Design problems now the primary cause of construction claims and disputes

Codes and Standards

Design problems now the primary cause of construction claims and disputes

More likely to occur due to more tight timescales imposed upon third parties engaged in design.


By Peter Fabris, Contributing Editor | December 15, 2021
excavator
Courtesy Pixabay

Design problems are now the primary cause of construction claims and disputes, according to HKA's CRUX Insight 2020 report.

“Design problems are more likely to occur as a result of increasingly tight timescales imposed upon third parties engaged in design” that result in late or incomplete designs and conflict between the parties, the report says. “Failings in the management of third parties across increasingly complex supply chains” also cause major problems.

The consulting firm’s previous report had found that change in project scope was the number one cause for disputes. Projects have also become more prone to deficiencies in workmanship and unforeseen physical conditions, the report found.

The report’s data was primarily compiled before the start of the COVID-19 pandemic. The report examined construction issues in 1,185 projects worldwide with a combined value of $1.8 trillion. HKA expects an increase in arbitration over litigation to settle disputes in the coming years.

Related Stories

Codes and Standards | Aug 11, 2021

Decentralized approach to codes means emissions reduction responsibility falls on local officials

Efficiency advocates focusing more on local code amendments.

Digital Twin | Aug 9, 2021

Digital Twin Maturity white paper offers guidance on digital twin adoption

Provides lifecycle map and an approach for incorporating digital twins.

Codes and Standards | Aug 5, 2021

Contractors can be liable for building failures many years after project completion

Personal injury suits could be brought decades after substantial completion.

Codes and Standards | Aug 4, 2021

Mass timber is a natural choice for building recycling through deconstruction

Designing wood buildings to optimize recovery of materials for disassembly aids carbon sequestration.

Codes and Standards | Aug 3, 2021

Dept. of Energy releases initial version of the Spawn of EnergyPlus software

Targets new use cases in advanced controls, district systems, and grid integration.

Codes and Standards | Aug 2, 2021

Several U.S. cities among most expensive places to build in the world

San Francisco, New York, and Boston head the domestic list.

Codes and Standards | Jul 28, 2021

American Concrete Institute creates new director of innovative concrete technology post

Aim is to attract emerging technologies for development.

Codes and Standards | Jul 28, 2021

Higher ed faces infrastructure backlog of $112.3 billion

Study recommends integrated strategic planning for best results.

Codes and Standards | Jul 27, 2021

Add a wobbly moon to flooding risk factors

Earth satellite’s orbit variations will lead to sunny-day flooding in the mid-2030s.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021