The Union Trust Building, commissioned by coal magnate Henry Clay Frick and completed in 1917, originally was a 240-store shopping arcade with 700 offices on its upper floors.
This 11-story Flemish-Gothic–style building has had several owners. The latest, Pittsburgh native Jon Davis, CEO of The Davis Companies, paid $14 million in 2014 with the intention of revitalizing it into an amenities-rich commercial center.
The building was in such disrepair that much of the reconstruction budget had to go toward structural, mechanical, and electrical infrastructure improvements that included opening up deep floor plates and removing valances on windows (added long after the building first opened) to let in more daylight.
The limestone exterior was cleaned. The leaking mansard roof was repaired and restored. A new rooftop cooling system, hidden by a contemporary screen, was installed. Ten passenger elevators and two freight elevators were modernized.
Cross axes that emanate from a central rotunda split Union Trust’s cruciform-shaped design into four quadrants. The interior features a grand atrium topped by a Tiffany glass dome measuring 40 feet in diameter. The project team relit the dome to draw eyes upward. The rotunda, now with comfortable seating, serves as a greeting area for office tenants; it can also be rented for events.
More than 19,000 sf of New Zealand wool carpet was laid throughout the building, with color changes on different floors that coordinate with 30 pieces of art that were commissioned for the building.
Amenities include a new fitness center, a renovated seminar room and breakout area, a marketing center, and a concierge desk in the lobby. Parking for 190 vehicles was added in the basement and sub-basement. The National Park Service allowed for the addition of glass canopies at the exterior entries and exposed ductwork to achieve higher interior ceiling heights.
Project Summary
Gold Award Winner
Building Team: Elkus Manfredi Architects (submitting firm, design/interior architect) The Davis Companies (developer) Perfido Weiskopf Wagstaff + Goettel (executive architect) Wessling Architects (exterior restoration architect) Atlantic Engineering Services (SE) AHA Consulting Engineers (MEP) Van Duesen & Associates (elevator consultant) Heritage Consulting Group (preservation consultant) Powers & Company (historic preservation) Mascaro Construction (GC).
Details: 666,993 sf. Construction cost: Confidential. Construction time: May 2014 to November 2016. Delivery method: Design-bid-build.
See all of the 2017 Reconstruction Award winners here
Related Stories
Reconstruction Awards | Jan 6, 2021
University of Pennsylvania’s Stemmler Hall forgoes retrofit in favor of complete renovation
The Edward J. Stemmler Hall project has won a Bronze Award in BD+C’s 2020 Reconstruction Awards.
Reconstruction Awards | Dec 29, 2020
The reenvisioned Sazerac House: A delectable cocktail that's just perfect for the Big Easy
The 51,987-sf Sazerac House is an interactive cocktail museum, active distillery, corporate headquarters, and event venue, all under one roof, next to the historic French Quarter of New Orleans.
Reconstruction Awards | Dec 18, 2020
Can converting a landmark office to a clinic raise up a downtrodden Philadelphia neighborhood?
BD+C’s Reconstruction Awards recognize the adaptive reuse of the Kensington Trust building.
Reconstruction Awards | Dec 18, 2020
Spokane Riverfront Park U.S. Pavilion project creates a refreshed gathering place in Spokane
The project has won a Bronze Award in BD+C's 2020 Reconstruction Awards.
Reconstruction Awards | Dec 16, 2020
Voters resuscitate an abandoned high school in northern California
A 2014 bond issue provided financing to seismically stabilize and modernize Historic Alameda High School, a 2020 Silver Reconstruction Award winner.
Reconstruction Awards | Dec 14, 2020
Wyoming Capitol Square renovation project is all about the details
The Wyoming Capitol Square project has won a Gold Award in BD+C's 2020 Reconstruction Awards.
Reconstruction Awards | Dec 12, 2020
A famed dome of a historic glasshouse is revived to its rightful glory
Scaffolding played a critical role in the repair and restoration of the Enid A. Haupt Conservatory’s Palm Dome at the New York Botanical Gardens, a Gold winner of BD&C’s 2020 Reconstruction Awards
Reconstruction Awards | Dec 8, 2020
A synagogue in Toronto is renewed while preserving its history
Holy Blossom Temple is a Platinum winner in BD+C’s 2020 Reconstruction Awards.