Industry groups petition for change order reform on federal projects

Codes and Standards

Industry groups petition for change order reform on federal projects

Nine design and construction associations ask for assurance that funds available for additional work.


By Peter Fabris, Contributing Editor | April 6, 2015
Industry groups petition for change order reform on federal projects

Photo: Matti Mattila via Wikimedia Commons

Nine associations representing construction contractors, subcontractors, and design professionals petitioned the Office of Federal Procurement Policy (OFPP) to alter how the office handles change orders.

The groups want the Federal Acquisition Regulation (FAR) amended to "make explicit" that before ordering a change to a construction contract, the contracting officer must assure that funds are available to pay for additional work being ordered.

“Our members are facing increasing numbers of instances in which a Contracting Officer will direct a change in the scope of work on a construction project, lacking funds available to pay for the increased costs being imposed upon the contractor,” the associations wrote in a March 18 letter to OFCPP Administrator Anne Rung.

The groups signing the letter included the Design-Build Institute of America, the American Council of Engineering Companies, the American Subcontractors Association, the Associated General Contractors of America, the Mechanical Contractors Association of America, the National Association of Surety Bond Producers, the National Electrical Contractors Association, the Sheet Metal and Air Conditioning Contractors’ National Association and The Surety & Fidelity Association of America.

They also recommended an amendment that would allow contracting officers to continue to make changes in the work within the general scope of the contract, at any time and without notice to sureties, “but only if funds are available to pay the costs of such changes.”

Related Stories

Smart Buildings | Jul 1, 2024

GSA to invest $80 million on smart building technologies at federal properties

The U.S. General Services Administration (GSA) will invest $80 million from the Inflation Reduction Act (IRA) into smart building technologies within 560 federal buildings. GSA intends to enhance operations through granular controls, expand available reporting with more advanced metering sources, and optimize the operator experience.

Sustainability | Jul 1, 2024

Amazon, JPMorgan Chase among companies collaborating with ILFI to advance carbon verification

Four companies (Amazon, JPMorgan Chase, JLL, and Prologis) are working with the International Living Future Institute to support development of new versions of Zero Carbon Certification.

K-12 Schools | Jul 1, 2024

New guidelines for securing schools and community spaces released by the Door Security and Safety Foundation

The Door Security and Safety Foundation (DSSF), in collaboration with Door and Hardware Institute (DHI), recently released of “Are Your Door Openings Secure?.” The document provides guidelines to equip school administrators, building management personnel, and community leaders with a clear roadmap to create a secure and safe environment. 

Codes and Standards | Jun 27, 2024

Berkeley, Calif., voters will decide whether to tax large buildings with gas hookups

After a court struck down a first-in-the-nation ban on gas hookups in new buildings last year, voters in Berkeley, Calif., will have their say in November on a measure to tax large buildings that use natural gas.

Sustainability | Jun 24, 2024

CBRE to use Climate X platform to help clients calculate climate-related risks

CBRE will use risk analysis platform Climate X to provide climate risk data to commercial renters and property owners. The agreement will help clients calculate climate-related risks and return on investments for retrofits or acquisitions that can boost resiliency.

MFPRO+ News | Jun 24, 2024

‘Yes in God’s Backyard’ movement could create more affordable housing

The so-called “Yes in God’s Backyard” (YIGBY) movement, where houses of worship convert their properties to housing, could help alleviate the serious housing crisis affecting many communities around the country.

Codes | Jun 17, 2024

To avoid lawsuits, contractors and designers need to do more than comply with codes

Climate change is making design and construction more challenging and increasing the potential for lawsuits against building teams, according to insurance experts. Building to code is not enough to reduce liability because codes have not kept up with the rapid climate changes that are making extreme weather more common.

Concrete Technology | Jun 17, 2024

MIT researchers are working on a way to use concrete as an electric battery

Researchers at MIT have developed a concrete mixture that can store electrical energy. The researchers say the mixture of water, cement, and carbon black could be used for building foundations and street paving.

Codes and Standards | Jun 17, 2024

Federal government releases national definition of a zero emissions building

The U.S. Department of Energy has released a new national definition of a zero emissions building. The definition is intended to provide industry guidance to support new and existing commercial and residential buildings to move towards zero emissions across the entire building sector, DOE says.

Green | Jun 11, 2024

Tool helps construction and renovation projects with CalGreen compliance

One Click LCA recently launched a new software tool to help building teams comply with Part 11, Title 24, of the California Code of Regulations—CALGreen. The regulation is the nation’s first state-mandated green building code to include embodied carbon emission control as a mandatory component, effective from July 1, 2024.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021