New York City Department of Buildings approves 3D BIM site safety plans

3D BIM site safety plans enable building inspectors to take virtual tours of construction projects and review them in real-time on site.

| May 31, 2012

Product Solutions June 2012

Curing agents; commercial faucets; wall-cladding systems.

| May 31, 2012

8 steps to a successful BIM marketing program

It's not enough to have BIM capability--you have to know how to sell your BIM expertise to clients and prospects.

| May 31, 2012

3 Metal Roofing Case Studies Illustrate Benefits

Metal roofing systems offer values such as longevity, favorable life cycle costs, and heightened aesthetic appeal.

| May 31, 2012

AIA Course: High-Efficiency Plumbing Systems for Commercial and Institutional Buildings

Earn 1.0 AIA/CES learning units by studying this article and successfully completing the online exam.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021