Cass Gilbert's landmark St. Louis Central Library gets a reboot

Cass Gilbert's landmark St. Louis Central Library gets a reboot

A $70 million project returns large sections of the building to their original Beaux Arts beauty, while modernizing the spaces to make them more inviting and useful for today’s patrons.


By Julie Higginbotham, Senior Editor | October 15, 2013
On the north side of St. Louiss Central Library, the Building Team created a fo
On the north side of St. Louiss Central Library, the Building Team created a four-story atrium in a wing once designed to hold

In the century since Cass Gilbert designed the flagship Central Library for the St. Louis Public Library, information science and building technology have been radically transformed. A $70 million project led by Cannon Design returned large sections of the building to their original Beaux Arts beauty, while modernizing other zones to make the library more inviting and useful for today’s patrons.

Important historic spaces, such as the central Grand Hall, have been revived, including millwork, ornamental plaster, polychrome decoration, bronze work, and marble and cork flooring. Ceiling paintings were restored, and period light fixtures were refurbished or replicated.

The Building Team replaced the outdated MEP and fire protection systems, exploiting original chases concealed within thick masonry walls. Floors in multiple areas were adapted for modern electrical and data infrastructure. The monumental front steps—565 pieces of granite in the form of slabs, balusters, railings, and wall facings—were labeled, removed, catalogued, stored, reassembled, and restored.

ST. LOUIS PUBLIC LIBRARY, CENTRAL LIBRARY
St. Louis, Mo.

 
Building Team 
Submitting firm: Cannon Design (architect) 
Owner: St. Louis Public Library 
Owner’s representative: CLR Consultants 
SE/CE, exterior restoration: David mason & Associates 
MEP/FP engineer: William Tao & Associates 
Historic preservation: Frens & Frens Environmental 
Graphics/signage: Kuhlmann Leavitt 
Construction manager: BSI Constructors
 
General Information 
Size: 185,000 sf 
Construction cost: $70 million 
Construction time: January 2010 to November 2012 
Delivery method: Design-build

The North Wing, once a repository for closed stacks, witnessed a dramatic change.

The original steel skeleton was replaced by a four-story atrium and a series of “floating” platforms. Visible through interior glazing, these levels hold compact-density shelving. A new entry canopy invites patrons to this side of the building, turning a welcoming (and less formal) face to the urban neighborhood.

Several administrative areas on the main floor were repurposed to serve children and teens, with colorful, contemporary de?cor and generous IT infrastructure. A 250-seat auditorium, built in a sub-basement once used for coal storage, creates space for performances and lectures.

The re-imagined Central Library reflects the civic ideals that inspired its founders—a place of uplift, but not a shrine. At last December’s grand opening, Director Waller McGuire emphasized the future. “Central Library isn’t finished yet,” he said. “It’ll never be finished. There will always be new possibilities and new ideas.”

 

The original Olive Street lobby, a counterpoint to the modern entry on the north side, has been meticulously restored, including the elaborate polychrome ceiling painting. The central Great Hall is accessible through the doors at the rear. Photos: Timothy Hursley

 

Reading rooms throughout the building were updated with new lighting and furniture, but historic millwork was preserved. The Building Team used both contemporary and period interior design, depending on each space’s function.

 

Related Stories

Coronavirus | Apr 15, 2020

COVID-19 alert: 93% of renters in professionally managed multifamily housing paid some or all of their rent, says NMHC

In its second survey of 11.5 million units of professionally managed apartment units across the country, the National Multifamily Housing Council (NMHC) found that 84% of apartment households made a full or partial rent payment by April 12, up 15 percentage points from April 5.

Coronavirus | Mar 15, 2020

Designing office building lobbies to respond to the coronavirus

Touch-free design solutions and air purifiers can enhance workplace wellness.

Architects | Mar 9, 2020

New York's façade inspection program gets an overhaul following a death from falling terra cotta

January 14, 2020, kicked off big changes to the NYC Local Law 11 Façade Inspection and Safety Program (FISP) for Cycle 9.

Healthcare Facilities | Mar 9, 2020

Mobile wayfinding platform helps patients, visitors navigate convoluted health campuses

Gozio Health uses a robot to roam hospital campuses to capture data and create detailed maps of the building spaces and campus.

AEC Innovators | Mar 5, 2020

These 17 women are changing the face of construction

During this Women in Construction Week, we shine a spotlight on 17 female leaders in design, construction, and real estate to spur an important conversation of diversity, inclusion, and empowerment.

AEC Tech | Feb 22, 2020

Investor interest in the built environment not quite as avid in 2019

Builtworlds’ annual list of venture deals led by workspace providers.

Modular Building | Feb 16, 2020

On the West Coast, prefab gains ground for speedier construction

Gensler has been working with component supplier Clark Pacific on several projects.

AEC Tech | Feb 13, 2020

Exclusive research: Download the final report for BD+C's Giants 300 Technology and Innovation Study

This survey of 130 of the nation's largest architecture, engineering, and construction firms tracks the state of AEC technology adoption and innovation initiatives at the AEC Giants.

Office Buildings | Feb 11, 2020

Forget Class A: The opportunity is with Class B and C office properties

There’s money to be made in rehabbing Class B and Class C office buildings, according to a new ULI report.

Sponsored | HVAC | Feb 3, 2020

Reliable Building Systems Increase Net Operating Income by Retaining Tenants

Tenants increasingly expect a well-crafted property that feels unique, authentic, and comfortable—with technologically advanced systems and spaces that optimize performance and encourage collaboration and engagement. The following guidance will help owners and property managers keep tenants happy.

boombox1
boombox2
native1

More In Category

Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021