Calculating the ROI of building enclosure commissioning

Calculating the ROI of building enclosure commissioning

A researcher at Lawrence Berkeley National Laboratory calls building enclosure commissioning “the single-most cost-effective strategy for reducing energy, costs, and greenhouse gas emissions in buildings today.”


By C.C. Sullivan | June 28, 2013
According to Evan Mills, PhD, a researcher at Lawrence Berkeley National Laboratory, building enclosure commissioning, or BECx, should be viewed as “the single-most cost-effective strategy for reducing energy, costs, and greenhouse gas emissions in buildings today.”
 
(This article excerpted from BD+C's June 2013 AIA/CES course on cladding and exterior insulation. Take this free course at BD+C University.)
 
Mills studied the benefits of BECx, noting that commissioning only costs about $1.16/sf for new construction and $0.30/sf for existing buildings on average, with a payback period of as little as 14 months. Savings associated with using BECx from both maintenance and energy savings average about 16% for existing buildings and 13% for new construction. The main benefit is that whole-building energy savings are guaranteed, thanks to the pivotal role of the enclosure in determining efficiency performance.
 
“Further enhancing the value of commissioning, its non-energy benefits surpass those of most other energy-management practices,” including major first-cost savings through right-sizing of HVAC equipment, Mills has testified. “When accounting for these benefits, the net median commissioning project cost was reduced by 49% on average, while in many cases they exceeded the direct value of the energy savings.”
 
The National Institute of Building Sciences published its NIBS Guideline 3-2012 on enclosure commissioning last year. The U.S. Green Building Council has allowed the application of BECx to earn an innovation credit in the LEED rating system, and BECx was even considered as a prerequisite, but that proposal lost momentum, says Rob Kistler, AIA, NCARB, Committee Chair for NIBS Guideline 3 and Principal, The Facade Group.
 
It appears that LEED v4 will not explicitly encourage the detail review, onsite testing, and observation that some enclosure experts say is what makes BECx effective, notes Tristan Roberts, with BuildingGreen’s LEEDUser service. Instead, the new LEED draft language directly quotes NIBS Guideline 3, which describes the following techniques as part of proper BECx for enhanced building commissioning:
•  Devise a plan early in the project cycle that describes testing requirements, acceptance criteria, and documentation.
•  Review details in the construction documentation to check for overall performance, continuity of weather barriers and insulation, and constructability.
•  Conduct observations on the job site as required for critical milestones in enclosure installation, from field mockups to trades startup to field testing.
•  Use mockups to benchmark workmanship requirements and ensure compliance with specifications and manufacturer’s installation requirements.
 
The NIBS committee for BECx, which Altenhofen serves on, recommends including a consulting enclosure expert for the building project, especially in the construction administration phase. The expert will help ensure proposed cladding materials and systems are integrated properly into the design process, followed by visual observations of a statistical sampling of installation of work. Toward the end of the CA phase and before acceptance, a blower-door test will check whether the air infiltration levels are equal to or better than standard.
 
As noted in the summary of NIBS Guideline 3, BECx helps reduce the chances that inadequate cladding work will be discovered during the punch list phase: “The performance of the enclosure cannot be verified until the entire building is completely enclosed. At this time it is not possible to tune or dial in the performance. To access a nonperforming subsystem or assembly might be very expensive.”
 
(This article excerpted from BD+C's June 2013 AIA/CES course on cladding and exterior insulation. Take this free course at BD+C University.)

Related Stories

| Jan 27, 2012

Columbia University’s New Core Laboratory aims for LEED Silver

Construction manager Sordoni Construction Co. along with the design team of Payette Architects and Vanderweil Engineers will provide design and construction services to renovate the majority of the existing Core Lab building to create the new Lamont Center for Bio-Geochemistry.

| Jan 26, 2012

Three dead, 16 missing in Rio buildings collapse

The buildings, one 20 floors high, collapsed on Wednesday night in a cloud of dust and smoke just one block away from the city's historic Municipal Theater.

| Jan 26, 2012

Siemens launches smoke detection knowledge center

New knowledge center web site demonstrates efficacy of smoke detection. 

| Jan 26, 2012

Hendrick Construction completes Osso Restaurant in Charlotte

Designed by François Fossard, Osso's upscale interior includes tapered, twisted decorative columns and an elegant fireplace in the center of the lounge. 

| Jan 26, 2012

HOK partners with USGBC on design of Haiti children's center

Passive design principles give form to a sustainable, restorative environment for the children of Haiti.

| Jan 26, 2012

American Standard names Gould as president and CEO

Gould succeeds Don Devine, who led the successful turnaround of American Standard Brands.

| Jan 26, 2012

Summit Design+Build completes law office in Chicago

Applegate & Thorne-Thomsen's new office suite features private offices, open office area, conference rooms, reception area, exposed wood beams and columns, and exposed brick. 

| Jan 24, 2012

New iPad app ready for prime time

Siemens’ versatile application connects users to APOGEE BAS control and monitoring functions via wireless network connectivity. The application directly interacts with BACnet/IP and Siemens APOGEE P2 field panels. 

| Jan 24, 2012

Vyhanek joins Thornton Tomasetti’s Kansas City office

Vyhanek will assemble a new MEP team in the Midwest to support Building Performance and Property Loss Consulting practices. 

| Jan 24, 2012

U of M installs new lighting at Crisler Player Development Center

Energy efficient lighting installed at PDC reduce costs and improves player performance.

boombox1
boombox2
native1

More In Category


Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.



Libraries

Reasons to reinvent the Midcentury academic library

DLR Group's Interior Design Leader Gretchen Holy, Assoc. IIDA, shares the idea that a designer's responsibility to embrace a library’s history, respect its past, and create an environment that will serve student populations for the next 100 years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021