ST. LOUIS (April 14, 2020) – The design-build team of Tarlton Corp., a St. Louis-based general contracting and construction management firm, working for the U.S. Army Corps of Engineers, completed conversion April 11 of a Florissant, Mo., hotel into an alternate healthcare facility to treat non-acute COVID-19 patients. The facility, if needed, would serve as backup for patients referred by St. Louis-area hospitals and would be staffed by members of the Missouri National Guard.
The project yielded more than 100 patient rooms on the four floors of the 130-room hotel. The team built a nurses’ station on each floor and turned the existing phone system into a nurse call system. Beds and furniture were moved. Extra furniture was put into temporary storage. PTAC units in rooms were inspected and repaired or replaced as necessary. Hardware was changed on hotel room doors and bathroom doors to disable locks. All rooms were deep cleaned. In 13 rooms, carpet was removed and walls and ceilings were painted.
Project scope also included steps to ensure proper ventilation for a patient care facility: inspection and cleaning of HVAC units; relocation of exhaust fans within 25 feet of HVAC intakes; extension of plumbing vents within 25 feet of HVAC intakes; and construction of isolation barriers in the corridors (three per floor) to separate the elevator/nurse station areas from the three patient wings.
100+ WORKERS ON THE DESIGN-BUILD TEAM
More than 100 employees from the design-build team, including 50 from Tarlton, worked on site at the Quality Inn from April 8 to 11 to help USACE complete its mission in less than 100 hours. The team consisted of Tarlton (design-build contractor), Ross & Baruzzini (architectural/engineering services), Rock Hill Mechanical Corp., and Guarantee Electrical Co.
Subcontractors working on the conversion included C&R Mechanical’s Plumbing Division, Collins & Hermann, Dynamic Air Solutions, Flooring Systems Inc., Jos. Ward Painting Co., Midwest Elevator, Stanley Steemer, Tech Electronics, Waterhout Construction, and Woodard Cleaning and Restoration.
Workers inspect rooftop units in support of ensuring healthy air circulation in the alternate care facility.
Government, health, and hospital officials toured the facility at 55 Dunn Road over the weekend and Monday morning. USACE Maj. Gen. R. Mark Toy recognized all the participants for their work. State agencies involved included the Missouri National Guard, Department of Public Safety, State Emergency Management Agency, Department of Health and Senior Services, Office of Administration and the Missouri Hospital Association, in partnership with FEMA and the U.S. Department of Health and Human Services.
“I’m proud of the quick and thorough response our team put together and executed,” said Tracy Hart, President of Tarlton. “We feel honored to be trusted by the Army Corps of Engineers for this critical project that is so important to our community.”
Becky Mehaffy, Tarlton workforce manager, said, “Our group jumped right in there with the single goal to get it done safely and on time. I’ve seen a lot in my years in this industry—never anything like this.”
“Our design-build partners, subcontractors, and consultants were critical to the project’s success,” said Tarlton COO Dirk Elsperman. “Everyone brought ideas and the will to succeed—a strong commitment to the 12:01 a.m. Sunday turnover."
"It was an extraordinary integrated design-build effort,” said Michael Shea, AIA, Ross & Baruzzini SVP/Director of Government. Guarantee Electrical President Dave Gralike added: “We are especially proud of our team and all the contractors and tradespeople involved in this quick turnaround project.”
Individual patient room at ACF in Florissant, Mo.
Related Stories
Coronavirus | Mar 16, 2020
Effective remote workforce: Key steps and strategies for success
As the potential scope of the COVID-19 outbreak has become more clear in the United States and Canada, public and private organizations from all industries, sectors and geographies are encouraging their teams to work remotely to reduce the spread of the virus.
Coronavirus | Mar 16, 2020
Coronavirus and the water cycle—here is what treatment professionals need to know
As the global health community tracks the spread of this virus, it’s important for water and wastewater professionals to keep updated on potential impacts.
Coronavirus | Mar 15, 2020
Designing office building lobbies to respond to the coronavirus
Touch-free design solutions and air purifiers can enhance workplace wellness.
Coronavirus | Mar 15, 2020
In the face of the coronavirus, workplace wellness is key
Here are a few considerations employers should keep in mind in creating plans for a healthy and effective work environment.
Coronavirus | Mar 13, 2020
AEC business impacts from COVID-19: We want your input!
The BD+C editors would like to hear from you on how your firm is handling business operations and projects during the coronavirus outbreak.
Coronavirus | Mar 13, 2020
COVID-19 and real estate: How the coronavirus is impacting the AEC industry
Here's the latest news BD+C editors are tracking on COVID-19's impact on the AEC industry and the real estate market.
Coronavirus | Mar 11, 2020
A look at how U.S. hospitals are designed to battle infectious diseases like coronavirus
Some health systems can use telehealth and video visits to asses and triage patients before they arrive at a hospital.