Griffin Electric completes electrical work at Cary Arts Center

Griffin Electric completes electrical work at Cary Arts Center


By By BD+C Staff | November 14, 2011
Griffin Electric Cary Arts Center fire pump chiller handler elevators
The Griffin Electric team was responsible for replacing the previous electrical service on-site with a 1000A, 480/277V service a

Wayne J. Griffin Electric, Inc. (Griffin Electric) has recently completed the electrical installation work at the new Cary Arts Center, located in Cary, NC. 

Opened this spring, the former Cary Elementary/High School is the site of this new arts center, encompassing 48,000-sf.  A complete renovation of the former learning institution, the updated building includes rooms for classes, studio, rehearsal and performance, plus office space for visual arts, ceramic arts, and performing arts. 

A spacious lobby welcomes visitors and patrons, with an adjacent gallery space.  Also on the main floor is a concession area and 399-seat theater, in addition to three classrooms, which may also be used for lobby overflow. Furthermore, this level has the addition of a fly tower, which allows for theater sets to be built and stored on-site. The lower level of the building includes classrooms for ceramics, wood and fabric shops. The upper level, comprised of five classrooms, also includes rehearsal and conference rooms.

The Griffin Electric team was responsible for replacing the previous electrical service on-site with a 1000A, 480/277V service and providing electrical feeds for a new fire pump chiller, six air-handlers and two elevators.

Additionally, the team installed several new systems including, fire alarm, security and public address, lighting control and lightning protection.  A new state-of-the-art performance lighting system was furnished for the theater and rehearsal rooms, in addition to three new dimmer racks and smart switches within the main control room for the performance lighting system. BD+C

Related Stories

| Oct 1, 2012

Tyco completes separation process, now largest pure-play fire protection and security business

Tyco Integrated Security focused on delivering security solutions to commercial businesses.

| Sep 28, 2012

Seattle is home to first LEED-certified modular radiation center

By using modular construction and strategic site design, RAD Medical Systems built the first radiation center to receive LEED certification.

| Sep 26, 2012

EDITORIAL OPPORTUNITY – BD+C Greenbuild 2012 Issue

Your firm is invited to contribute to this special issue, which will be distributed at Greenbuild San Francisco, Nov. 14-16, 2012.

| Sep 24, 2012

Reed Construction completes Lafarge headquarters in Chicago

Reed Construction was contracted to complete the full third floor build-out which included the construction of new open area work space, private offices, four conference rooms with videoconferencing capabilities and an executive conference boardroom.

| Sep 24, 2012

Chicago Lakeside shortlisted for the Sustainia Award

The “Lakeside Idea” is about bridging a brownfield industrial past to a green lifestyle future, from steel mill to innovation mill.

| Sep 24, 2012

$3.8-million athletic field and track opens in Glen Head, N.Y.

The complex also includes a new, one-story, multi-purpose building that serves as the main entry port to the athletic facilities.

| Sep 21, 2012

AAMA and WDMA release updated review and forecast that predicts industry trends

Significant volume is expected to return to the entry and interior door market as new construction demand is expected to grow at double-digit rates, outpacing remodeling and replacement activity as the housing market recovers.

| Sep 20, 2012

Mid-box retail study shows lack of available sites in Chicago

Existing supply is tight everywhere and almost non-existent in the most attractive zones.

| Sep 20, 2012

Forrester begins construction of freestanding cancer center in Montgomery County, Md.

The new 51,000-square-foot building will include two linear accelerator vaults for radiation equipment.

| Sep 19, 2012

Modular, LEED-Gold Certified Dormitory Accommodates Appalachian State University Growth

By using modular construction, the university was able to open a dorm a full year earlier than a similar dorm built at the same time with traditional construction.

boombox1
boombox2
native1

More In Category


Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.



Libraries

Reasons to reinvent the Midcentury academic library

DLR Group's Interior Design Leader Gretchen Holy, Assoc. IIDA, shares the idea that a designer's responsibility to embrace a library’s history, respect its past, and create an environment that will serve student populations for the next 100 years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021