Holt Construction, U.S. Army Corps of Engineers complete temporary hospital in two weeks

Healthcare Facilities

Holt Construction, U.S. Army Corps of Engineers complete temporary hospital in two weeks

The project is located in Paramus, N.J.


By David Malone, Associate Editor | May 5, 2020
BNBMC Temporary Hospital with contractors

All photos courtesy Holt Construction

A new temporary medical facility, comprising two fully-equipped tents, was completed in just two weeks at Bergen New Bridge Medical Center (BNBMC) in Paramus, N.J. The project was built by Holt Construction, the U.S. Army Corps of Engineers, and FEMA.

The hospital is a first of its kind for Army Corps temporary facility construction standards and will serve as a treatment facility for acute, non-COVID related patients due to the influx of COVID-positive patients in the main building. Located in a large parking lot adjacent to BNBMC's main building, the temporary hospital will serve an additional 100 patients in total.

 

BNBMC temporary hospital hallway and patient bays

 

Each tent includes 50 patient beds as well as an admissions bay, nurse stations, six bathrooms with showers, hospital staff nourishment and support areas, a nurse call system in each patient room, medical gas storage, medicine storage, and soiled holding. Life safety provisions, such as fire alarm, sprinkler, fire extinguishers, and other life-safety systems, were also installed. Plumbing and sprinkler were run from the main building to the lot and new incoming primary power with a stepdown transformer was provided to power the two tents.

 

See Also: Danish hospital is constructed from 24 steel frame modules

 

The tents were constructed by over 80 carpenters, 20 electricians, and 20 plumbers working in three shifts around the clock. Social distancing was enforced at all times and all personnel were equipped with N95 face masks, face shields, gloves, and goggles. Additionally, sanitation stations were set up for use upon entering and exiting the site.

 

BNBMC temporary hospital interior

 

BNBMC temporary hospital exterior power

 

BNBMC Temporary Hospital covered entrance

 

Related Stories

| Jun 6, 2012

KLMK Group awarded contract with Parkland Health & Hospital System in Texas

KLMK will also provide planning guidance in all aspects of the project related to facility activation.

| Jun 1, 2012

New BD+C University Course on Insulated Metal Panels available

By completing this course, you earn 1.0 HSW/SD AIA Learning Units.

| Jun 1, 2012

Ground broken for Children’s Hospital Colorado South Campus

Children’s Hospital Colorado expects to host nearly 80,000 patient visits at the South Campus during its first year.

| Jun 1, 2012

K-State Olathe Innovation Campus receives LEED Silver

Aspects of the design included a curtain wall and punched openings allowing natural light deep into the building, regional materials were used, which minimized the need for heavy hauling, and much of the final material included pre and post-consumer recycled content.

| May 31, 2012

5 military construction trends

Defense spending may be down somewhat, but there’s still plenty of project dollars out there if you know where to look.

| May 29, 2012

Torrance Memorial Medical Center’s pediatric burn patients create their version of new Patient Tower using Legos

McCarthy workers joined the patients, donning construction gear and hard hats, to help with their building efforts.

| May 29, 2012

Reconstruction Awards Entry Information

Download a PDF of the Entry Information at the bottom of this page.

| May 24, 2012

2012 Reconstruction Awards Entry Form

Download a PDF of the Entry Form at the bottom of this page.

| May 23, 2012

New hospitals invest in data centers to manage growth in patient info

Silver Cross became one of the first hospitals to install patient tracking software so families know where a patient is at all times. New communication equipment supports wireless voice and data networks throughout the hospital, providing access to patients and their families while freeing clinicians to use phones and computers where needed instead of based on location.

| May 22, 2012

Batson-Cook names Partin VP of Business Development

Partin joins general contractor from Georgia Hospital Association.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021