Guardian Building, Detroit, Mich.

Guardian Building, Detroit, Mich.


By By Robert Cassidy, Editorial Director | October 12, 2010

The relocation and consolidation of hundreds of employees from seven departments of Wayne County, Mich., into the historic Guardian Building in downtown Detroit is a refreshing tale of smart government planning and clever financial management that will benefit taxpayers in the economically distressed region for years to come.

The Guardian Building was designed by Wirt C. Rowland, of Smith Hinchman and Grylls (now SmithGroup) and completed in 1929 as the Union Guardian Building. It combined Native American, Aztec, and Arts & Crafts influences in an inspiring display of Art Deco enthusiasm, with polychromed terra cotta on its exterior, travertine marble from Italy and Numidian marble from Africa on the walls and floors, Monel metal in the ornamental screen in the lobby, custom tiles by Mary Chase Stratton’s Pewabic Pottery, and sculpted architectural reliefs by Corrado Parducci—no wonder people called it “The Cathedral of Finance.” It has been designated a National Historic Landmark.

For two decades, the county had been paying $5.2 million a year in rent for space at 600 Randolph in Detroit—more than $100 million total. Seven years ago, as the lease was running out, the county purchased the Guardian Building (along with another building and a parking structure) for $14 million and bonded another $13.5 million for tenant improvements.

By 2008, with construction costs at favorable levels, the county bonded for another $30 million to change the project scope and accelerate the capital improvement schedule. The Building Team brought the project in at $33,261,000 in construction costs, $11,535,000 (25.7%) below budget.

The HVAC system was upgraded, improving indoor air quality and energy efficiency, and a distributed direct digital controls system was installed, along with video conferencing technology, flat screen monitors for public presentations, electronic faxing to reduce the use of paper, and Voice Over IP, which eliminated 3,500 land lines and will save $500,000 in phone costs.

Instead of shelling out $5.2 million a year at 600 Randolph, plus $1 million at another building, the annual operating costs for the county’s space in the Guardian Building is only $1.9 million. With payment of the debt service, taxpayers will come out $2 million ahead every year—and the county owns a historic building with an estimated current value of $60-100 million. BD+C

PROJECT SUMMARY

Building Team

Owner: Department of Economic Development, Wayne County, Mich.

Submitting firm: SmithGroup (architect, AOR, SE/MEP engineer)

Property manager: Sterling Group

Construction administrator: Hines

General contractor: Sachse Construction/Tooles Contracting Group JV

General Information

Area: 495,600 rentable sf

Construction Cost: $33,261,000

Construction time: September 2008 to December 2009

Delivery method: PM/GC

Related Stories

Codes and Standards | Jul 22, 2022

Hurricane-resistant construction may be greatly undervalued

  New research led by an MIT graduate student at the school’s Concrete Sustainability Hub suggests that the value of buildings constructed to resist wind damage in hurricanes may be significantly underestimated.

School Construction | Jul 22, 2022

School integrating conventional medicine with holistic principles blends building and landscape

Design of the new Alice L. Walton School of Medicine in Bentonville, Ark., aims to blend the building and landscape, creating connections with the surrounding woodlands and the Ozark Mountains.

Market Data | Jul 21, 2022

Architecture Billings Index continues to stabilize but remains healthy

Architecture firms reported increasing demand for design services in June, according to a new report today from The American Institute of Architects (AIA).

Market Data | Jul 21, 2022

Despite deteriorating economic conditions, nonresidential construction spending projected to increase through 2023

Construction spending on buildings is projected to increase just over nine percent this year and another six percent in 2023, according to a new report from the American Institute of Architects (AIA). 

Mixed-Use | Jul 21, 2022

Former Los Angeles Macy’s store converted to mixed-use commercial space

Work to convert the former Westside Pavilion Macy's department store in West Los Angeles to a mixed-use commercial campus recently completed.

Building Team | Jul 20, 2022

San Francisco overtakes Tokyo as the world’s most expensive city for construction

San Francisco has overtaken Tokyo as the world’s most expensive city for construction, according to a new report from Turner & Townsend.

Libraries | Jul 20, 2022

Canada to open one of the world’s largest library and archive facilities

When it opens in 2026, Ādisōke is expected to be one of the largest library and archive facilities in the world. 

Architects | Jul 19, 2022

Perkins Eastman Bolsters Its Dallas Studio with 5 Dynamic New Principals

Seasoned staff bring talent, experience, and enthusiasm to expand firm.

Energy-Efficient Design | Jul 19, 2022

All is not lost: 3 ways architects can respond to the Supreme Court’s EPA ruling

The U.S. Supreme Court’s ruling to limit the Environmental Protection Agency’s power to regulate greenhouse gas (GHG) emissions from power plants dealt a significant blow to our ability to fight the climate crisis with federal policy.

Office Buildings | Jul 19, 2022

Austin adaptive reuse project transforms warehouse site into indoor-outdoor creative office building

Fifth and Tillery, an adaptive reuse project, has revitalized a post-industrial site in East Austin, Texas.

boombox1
boombox2
native1

More In Category


Urban Planning

Bridging the gap: How early architect involvement can revolutionize a city’s capital improvement plans

Capital Improvement Plans (CIPs) typically span three to five years and outline future city projects and their costs. While they set the stage, the design and construction of these projects often extend beyond the CIP window, leading to a disconnect between the initial budget and evolving project scope. This can result in financial shortfalls, forcing cities to cut back on critical project features.



Libraries

Reasons to reinvent the Midcentury academic library

DLR Group's Interior Design Leader Gretchen Holy, Assoc. IIDA, shares the idea that a designer's responsibility to embrace a library’s history, respect its past, and create an environment that will serve student populations for the next 100 years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021