Data center construction costs for 2024

Construction Costs

Data center construction costs for 2024

This table shows a five-year view of costs per square foot for one-story computer data centers. 


By Gordian | July 18, 2024
Data center construction costs for 2024, Gordian RSMeans. Image by Pete Linforth from Pixabay

Image by Pete Linforth from Pixabay

The drive toward smart cities necessitates substantial investment in modernizing data centers, which are the technological backbone of this transformation. Data centers have evolved from traditional physical servers to complex networks that support applications across multi-cloud environments. This modern infrastructure is essential for cities to become more efficient, business-friendly, and livable.

However, upgrading data centers to meet these smart city demands comes with significant costs. The advanced features required for these facilities, such as high-speed connectivity, security, and energy efficiency, contribute to the overall expense. Despite the high costs, these investments are critical for cities to remain competitive and to provide the expected level of public service in the digital age. 

Current, localized construction cost data is crucial for creating accurate budgets, planning future expansions, ensuring timely project completion and maintaining a competitive edge. Gordian’s data features more than 100 building models, including computer data centers. These localized models allow architects, engineers, and other preconstruction professionals to quickly and accurately create conceptual estimates for future builds. This table shows a five-year view of costs per square foot for one-story computer data centers. 

Visit rsmeans.com/bdandc for more information about Gordian’s RSMeans Data.

Location

2020

2021

2022

2023

2024

5-Year Change

National Average

$380.66

$384.97

$409.48

$447.91

$468.66

23.12%

New York, NY

$537.83

$545.30

$569.75

$604.27

$639.83

18.97%

Chicago, IL

$465.73

$470.97

$494.26

$536.91

$561.33

20.53%

Boston, MA

$448.40

$448.02

$479.69

$522.90

$543.43

21.19%

Los Angeles, CA

$440.10

$445.51

$472.86

$519.68

$545.05

23.85%

Ann Arbor, MI

$374.18

$383.16

$402.05

$431.41

$453.86

21.29%

Omaha, NE

$342.87

$349.92

$364.05

$401.75

$419.71

22.41%

Denver, CO

$335.68

$339.71

$362.74

$396.33

$416.33

24.03%

Atlanta, GA

$323.09

$330.83

$352.09

$386.26

$407.77

26.21%

Phoenix, AZ

$323.02

$320.24

$345.39

$386.40

$407.58

26.18%

Dallas, TX

$306.35

$309.88

$330.99

$361.55

$379.21

23.78%

Please note: Square foot models are used for planning and budgeting and are not meant for detailed estimates.


More building construction cost reports from Gordian:

Related Stories

Construction Costs | Oct 16, 2024

Construction Crane Index: Most major markets’ crane counts increase or hold steady in third quarter

Rider Levett Bucknall’s (RLB’s) latest Crane Index and Quarterly Cost Report shows continued decreasing cost inflation and crane counts increasing or holding steady in 10 of the 14 major markets it surveyed. The national average increase in construction costs was 1.07%, the lowest it’s been in the last three years.

Construction Costs | Sep 2, 2024

Construction material decreases level out, but some increases are expected to continue for the balance Q3 2024

The Q3 2024 Quarterly Construction Insights Report from Gordian examines the numerous variables that influence material pricing, including geography, global events and commodity volatility. Gordian and subject matter experts examine fluctuations in costs, their likely causes, and offer predictions about where pricing is likely to go from here. Here is a sampling of the report’s contents.

Construction Costs | Jun 3, 2024

Escalation: Predicting project costs in a volatile market

Thad Berkes, Chief Cost Estimator, Design Collaborative, shares that one of the major hurdles that Design Collaborative attempts to forecast for its commercial construction projects is escalation.

Construction Costs | May 31, 2024

Despite challenges, 2024 construction material prices continue to stabilize

Gordian’s Q2 2024 Quarterly Construction Cost Insights Report indicates that supply chain issues notwithstanding, many commodities are exhibiting price normalization.

Construction Costs | May 16, 2024

New download: BD+C's May 2024 Market Intelligence Report

Building Design+Construction's monthly Market Intelligence Report offers a snapshot of the health of the U.S. building construction industry, including the commercial, multifamily, institutional, and industrial building sectors. This report tracks the latest metrics related to construction spending, demand for design services, contractor backlogs, and material price trends.

Healthcare Facilities | May 6, 2024

Hospital construction costs for 2024

Data from Gordian breaks down the average cost per square foot for a three-story hospital across 10 U.S. cities.

Construction Costs | Apr 18, 2024

New download: BD+C's April 2024 Market Intelligence Report

Building Design+Construction's monthly Market Intelligence Report offers a snapshot of the health of the U.S. building construction industry, including the commercial, multifamily, institutional, and industrial building sectors. This report tracks the latest metrics related to construction spending, demand for design services, contractor backlogs, and material price trends.

Construction Costs | Apr 16, 2024

How the new prevailing wage calculation will impact construction labor costs

Looking ahead to 2024 and beyond, two pivotal changes in federal construction labor dynamics are likely to exacerbate increasing construction labor costs, according to Gordian's Samuel Giffin.

Construction Costs | Apr 11, 2024

Construction materials prices increase 0.4% in March 2024

Construction input prices increased 0.4% in March compared to the previous month, according to an Associated Builders and Contractors analysis of the U.S. Bureau of Labor Statistics’ Producer Price Index data released today. Nonresidential construction input prices also increased 0.4% for the month.

Construction Costs | Mar 15, 2024

Retail center construction costs for 2024

Data from Gordian shows the most recent costs per square foot for restaurants, social clubs, one-story department stores, retail stores and movie theaters in select cities.

boombox1
boombox2
native1

More In Category


Construction Costs

Construction material decreases level out, but some increases are expected to continue for the balance Q3 2024

The Q3 2024 Quarterly Construction Insights Report from Gordian examines the numerous variables that influence material pricing, including geography, global events and commodity volatility. Gordian and subject matter experts examine fluctuations in costs, their likely causes, and offer predictions about where pricing is likely to go from here. Here is a sampling of the report’s contents.



halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021