COVID-19 has altered the speed and design of healthcare projects, perhaps irrevocably

Healthcare Facilities

COVID-19 has altered the speed and design of healthcare projects, perhaps irrevocably

Healthcare clients want their projects up and running quicker, a task made more complicated by the shortage of skilled labor in many markets.


By John Caulfield, Senior Editor | December 15, 2021
COVID-19 has altered the speed and design of healthcare projects, perhaps irrevocably vcu-chor-rendering
HKS-designed VCU Health’s ground-up 500,000-sf Children’s Hospital of Richmond is being built by DPR Construction and is scheduled for completion in 2023. For the first time, VCU Health’s pediatric services will operate from one building, dubbed the Wonder Tower, with 72 private rooms and shell space for 48 more if needed. The tower will connect by bridge to the hospital’s outpatient pavilion built in 2016. The hospital’s Emergency Department will extend 5,000 sf. Rendering: HKS

A six-story, 180,000-sf patient tower addition to BayCare St. Joseph’s Hospital in Tampa, Fla., was well under way when, in the summer of 2020, the healthcare system wanted to open three patient floors earlier than scheduled to accommodate the COVID-19 pandemic’s anticipated surge.

The project’s construction manager, Robins & Morton, brought in additional supervisory staff to coordinate this compressed schedule with other building team members, which included AE firm HOK and structural engineer Carastro Engineering. As a result of this collaboration, the tower opened two months early, in July 2020, says Robins & Morton’s President and COO Robin Savage.

This has been a common tale during the pandemic, told by AEC firms whose healthcare clients want their projects up and running quicker, a task made more complicated by the shortage of skilled labor in many markets.

“A major challenge has included changes made during design and construction while maintaining the budget,” states Matthew Holmes, Global Solutions Director of Health Infrastructure for the construction management firm Jacobs, 70 percent of whose healthcare-related work last year involved in-patient design. To mitigate this issue, Jacobs continuously forecasts estimates during a project to leverage proper budgeting. “Taking the time to accurately scope the project in the budgeting process is essential,” Holmes says.

“The healthcare core market continues to operate on razor-thin margins,” observes Hamilton Espinosa, DPR Construction’s Healthcare Core Market Leader. “The need to project value and efficiency is at the forefront of key decision-making.” 

A geotechnical report conducted during preconstruction of a 32,000-sf Veterans Affairs outpatient clinic in Johnson County, Kan., uncovered an unexpected need for rock excavation totaling $150,000. McCownGordon Construction, the project’s CM, reduced that allowance to $100,000 by rerouting the water, fire, and storm utilities, recalls Daniel Lacy, the firm’s Vice President−Healthcare and Life Sciences.

Many of Jacobs’ healthcare projects entail what Holmes calls “progressive design-build,” where the designer and builder work together “from day one with an established budget and program description.” Early project team engagement, asserts Pepper Construction’s Project Director Brian Mullen, CHC, LEED AP, is critical because “it leads to more informed design.” And by remaining flexible to accommodate future improvements in interior remodeling, Pepper “can help ensure that clients are prepared to incorporate the latest technology.” 

By aligning a project manager with key designer, trade partner, and healthcare system personnel, McCarthy Building Companies is able to “triage” questions and ask only what’s needed to move the project forward. Then, it can provide options for consideration, says Patrick Peterson, McCarthy’s Executive Vice President of Healthcare for the Southern California region.

AEC firms have had to be creative to find skilled labor to complete healthcare projects within time and budget parameters. To connect with smaller and more diverse subcontractors, Skanska breaks up its bid packages “to widen the labor pool,” says Chris Hopper, its Vice President and General Manager. Skanska also conducts its Construction Management Building Blocks Training Program in its offices across the country to engage smaller subs through partnership and business development.

HEALTHCARE PROJECTS BACK ON TRACK

AEC Giants contacted for this report say they’ve been working on a wide range of healthcare projects. But the agenda for some clients shifted between 2020 and 2021. 

Most of Henderson Engineers’ healthcare projects over the past year were for “temporary measures” that included infrastructure to support care for COVID-19 patients, says Mark Chrisman, Healthcare Practice Director for Henderson Engineers and Henderson Building Solutions. But since early 2021, “demand for construction and renovation projects of all sizes has reverted close to pre-pandemic levels.”

COVID-19 has altered the speed and design of healthcare projects, perhaps irrevocably Skanska_UVA
The $329 million, 444,000-sf expansion and renovation of the University of Virginia Health System’s University Hospital in Charlottesville increased bed capacity to 84 (all of them ICU-compliant), with the potential for up to 180 beds. The architect was Perkins and Will. Skanska the CM at Risk on this LEED Silver project, which was completed in July 2020. Photo: Halkin|Mason Photography, courtesy Skanska

During the pandemic, DPR Construction pivoted to respond to help with clients’ immediate needs. But much of its work continued to be for new hospitals and patient tower expansions. There’s strong demand for outpatient care, too, although health systems are re-evaluating program sizes to factor the impact of virtual healthcare and remote patient monitoring for lower-acuity chronic case management, say Sean Ashcroft and Deb Sheehan, DPR’s Healthcare Core Market Leader and Healthcare Strategy Lead, respectively.

