The new home for the L.A. Rams and L.A. Chargers will not be opening as soon as was originally intended. The 70,000-seat stadium was initially scheduled to be ready in time for the 2019 NFL season, but thanks to a surfeit of rain the opening will be delayed until the start of the 2020 season, the Los Angeles Times reports.
The rainfall in the area didn’t just reach record amounts, but it also occurred at the worst possible time during the HKS-design stadium’s construction: the excavation phase.
At times, the stadium’s excavation site was filled with as much as 10 to 12 feet of standing water, which needed to be drained before work could resume. This caused the project, which is being built by Turner Construction and AECOM, to screech to a halt for two months.
The two months can’t be made up over the next two years, thus getting the project back on schedule, due to an already ambitious construction timetable and the increased workload associated with creating a stadium that will house two separate teams, according to the LA Times.
Due to the delay, the Rams will continue to play in the Coliseum for the 2019 season while the Chargers will have to play their home games at the StubHub Center for an extra season. While the Coliseum has a seating capacity of around 93,000, the StubHub center only offers 27,000 seats, but this will be expanded to 30,000 for Chargers games.
The stadium will be the focal point of a mixed-use entertainment district that will include a 300-room hotel, retail and office space, and a 6,000-seat performance venue.
Related Stories
Sports and Recreational Facilities | Jul 7, 2021
Chicago’s first indoor track and field facility features a hydraulically banked track
It is the first hydraulically banked track in Illinois.
Resiliency | Jun 24, 2021
Oceanographer John Englander talks resiliency and buildings [new on HorizonTV]
New on HorizonTV, oceanographer John Englander discusses his latest book, which warns that, regardless of resilience efforts, sea levels will rise by meters in the coming decades. Adaptation, he says, is the key to future building design and construction.
Sports and Recreational Facilities | Jun 16, 2021
Populous designs 9,000-seat stadium and training center for the Brisbane Lions
The project will include fields for public use.
Digital Twin | May 24, 2021
Digital twin’s value propositions for the built environment, explained
Ernst & Young’s white paper makes its cases for the technology’s myriad benefits.
Sports and Recreational Facilities | May 17, 2021
Indoor volleyball and basketball complex set for St. Louis
The project will be the largest youth volleyball and basketball facility in St. Louis.
Sports and Recreational Facilities | May 11, 2021
Total Quality Logistics Stadium completes in Cincinnati
Populous designed the project.
Sports and Recreational Facilities | Apr 27, 2021
Populous completes Phase II of renovations at Georgia Tech’s Mac Nease Baseball Park at Russ Chandler Stadium
The project includes a new, year-round elite training facility.
Sports and Recreational Facilities | Apr 9, 2021
AdventHealth Training Center breaks ground in Orlando
HOK designed the project.
Sports and Recreational Facilities | Mar 26, 2021
Populous and SRG Partnership selected to transform Oregon State University’s Reser Stadium
Populous has recently release renderings of the project.
Market Data | Feb 24, 2021
2021 won’t be a growth year for construction spending, says latest JLL forecast
Predicts second-half improvement toward normalization next year.