flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

The Hills of Governors Island reach completion one year ahead of schedule

Sports and Recreational Facilities

The Hills of Governors Island reach completion one year ahead of schedule

The man made hills are the latest attraction to open on the island that has been under development since 2006.


By David Malone, Associate Editor | August 22, 2016

Photo courtesy of STV

Rising between 25 and 70 feet above sea level, four man-made hills on the southern tip of New York City’s Governors Island opened to the public in July, one full year ahead of schedule. Dubbed The Hills, the new attraction boasts walking paths, recreational opportunities, and full 360-degree vistas of New York Harbor. And while the Hills offer strong aesthetic value and public space for outdoor activities, they also provide a resiliency measure to protect the island against rising sea levels.

The first phase of construction for the island, which can only be accessed by ferry, was completed in 2014 and consisted of 30 new acres of park and public spaces; an upgrade to Soissons Dock, the only vehicular landing on the island; transfer bridges and approach platforms at the dock; reconstruction of the seawall and the island’s drainage system; restoration of potable water and electrical distribution systems; and stabilization of historic buildings.

As part of a joint venture, STV is providing resident engineering inspection and design review services for the implementation of the Governors Island Park and Public Space Master Plan. In addition to changing 10 acres of flat land into rolling hills that would have Julie Andrews singing like it was 1965, the island’s Master Plan also calls for over 75,000 new plantings, which includes 42,963 shrubs and 2,960 trees.

In creating the hills, STV saved in construction costs by using terraced, mechanically stabilized earth and lightweight fill rather than going the more traditional route using deep soil mixing methods. In addition to the monetary savings, this method also reduced the overall weight on the underground utilities and sea well.

Included in the four hills are Grassy Hill, which is the first to be seen when approaching from the park; Slide Hill, which includes four slides built into the hill itself, including a 57-foot long slide that is the longest in New York City; Outlook Hill, which features “The Scramble,” a shortcut cutting straight up the hill constructed from blocks of granite from the seawall the Army placed in the harbor when they expanded the island in 1905; and Discovery Hill, which features a site-specific work of art from British artist Rachel Whiteread. 

With The Hills completed, the next step of the Master Plan for Governors Island calls for improvements to Picnic Point and the 2.2 mile promenade.

West 8 provided design services for the island’s transformation.

Related Stories

| Mar 1, 2012

Bomel completes design-build parking complex at U.C. San Diego

The $24-million facility, which fits into a canyon setting on the university’s East Campus, includes 1,200 stalls in two adjoining garages and a soccer field on a top level. 

| Feb 24, 2012

Skanska hires Tingle as senior VP and national director for its Sports Center of Excellence

Tingle has worked in the architecture and construction industries for more than 30 years, and for the last 23 years, he has focused primarily on large-scale sports construction projects

| Feb 2, 2012

Shawmut Design and Construction launches sports venues division

Expansion caps year of growth for Shawmut.

| Jan 31, 2012

Fusion Facilities: 8 reasons to consolidate multiple functions under one roof

‘Fusing’ multiple functions into a single building can make it greater than the sum of its parts. The first in a series  on the design and construction of university facilities.

| Nov 29, 2011

SB Architects completes Mission Hills Volcanic Mineral Springs and Spa in China

Mission Hills Volcanic Mineral Springs and Spa is home to the largest natural springs reserve in the region, and measures 950,000 sf.

| Nov 11, 2011

Streamline Design-build with BIM

How construction manager Barton Malow utilized BIM and design-build to deliver a quick turnaround for Georgia Tech’s new practice facility.

| Nov 9, 2011

Sika Sarnafil Roof Recycling Program recognized by Society of Plastics Engineers

Program leads the industry in recovering and recycling roofing membrane into new roofing products.

| Nov 1, 2011

Sasaki expands national sports design studio

Sasaki has also added Stephen Sefton to the sports design studio as senior associate. 

| Oct 20, 2011

UNT receives nation’s first LEED Platinum designation for collegiate stadium

Apogee Stadium will achieve another first in December with the completion of three wind turbines that will feed the electrical grid that powers the stadium.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021