Cell and Genome Sciences Building, Farmington, Conn.

Cell and Genome Sciences Building, Farmington, Conn.


By By Jay W. Schneider, Editor | October 12, 2010

Administrators at the University of Connecticut Health Center in Farmington didn’t think much of the 1970s building they planned to turn into the school’s Cell and Genome Sciences Building. It’s not that the former toxicology research facility was in such terrible shape, but the 117,800-sf structure had almost no windows and its interior was dark and chopped up.

Enter the Building Team of Goody Clancy (architect) and FIP Construction (GC), who worked with the university to create an open, bright, and sustainable home (targeting LEED Silver) for three major research programs: UConn Stem Cell Institute, the R.D. Berlin Center for Cell Analysis and Modeling, and the Department of Genetics and Developmental Biology.

But how to get daylight deep into the lab spaces? Fortunately, the one-story framework allowed light to be brought in from above. The Building Team ran a 464-foot-long skylight the length of the main corridor, and clerestory windows were installed above the “Crossroads,” a central gathering and eating space that features a newly raised roof.

Additional daylighting comes from 56 new windows installed in exterior walls—not an easy task, given the building’s concrete panel construction. The team calculated the maximum window size allowable without compromising the panels and then standardized all windows to that size. Louvered sunshades were added above each of these.

Interior walls were also punched through with window openings to further distribute daylight. Leaving interior walls largely in place also kept construction costs down, to $259/sf (inclusive of site work). Also helping the budget: refurbishing and reconfiguring existing metal casework in research labs, which were extensively upgraded to modern research and safety standards, and finishing the new 100-seat auditorium in wood paneling left over from another campus project.

The facility’s wetlands site was carefully reconfigured to accommodate extra parking, and a bioretention pond was added to control runoff and keep stormwater out of the town’s sewer system. Also, because the existing building lacked a recognizable “front door,” a proper front entrance was added.

“It’s very difficult to do these types of buildings, and this one was very well done,” said David Callan, SVP, Environmental Systems Design, Chicago. “Excellent job on a low budget.” BD+C

PROJECT SUMMARY

Building Team

Submitting firm: Goody Clancy (architect)

Owner/developer: University of Connecticut Health Center

CM: FIP Construction

Structural engineer: LeMessurier Consultants Inc.

M/E engineer: Cosentini Associates

Plumbing engineer: BVH Integrated Services

General Information

Size: 117,813 gsf

Construction cost: $30.53 million

Construction time: September 2008 to June 2010

Delivery method: CM at risk

Related Stories

Building Technology | Mar 8, 2019

What is your firm's innovation 'hit rate'?

As firms begin to adopt the practices and mindset of Silicon Valley tech and advanced manufacturing, it’s fair to ask: Are all of these innovation projects and initiatives working?

Architects | Mar 7, 2019

HED, Integrated Design Group to merge firms

ID has a strong reputation for data center design with locations in Boston in Dallas.

Architects | Mar 5, 2019

Arata Isozaki named 2019 Pritzker Architecture Prize Laureate

The Japanese architect, city planner, and theorist is known for his deep commitment to the “art of space” and transnational methodology.

Architects | Feb 14, 2019

Amazon will not build HQ2 in New York City

The tech giant walks away from a deal, succumbing to opposition over huge tax breaks.

Architects | Feb 12, 2019

The basics of building commissioning

As building system technology increases in complexity and sustainability remains at the forefront of design, the need for commissioning continues to rise. This is the first post in our series examining the basics, benefits and boundaries of building commissioning.

Architects | Jan 28, 2019

9 tech trends to track in 2019

Innovations in voice recognition, cognitive neuroscience, and biometrics are among the trending tech topics for 2019, according to CallisonRTKL's Kristin Tilley.

AEC Tech | Jan 9, 2019

Our robotic future: Assessing AI's impact on the AEC profession and the built environment

This is the first in a series by Lance Hosey, FAIA, on how automation is disrupting design and construction.

Architects | Dec 17, 2018

New toolkit helps architect achieve high-performance buildings

Architects can download a copy of the toolkit online.

Architects | Dec 13, 2018

Social media synergy: Revving up your AEC firm’s content engine

Design firms know that just having a website and a blog aren’t enough, but social media complicates how they communicate.   

boombox1
boombox2
native1

More In Category


Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.



Libraries

Reasons to reinvent the Midcentury academic library

DLR Group's Interior Design Leader Gretchen Holy, Assoc. IIDA, shares the idea that a designer's responsibility to embrace a library’s history, respect its past, and create an environment that will serve student populations for the next 100 years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021