Five fire scenarios tested on full-scale mass timber building

Codes and Standards

Five fire scenarios tested on full-scale mass timber building

Results will help inform code changes.


By Peter Fabris, Contributing Editor | July 27, 2017

Pixabay Public Domain

Five full-scale mass timber fire tests in a multi-story apartment building with promising results will be used to inform code changes.

The International Code Council Ad-hoc Committee on Tall Wood Buildings conducted the fire scenarios tested in two one-bedroom apartments constructed using mass timber. The test scenarios included various arrangements of exposed and unexposed cross-laminated timber (CLT) with open doors between living and sleeping areas.

In addition, the tests evaluated automatic sprinkler systems effectiveness. A General Technical Report FPL-GTR-247 on the fire tests will be available from the Forest Products Laboratory in the near future.

One finding after one test was that exposed CLT essentially self-extinguished due to the formation of char that protected the underlying wood. In two tests, sprinklers were able to effectively control the fire.

Related Stories

| Dec 15, 2011

Dayton, Ohio schools saving $2.6 million annually by building to LEED

On average, green schools save about $100,000 a year on operating costs, including energy and water savings.

| Dec 15, 2011

Building to LEED standards can pose new risks for construction workers

Workers on these projects suffer a 24% increase in falls to lower levels during roof work, which researchers attributed to the installation of solar panels, and a few other risks.

| Dec 15, 2011

NRDC charges Maine governor with weakening green wood requirement

The FSC program is administered through the Leadership in Energy and Environmental Design (LEED) and requires wood to be harvested in a sustainable way.

| Dec 15, 2011

Post-tornado, Tuscaloosa seeks to create walkable urban, retail areas

Block sizes initially were limited to a maximum perimeter of 1,750 feet, with no side of the block being longer than 500 feet.

| Dec 15, 2011

Allentown, Pa. city council asked to repeal union-friendly law

The mayor of Allentown, Pa. asked the City Council to repeal a year-old ordinance that forces contractors to hire union workers for large city projects funded with state and federal dollars.

| Dec 13, 2011

LEED-EB outpaces LEED for new construction

The U.S. Green Building Council's (USGBC's) LEED certifications for existing buildings standard is outpacing LEED for new buildings for the first time.

| Dec 13, 2011

Regulators charge pervasive abuse of construction workers in Connecticut

Federal and state regulators say they have uncovered what they call "widespread noncompliance" with minimum wage and overtime laws in Connecticut's construction industry.

| Dec 13, 2011

Philadelphia mayor signs order for project labor agreements

Philadelphia Mayor Michael Nutter signed an executive order establishing project labor agreements for major public works projects in Philadelphia.

| Dec 13, 2011

Improved code requirements for attic ventilation

The Roof Assembly Ventilation Coalition (RAVC) participated in the development of the code.

| Dec 12, 2011

LEED-EB Outpaces LEED for New Construction

The U.S. Green Building Council’s (USGBC’s) LEED certifications for existing buildings standard is outpacing LEED for new buildings for the first time.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021