China builds 645,000-sf coronavirus hospital in 10 days

Healthcare Facilities

China builds 645,000-sf coronavirus hospital in 10 days

The project began construction on Jan. 23.


By David Malone, Associate Editor | February 3, 2020
Huoshenshan hospital

Images courtesy Xinhua

A new hospital in Wuhan, China, built to treat patients of the coronavirus outbreak, has finished construction in just 10 days, according to an Associated Press article.

The 645,000-sf Huoshenshan Hospital relied on the use of prefabricated rooms and 7,000 engineers, carpenters, electricians, plumbers, and other tradesmen working around the clock to complete the project so quickly. The two-story, 1,000-bed facility houses patient wards, which includes isolation wards and 30 intensive-care units; bathrooms; doctor rooms, and nurse stations, the Associated Press said, citing China’s Yangtze Daily newspaper.

Huoshenshan Hospital under construction fromabove

Specialized ventilation systems and double-sided cabinets that connect patient rooms to hallways allow staff to bring supplies to patients without having to enter the rooms. Infrared scanners will warn if any staff members show signs of fever. A video system, installed in fewer than 12 hours, will allow doctors to talk with experts in Beijing’s PLA General Hospital.

 

See Also: The complex dance of healthcare transitioning

 

A second facility, the 1,500-bed Leishenshan Hospital, is set to open Wednesday after beginning construction on Jan. 27.

 

Related Stories

| Mar 21, 2012

Iowa’s Mercy Medical Center’s new Emergency Department constructed using Lean design

New Emergency Department features a "racetrack" design with a central nurses' station encircled by 19 private patient examination rooms and 2 trauma treatment rooms. 

| Mar 19, 2012

HKS Selected for Baylor Medical Center at Waxahachie

Baylor Medical Center at Waxahachiewill incorporate advanced technology including telemedicine, digital imaging, remote patient monitoring, electronic medical records and computer patient records. 

| Mar 14, 2012

Tsoi/Kobus and Centerbrook to design Jackson Laboratory facility in Farmington, Conn.

Building will house research into personalized, gene-based cancer screening and treatment.

| Mar 6, 2012

Country’s first Green House home for veterans completed

Residences at VA Danville to provide community-centered housing for military veterans.

| Mar 1, 2012

7 keys to ‘Highest value, lowest cost’ for healthcare construction

The healthcare design and construction picture has been muddied by uncertainty over the new healthcare law. Hospital systems are in a bind, not knowing what levels of reimbursement to expect. Building Teams serving this sector will have to work even harder to meet growing client demands.

| Feb 29, 2012

Construction begins on Keller Army Community Hospital addition

The 51,000 square foot addition will become the home for optometry, ophthalmology, physical therapy, and orthopedics clinics, as well as provide TRICARE office space.

| Feb 29, 2012

Shepley Bulfinch selected to design new Children’s Hospital of Buffalo

The firm was selected because of their past experience in designing clinically complex facilities that emphasize patient- and family-centered care and operational efficiency as well as distinctive architectural forms for many other children's and women's hospitals.

| Feb 28, 2012

More than 1,000 have earned EDAC certification since 2009

Milestone achieved as evidence-based design becomes a top 2012 strategy for healthcare organizations.

| Feb 28, 2012

McCarthy completes second phase of San Diego’s Scripps Hospital

Representing the second phase of a four-phased, $41.3 million expansion and remodeling project, the new addition doubles the size of the existing emergency department and trauma center to encompass a combined 27,000 square feet of space. 

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021