Cass Gilbert's landmark St. Louis Central Library gets a reboot

Cass Gilbert's landmark St. Louis Central Library gets a reboot

A $70 million project returns large sections of the building to their original Beaux Arts beauty, while modernizing the spaces to make them more inviting and useful for today’s patrons.


By Julie Higginbotham, Senior Editor | October 15, 2013
On the north side of St. Louiss Central Library, the Building Team created a fo
On the north side of St. Louiss Central Library, the Building Team created a four-story atrium in a wing once designed to hold

In the century since Cass Gilbert designed the flagship Central Library for the St. Louis Public Library, information science and building technology have been radically transformed. A $70 million project led by Cannon Design returned large sections of the building to their original Beaux Arts beauty, while modernizing other zones to make the library more inviting and useful for today’s patrons.

Important historic spaces, such as the central Grand Hall, have been revived, including millwork, ornamental plaster, polychrome decoration, bronze work, and marble and cork flooring. Ceiling paintings were restored, and period light fixtures were refurbished or replicated.

The Building Team replaced the outdated MEP and fire protection systems, exploiting original chases concealed within thick masonry walls. Floors in multiple areas were adapted for modern electrical and data infrastructure. The monumental front steps—565 pieces of granite in the form of slabs, balusters, railings, and wall facings—were labeled, removed, catalogued, stored, reassembled, and restored.

ST. LOUIS PUBLIC LIBRARY, CENTRAL LIBRARY
St. Louis, Mo.

 
Building Team 
Submitting firm: Cannon Design (architect) 
Owner: St. Louis Public Library 
Owner’s representative: CLR Consultants 
SE/CE, exterior restoration: David mason & Associates 
MEP/FP engineer: William Tao & Associates 
Historic preservation: Frens & Frens Environmental 
Graphics/signage: Kuhlmann Leavitt 
Construction manager: BSI Constructors
 
General Information 
Size: 185,000 sf 
Construction cost: $70 million 
Construction time: January 2010 to November 2012 
Delivery method: Design-build

The North Wing, once a repository for closed stacks, witnessed a dramatic change.

The original steel skeleton was replaced by a four-story atrium and a series of “floating” platforms. Visible through interior glazing, these levels hold compact-density shelving. A new entry canopy invites patrons to this side of the building, turning a welcoming (and less formal) face to the urban neighborhood.

Several administrative areas on the main floor were repurposed to serve children and teens, with colorful, contemporary de?cor and generous IT infrastructure. A 250-seat auditorium, built in a sub-basement once used for coal storage, creates space for performances and lectures.

The re-imagined Central Library reflects the civic ideals that inspired its founders—a place of uplift, but not a shrine. At last December’s grand opening, Director Waller McGuire emphasized the future. “Central Library isn’t finished yet,” he said. “It’ll never be finished. There will always be new possibilities and new ideas.”

 

The original Olive Street lobby, a counterpoint to the modern entry on the north side, has been meticulously restored, including the elaborate polychrome ceiling painting. The central Great Hall is accessible through the doors at the rear. Photos: Timothy Hursley

 

Reading rooms throughout the building were updated with new lighting and furniture, but historic millwork was preserved. The Building Team used both contemporary and period interior design, depending on each space’s function.

 

Related Stories

| Aug 16, 2014

The science of learning: Designing the STEM learning facilities of the future

New technology and changing pedagogies are influencing how to best teach a generation of learners who have never known a world without smartphones or tablets, writes HOK's Kimberly Robidoux.

| Aug 15, 2014

First look: RMJM’s 'jumping fish' tower design for the Chinese Riviera

The tower's fish-jumping gesture is meant to symbolize the prosperity and rapid transformation of Zhuhai, China.

| Aug 15, 2014

Periscope structure gives public toilet an unobstructed sea view

Polish architect Adam Wiercinski designs a public toilet with a periscope mechanism that gives visitors unobstructed views of the sea.

| Aug 14, 2014

8 do's and don'ts for completing an HVAC life cycle cost assessment

There are many hurdles to overcome when completing a life cycle cost assessment. RMF Engineering’s Seth Spangler offers some words of advice regarding LCCAs.

| Aug 14, 2014

Life cycle cost analysis using energy modeling

A life cycle cost analysis helps a school district decide which HVAC system to use in $198 million worth of future building projects.

| Aug 14, 2014

Museum of Mayan Culture draws inspiration from temple design [slideshow]

The Museo Maya de América in Guatemala City will be the world’s largest museum of Mayan history and culture, at 60,000 sf. 

| Aug 14, 2014

How workplace design can empower employees, businesses

Focusing on recent work at Follett and Zurich, CannonDesign’ Meg Osman reveals the power of research, strategy, change management, and measurement to transform businesses for the better.

| Aug 13, 2014

Campus UX: Why universities should be creating 'branded environments' on campus

When most colleges and universities consider their brands, they rarely venture beyond the design and implementation of a logo, writes Gensler Design Director Brian Brindisi.

| Aug 12, 2014

Vietnam's 'dragonfly in the sky' will be covered in trees, vegetation

Designed by Vietnamese design firm Vo Trong Nghia Architects, the building will be made up of stacked concrete blocks placed slightly askew to create a soft, organic form that the architects say is reminiscent of a dragonfly in the sky.

| Aug 12, 2014

Design firms invited to submit qualifications for St. Petersburg, Fla., waterfront project

The city of St. Petersburg, Fla., invites firms to submit their ideas for a new and improved pier for Florida's fifth largest city.

boombox1
boombox2
native1

More In Category

Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021