While new construction that included the nine-story Children’s Mercy Research Institute in Kansas City, Mo., accounted for McCownGordon’s largest recent healthcare projects, the majority, in terms of volume, have been adaptive reuse, says Lacy. McCarthy’s Peterson points out that healthcare clients are exploring strategies for maintaining aging buildings and repurposing existing spaces for “a changing service model.”

AEC firms are engaging more renovations and expansions, too. McCarthy recently worked on the Loma Linda University Medical Center’s Campus Transformation Project to bring it up to California’s seismic compliance requirements. 

Brian Forsythe, LEED AP, CHC, Pepper’s Vice President and Project Director, predicts that clients who have delayed master-planning projects will need to move forward to remain competitive. And he cites a trend toward public-private partnerships to fund healthcare projects, such as the University of Illinois Health’s 205,000-sf Outpatient Surgery Center and Specialty Clinics in Chicago, for which Provident Resources Group, a 501(c)(3) corporation, is financing three-quarters of the building’s $194 million total cost through tax-exempt bonds, and will lease the building to UI Health during the 30-year term of the bonds. This project should be completed next year.

UNIVERSAL PATIENT ROOMS ARE IN VOGUE

Alternative project delivery is among the design and construction trends that have emerged in the healthcare sector. The University of Illinois project, designed by Shive Hattery, deployed modular construction to stay within budget. One of Robins & Morton’s priorities is to determine how to leverage prefabrication and modularization, says Savage. And during the pandemic, the controlled environment and potentially higher production rates that prefab offers “took on a renewed sense of urgency” for McCarthy. Peterson says prefab systems his firm now focuses on include exterior envelopes, framing and wall panels, MEP, medical and interiors, bathrooms, and vertical transportation.

Skanska is among the AEC firms that have been getting more requests for larger private and “universal” rooms. For its University of Virginia Health System hospital expansion in Charlottesville, Skanska built a patient tower with fully ICU-compliant universal patient beds. Chrisman of Henderson Engineers says that healthcare providers are showing a “strong desire” to establish permanent isolation rooms to manage patients during infectious disease outbreaks. 

Other trends in healthcare projects that Jacobs’ Holmes is seeing include high-end technology for patient and procedural spaces, combined heat and power turbines for steam and electricity, combined pre- and post-recovery bays, more space allotted for telehealth and behavioral health, and growth in emergency departments.

The Phoenix-based architectural planning and interior design firm Orcutt | Winslow has experimented lately with alternate structural solutions to steel framing and joists, such wide-flange structural frames and steel-masonry hybrids. The firm is also increasingly using Lean approaches, such as pull planning, to improve a project’s speed to market, says Chuck Hill, its Healthcare Studio Leader.

Matthew Kennedy, Orcutt | Winslow’s Senior Healthcare Planner, adds that his firm has tried out several digital media platforms—such as Miro and Microsoft Teams—for communications and file sharing. It’s not alone, as virtual interaction has become the norm in a socially distanced world. 

When the pandemic hit, Skanska saw an opportunity to use StructionSite, a project site photo documentation software, to conduct virtual job walks abetted by advanced imagery and video. Pepper leverages web-based platforms “to bring everyone to the jobsite virtually,” says Forsythe. During the pandemic, Pepper also launched Virtual Reality Training modules, and expanded its use of TouchPlan with the Last Planner System for digital pull planning. Robins & Morton’s application of technology for healthcare projects includes entirely virtual mockups, 3D printing, augmented reality, and testing robots to photograph and laser-scan jobsites.

SUSTAINABLE AND RESILIENT HEALTHCARE BUILDINGS

Healthcare systems are trying to change their reputation for being profligate users of energy and water by seeking project solutions for efficiency, carbon neutrality, sustainability, and resilience.

Savage of Robins & Morton points out that healthcare clients are interested in stemming carbon emissions that are mostly released from the material supply chain before a new or renovated facility even opens. Skanska’s Hopper cites a 2020 Health Affairs study, which estimated that the healthcare industry accounted for more than 8 percent of CO2 emissions in the U.S. “Healthcare systems have made carbon reduction a part of their collective mission and values,” says Hopper.

Concerns about embodied carbon can be tied to a larger effort among healthcare systems and their AEC partners in favor of environmental sustainability and resilience. One of Robins & Morton’s projects—the recently completed Fisherman’s Community Hospital in Marathon, Fla.—sits on higher elevation to combat storm surges, has a tilt-up concrete core, and includes impact-resistant exterior and removable flood barriers.

