The Bank of San Antonio’s reputation for strong relationships and quality service has led to exponential growth. In 2015, they broke ground on a 56,000-square-foot office building to accommodate an increasing number of customers and employees. Their HVAC system requirements included energy efficiency as well as high-quality comfort control. They learned that Variable Refrigerant Flow (VRF) technology from Mitsubishi Electric Cooling & Heating could help them achieve those goals.
Tom Moreno, Executive Vice President of Operations and Technology for Bank of San Antonio, served as the liaison for the bank and oversaw the project. He knew it would be a challenge to find an HVAC system that would meet everyone’s needs. “We were looking for a system that was energy efficient but that could also provide comfort and produce the temperatures that we needed throughout the organization.” Moreno and his team originally planned to install traditional HVAC technology, but with the assistance of local HVAC contractor, Flo-Aire Service Inc., and engineering consultant, Cleary Zimmermann Engineers, they decided to consider VRF.
Moreno discovered that VRF’s ability to zone would allow the bank to offer comfort to every person in the building. “We needed control in the offices, conference rooms, lobby area and other communal spaces in the building. We needed to be able to manage the fluctuation of people.”
Upon a recommendation from their distributor, Moreno selected a Mitsubishi Electric system over a competitive system. Eddie McDuff, vice president Flo-Aire said, “Being the first in the industry, [Mitsubishi Electric] worked out the kinks with their systems, and we really like their products. They’re easy to install and start up, and they also offer a good warranty. We’ve had really good success with them.”
A CITY MULTI® VRF system keeps building occupants comfortable while maintaining impressive energy efficiency.
Since project completion, the VRF system has provided precise comfort control for the building’s occupants. Moreno said, “We like the flexibility and being able to set standardized temperatures throughout the organization. We can lock specific thermostats to control cost, but we can also unlock some thermostats when clients come into conference rooms.”
The VRF system not only keeps the employees comfortable, but it also keeps the bank’s technology safe, and most importantly, cool. Moreno said, “They installed wall hung units in the information technology equipment office, which is essential to operation of the organization. They can’t overheat.”
Moreno commented that the system accomplished the one true goal for the bank – comfort everywhere, at any time. “We’ve liked how we can set the temperature an hour before guests walk in during an event and immediately they can be comfortable. It has been easy to manage and helps us make sure the folks here are comfortable.”
The Bank of San Antonio’s new office space, complete with Mitsubishi Electric VRF, has been a success. Moreno said, “Our clients should get good service, and ensuring that our team is comfortable allows us to fulfill our promise to our clients that they will receive an exceptional experience.”
For more information:
Mitsubishi Electric Cooling & Heating
1-888-979-9686
Related Stories
75 Top Building Products | Dec 16, 2019
101 Top Products for 2019
Building Design+Construction readers and editors select their top building products for the past 12 months in the fourth-annual 101 Top Products report.
75 Top Building Products | Dec 16, 2019
Top Building Systems Products for 2019
FabricAir’s ceiling-hung fabric duct and Ellumi Lighting’s bacteria-killing lights are among the 13 new building systems products to make Building Design+Construction's 2019 101 Top Products report.
Sponsored | Plumbing | Nov 10, 2017
Big ideas in a small space
Tiny house with Viega products finished second in a tiny house competition in California.
University Buildings | Nov 6, 2017
A reconstructed building sets the standard for future rehabs at Cornell
Early AE collaboration played a major role in moving this project forward efficiently.
Codes and Standards | Sep 28, 2017
New tool compares HVAC system efficiency
IAPMO and Hydronics Industry Alliance unveil BEST to evaluate systems in early design phase.
HVAC | Sep 7, 2017
See the Latest HVACR Innovations, Products and Technologies at the Highly-Anticipated 2018 AHR Expo in Chicago
Showcase features hundreds of products and technologies for contractors, engineers, facility managers, OEMs and other HVACR industry professionals.
Sponsored | HVAC | May 15, 2017
Student residences get the PEX hydronic treatment
The Bricker Residence required a retrofit that was designed to have fan coil units located in each of the suites, and a new piping system to supply heating and cooling water in a two-pipe switch-over system.
Sponsored | HVAC | Apr 6, 2017
Viega ProPress shines in SolarCity construction
Buffalo will be the first city to produce the first-ever true solar roof – a roofing product with solar panels built in.
Religious Facilities | Mar 9, 2017
St. Patrick’s Cathedral in NYC launches new geothermal plant
The plant is the first in a series of upgrades planned for 2017 to adapt one of New York’s earliest landmarks.