Chrisman expects larger healthcare systems with financial means to be the main drivers of sustainability and resilience over the next decade. Client demand was one of the reasons why Henderson last April hired its first director of sustainability, Brian Alessi, AIA, LEED AP BD+C, who has worked on more than 400 LEED-certified, net-zero, and passive house projects. 

By August 29, Louisiana had evacuated 22 nursing homes and 18 assisted living facilities as Category 4 Hurricane Ida was pounding that state’s coast. However, 2,400 COVID-19 patients still in Louisiana hospitals hadn’t been moved, partly because there was no other place to put them, but also because modern hospitals are better prepared to stay open during natural disasters.

“COVID-19 has made clear there is a need to increase and maintain resilient healthcare systems through a holistic approach to how, when, and where we access care,” says Jacobs’ Holmes. “Sustainability is a required item and, at Jacobs, that means ensuring long-term business resilience.”

McCarthy’s Peterson says that resilience “is built into every healthcare design we see.” And Hill of Orcutt | Winslow is confident that once this sector is less distracted by its immediate supply-chain issues, “resilience will emerge as a driver” for healthcare projects.

Related Stories

| Mar 3, 2011

HDR acquires healthcare design-build firm Cooper Medical

HDR, a global architecture, engineering and consulting firm, acquired Cooper Medical, a firm providing integrated design and construction services for healthcare facilities throughout the U.S. The new alliance, HDR Cooper Medical, will provide a full service design and construction delivery model to healthcare clients.

| Mar 1, 2011

New survey shows shifts in hospital construction projects

America’s hospitals and health systems are focusing more on renovation or expansion than new construction, according to a new survey conducted by Health Facilities Management magazine and the American Society for Healthcare Engineering (ASHE). In fact, renovation or expansion accounted for 73% of construction projects at hospitals responding to the survey.

| Feb 22, 2011

HDR Architecture names four healthcare directors

Four senior professionals in HDR Architecture’s healthcare program have been named Healthcare directors.

| Feb 17, 2011

HDR Architecture sponsors national effort to green operating rooms

HDR Architecture, Inc. has joined the group of corporate sponsors of Practice Greenhealth’s Greening the Operating Room Initiative. This sweeping and prescriptive path to green the nation’s operating rooms was launched earlier this year to reduce the environmental footprint of the operating suites in hospitals across the country, which can produce between 20 and 30% of a hospital’s total waste.

| Feb 11, 2011

Iowa surgery center addresses both inpatient and outpatient care

The 12,000-person community of Carroll, Iowa, has a new $28 million surgery center to provide both inpatient and outpatient care. Minneapolis-based healthcare design firm Horty Elving headed up the four-story, 120,000-sf project for St. Anthony’s Regional Hospital. The center’s layout is based on a circular process flow, and includes four 800-sf operating rooms with poured rubber floors to reduce leg fatigue for surgeons and support staff, two substerile rooms between each pair of operating rooms, and two endoscopy rooms adjacent to the outpatient prep and recovery rooms. Recovery rooms are clustered in groups of four. The large family lounge (left) has expansive windows with views of the countryside, and television monitors that display coded information on patient status so loved ones can follow a patient’s progress.

| Feb 11, 2011

Two projects seek to reinvigorate Los Angeles County medical center

HMC Architects designed two new buildings for the Los Angeles County Martin Luther King, Jr., Medical Center as part of a $360 million plan to reinvigorate the campus. The buildings include a 120-bed hospital, which involves renovation of an existing tower and several support buildings, and the construction of a new multi-service ambulatory care center. The new facilities will have large expanses of glass at all waiting and public areas for unobstructed views of downtown Los Angeles. A curved glass entrance canopy will unite the two buildings. When both projects are completed—the hospital in 2012 and the ambulatory care center in 2013—the campus will have added more than 460,000 sf of space. The hospital will seek LEED certification, while the ambulatory care center is targeting LEED Silver.

| Feb 9, 2011

Hospital Construction in the Age of Obamacare

The recession has hurt even the usually vibrant healthcare segment. Nearly three out of four hospital systems have put the brakes on capital projects.  We asked five capital expenditure insiders for their advice on how Building Teams can still succeed in this highly competitive sector.

| Jan 31, 2011

Cuningham Group Architecture launches Healthcare studio with Lee Brennan

International design firm Cuningham Group Architecture, P.A. (Cuningham Group) has announced the arrival of Lee Brennan, AIA, as Principal and Leader of its new Healthcare studio. Brennan comes to Cuningham Group with over 30 years of professional experience, 22 of those years in healthcare, encompassing all aspects of project delivery, from strategic planning and programming through design and construction. The firm’s new Healthcare studio will enhance Cuningham Group’s expertise in leisure and entertainment, education, mixed-use/housing and workplace environments.

| Jan 31, 2011

HDR Architecture Releases Evidence-based Design Videos

As a follow-up to its book Evidence-based Design for Healthcare Facilities, HDR Architecture, Inc. has released three video case studies that highlight evidence-based design principles in action.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021